Progressive Review for the month(s) of : January - 2018,

Showing Page Number : 41 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1229
(New)
170576-Improvement /Widening / Rehabilitation of road from main Hangu thall road (Mamoo Banda to Dallan Gurguri Road (22 Km), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 Line Deptt 349 0 5 5 1.25 0 0 0 - -
January - 2018
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE submitted to P&D on 2/1/2018. Discussed in pre-PDWP. Refered to M&E.
Hangu
1230
(New)
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 Line Deptt 161.2 0 5 5 1.25 0 0 0 - -
January - 2018
Approved in PDWP on 31/01/2018. AA awaited.
Hangu
1231
(New)
170658-Const of internal roads in PK-10, Distt. Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 0 100 100 25 25 25 100 50% 13%
January - 2018
Internal Roads 20 Km - work started.
1232
(New)
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 105.593 0 10 10 2.5 0 0 95.593 9% -
January - 2018
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited.
Charsadda
1233
(New)
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 2.5 0 0 290 3% -
January - 2018
NIT Delayd due to decsion of PDWP regarding procurement as per alloactions. Decsion on summary awaited.
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam
1234
(New)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 0 10 30 30 30 30 140 7% 20%
January - 2018
7 Km - in progress.
1235
(New)
170582-Construction of 10 Km Road in PK-35, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 0 10 7.5 0 0 0 153.7 6% -
January - 2018
Tender opened on 01/11/2017 (4 units). Approval of tender under process. Pre-qualification approval under process (1 unit).
1) BT of Hund Lar Zaida Road 1.20 Km 2) Construction of Babinin Road 1 Km 3) Rehabilitation of Gar Aka Khelk Road 1 Km 4) Rehabilitation of Zaida Bypass Road 3.60 Km 5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1236
(New)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 0 10 7.5 0 0 0 90.03 10% -
January - 2018
Tender from pre-qualified contractors called on 09/01/2018, approval under process.
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
January - 2018
Tender from pre-qualified contractors called on 09/01/2018, approval under process.
1238
(New)
170584-Construction of Ganga Lar Sawaldher Road/Rehabilitation and Improvement of Ganga Lar Swaldher Road (3 Km) PK-29, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 56.4 0 5 5 1.25 0 0 51.4 9% -
January - 2018
Work order issued.
1239
(New)
170661-Rehabilitation of Road from Kandaro Kalay to Asif Kalay (2 KM), Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 20 0 10 12.561 12.561 9.916 9.916 10 50% 50%
January - 2018
RW completed. Sub base in trench both side completed. Pipe culverts in progress. WBM 85% completed.
1240
(New)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 0 0.001 0.001 0 0 0 199.916 0% -
January - 2018
Observation under process. Summary approved to grant waiver from the hiring of consultant and allow C&W Deptt to execute the work on its own.
1241
(New)
170627-Rehabilitation of Karora to Ajmir Road (12Km) District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 150 0 10 10 2.5 0 0 140 7% -
January - 2018
Tender approval under process.
1242
(New)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 199.9 0 5 5 1.25 0 0 0 - -
January - 2018
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants. PC-I/DCE submitted to P&D on 09-01-2018. Pre-PDWP held on 17/01/2018.
1243
(New)
170179-Construction of road from Kuza Bandai to New Cannt Swat (2.40 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 506.12 0 10 10 2.5 0 0 0 - -
January - 2018
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants. PC-I/DCE for Rs.780.270 m submitted to Chief Infra P&D on 23/01/2018. PDWP held on 08/02/2018. Deferred.
1244
(New)
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 174.76 0 10 10 2.5 0 0 164.76 6% -
January - 2018
Land acquisition under process by district administration.
1245
(New)
170568-Construction of 2 Km Bypass Road in Barikot District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 112.9 0 8.814 8.814 2.203 0 0 104.086 8% -
January - 2018
Land acquisition under process by district administration.
1246
(New)
170669-Const/BT of rd from Baryam-Nazarbad, Airport-Mamdhera, Gorra-Tangai Shah,Totanu Bandai, Tangai Cheena,Sigram,Mahak-Narang pura, Venai-Ochrai & Sijban-Sperdar. Reconst. Of rd Kalakaly-Nasrat Chowk,Giga Tangbanr,Bara Bandai-Ghurejo, Shawar Gat- Landysar Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 449.995 0 15 15 15 0 0 434.995 3% -
January - 2018
Tender called on 28/12/2017 (pre-qualification). Evaluation oof pre-qualification of contractors under process. Land acquisition under process. Fianancial bid invited on 15/02/2018.
1247
(New)
170670-Construction of different roads (11 KM) at Tehsil Matta District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 171.995 0 10 10 2.5 0 0 161.995 6% -
January - 2018
Tender called on 03/01/2018 (post-qualification), approval under process. Financail bid approval under process.
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
January - 2018
Work order issued.
1249
(New)
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 157.708 0 10 10 0 0 0 147.708 6% -
January - 2018
Tender approved. Work order under process.
1250
(New)
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 30.617 0 5 5 1.25 0 0 25.617 16% -
January - 2018
Tender opened on 30/11/2017, approval under process.
1251
(New)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 275 0 5 3.75 0 0 0 0 - -
January - 2018
PC-II for Rs.5.50 m approved in DDWP on 18/07/2017. LOA issued to AA Associates JV on 23/11/2017. PC-I/DCE for Rs.335.300 m submitted to P&D
1252
(New)
170579-F/S, Desig / Construction of RCC Bridges a) Qanjobori, b) Kakar Shang, c) Banda Akhoon Zadgan Shari Khwar Alai and Reqpair of Battagram Paimal Road (12 Km), District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 207.147 0 5 3.75 0 0 0 0 - -
January - 2018
PC-II for Rs.3.227 m approved in DDWP on 18/07/2017. LOA issued to AA Associates JV on 23/11/2017. PC-I/DCE submitted to P&D for Rs.277.169 m on 05/01/2018. PDWP held. Aa awaited.
1253
(New)
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 0 0 0 0 - -
January - 2018
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited.
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 1.25 1.25 1.25 45 10% 3%
January - 2018
Work started.
1255
(New)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 1.25 0 0 145 3% -
January - 2018
Financial bid opened on 9/2/2018. appoval Under process.
1256
(New)
170572-Construction of Qalandarabad Bypass Road, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 239.642 0 10 10 2.5 0 0 229.642 4% -
January - 2018
Work order issued.
1257
(New)
170574-BT/PCC Road 25 Km in PK-46, District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 0 5 5 1.25 0 0 245 2% -
January - 2018
Work order issued.
1258
(New)
170626-F/S of Improvement / Widening of road from Kalabagh bazar to Charrain Kalpani (2 Km), Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 1.05 0 1.05 1.05 0 0 0 0 - -
January - 2018
PC-II deffered. PC-I with summary submitted on 15/09/2017 for removal of consultant and change of nomenclature to CA.
1259
(New)
170628-Construction of BT road from Takia Shekhan to Ghora Baz Garan road (5 KM) via Rajoya, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 69.085 0 5 5 0 0 0 0 - -
January - 2018
Approved. AA awaited.
1260
(New)
170182- onstruction of Internal Road, in U/Cs Central, South, North, Rehana, Shah Maqsood, Ali Khan, Darwesh, Pandak, Mankrai, Pind Hashim Khan, Sarai Saleh, Sarai Naimat Khan and Sikanderpura, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 0 10 196.69 196.69 43.8 43.8 390 3% 11%
January - 2018
Work started.
1261
(New)
170183-Construction of a) Makhnial to Kharian Neelan Poto road (9Km) b) Gandian Kamawa Chapra Road (12 Km), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 27.073 27.073 0 0 0 - -
January - 2018
Approved. AA awaited.
1262
(New)
170577-Construction of Thalikot Bridge at Jhari Kass Road, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 10 10 2.5 0 0 0 - -
January - 2018
Pc-I/ /DCE under preparation by Spectra Consultnmt
PK-52
1263
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 119 40 24.2 14.2 14.2 133.2 639.06 20% 17%
January - 2018
Pack-1 (7 Km) - earth work, sub-base, base course in progress. Pack-2 (7 Km) - earth work, culverts in progress. Pack-3 (5.825 Km) - earth work in progress.
1) Package-1 (7 Km) 2) Package-2 (7 Km) 3) Package-3 (5.825 Km)
1264
(OG)
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km).
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 294.598 217 74.598 74.598 55.949 55.949 272.949 3 99% 93%
January - 2018
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress.
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1329.516 446 59.75 36.148 21.211 21.211 467.211 823.766 38% 35%
January - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
1) Package-1 (Gulshan Chowk to Hangu Phatak) 2) Package-2 (Hangu Phatak to Saif CNG) 3) Package-3 (Saif CNG to Jerma Bridge Start Point) 4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1266
(OG)
120282-Improvement and Widening of Road from Mufti Mehmood Flyover to old Budni Bridge upto Wahid Garhi 9 Km on PH S-I i/c reconstruction of old Budhni Bridge District Peshawar.
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 1119.959 469.033 50 30.25 17.75 17.75 486.783 600.926 46% 43%
January - 2018
Bridge completed and opened for traffic. Section-1 (1550 mtr) - asphalt overlay both side completed, drain in progress. Section-2 (1000 mtr)- sub base, aggregate base, RCC pipe culvert completed, asphalt base course, asphalt WC in progress. Financial evauation proposals of bidder opened for balance approach road.
1) 2.5 Kms
1267
(OG)
170186-Reconstruction of bridge at Tauheed Abad, District Peshawar on Peshawar - Naguman of Provincial Highway S-1.
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 130 0 10 8.55 3.55 3.55 3.55 120 8% 3%
January - 2018
PC-I/DCE for Rs.77.559 m and PC-II for Rs.22.860 m approved in DDWP-I on 02/11/2017. Pre-qualification of contractors notified. Tender re-invited due to less participation.
1268
(OG)
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1394 1291.5 30 18.15 10.65 10.65 1302.15 72.5 95% 93%
January - 2018
10/14 Km completed, Dargai bypass (3 Km) in progress.
Package-1 Package-2 Package-3 Package-4 Package-5
1269
(OG)
140621-Dualization of Naguman Shabqadar Section of Provincial Highway S-A, District Charsadda (13 Km).
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1609.96 507 90 62.125 31.95 31.95 538.95 1012.96 37% 33%
January - 2018
Land acquisition in progress. 6 Nos culverts, clearing and grubbing in progress.
Package-1 (Naguman Chowk to Hajizai) Package-2 (Bridge at Km 4+420 and Bridge at Km 4+010 at Hajizai) Package-3 (Hajizai to Ocha Wala) Package-4 (Ocha Wala to Shabqadar Chowk)
1270
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 47.5 40 24.2 14.2 14.2 61.7 1410.519 6% 4%
January - 2018
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
Package-1 (Ghani Khan Road to Munaf Kali) Package-2 (Munaf Kali to Ahmadabad) Package-3 (Ahmadabad to Saro Shah Bridge)
1271
(OG)
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera.
Nowshera
PKHA
30-11--1 30-11--1 - 30-11--1 - 1726.703 1208.499 240 145.2 85.2 85.2 1293.699 278.204 84% 75%
January - 2018
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress.
Package-1 (Malang to Kana Khel) Package-2 (Kana Khel to Sadu Khel) Package-3 (Sadu Khel to Gajo Khel)
1272
(OG)
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner.
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 1017.223 79.871 30 18.15 10.65 10.65 90.521 907.352 11% 9%
January - 2018
Length 25 mtr - diversion, load test pile, pile 16/16, pile cape 3/3, pier shaft 5/5, transum 3/3, abutment A&B, RCC beam 12/12, deck slab 2/2, diaphragm 24/24, RW 44/240 completed. PC-II for Rs.43.750 m approved in DDWP on 19/06/2017 for construction supervision.
Package-1 (Bridge at Tor Warsak Daggar) Package-2 (Swarai Pir Qilla Puran Road)
1273
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 318.69 192.5 30 25.65 10.65 10.65 203.15 96.19 70% 64%
January - 2018
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress.
Package-1 Package-2
1274
(OG)
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 1798.521 1659.087 40 24.2 14.2 14.2 1673.287 99.434 94% 93%
January - 2018
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed.
1) Package-1 Km-0 to 9 (9 Kms) 2) Package-2 Km-9 to 16 (7 Kms) 3) Package-3 Km-17 to 24 (7 Kms) 4) Package-4 Km-24 to 31+797 m (7.8 Kms) 5) Package-5 3 Nos bridges
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 42.35 14.7 14.7 262.2 671.02 32% 27%
January - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
Package-1 (Barawal Bandi to Jan Bati) Package-2 (Jan Bati to Shaltalo) Package-3 (Shaltalo to Marawaro) Package-4 (Marawaro to Shahi Top)
1276
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 344.978 167.5 40 24.2 14.2 14.2 181.7 137.478 60% 53%
January - 2018
Structure/road work in progress.
1277
(OG)
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad.
Abbottabad
PKHA
30-11--1 30-11--1 - 30-11--1 - 983.904 454.5 55 33.4 19.575 19.575 474.075 474.404 52% 48%
January - 2018
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress.
Package-1 Package-2 Package-3
1278
(OG)
140877-Construction of Haripur Bypass Road (23 Km).
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 - 4686.204 1655 120 102.6 72.6 72.6 1727.6 2911.204 38% 37%
January - 2018
Length 23 Km - Pack-1 to 6 work started. Land acquisition payment completed. P&D directed DG M&E to examine revised PC-I and submit recommendations.