Progressive Review for the month(s) of : May - 2018,

Showing Page Number : 6 of 49

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
101
(OG)
GPS Shahidan (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.004 0 0 0 0 2.97 2.97 15.004 - 20%
May - 2018
M4 - flooring and plastering completed in GF and FF. LB - structure completed. Bore well completed.
No Image
101
(OG)
GPS Mardand (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
May - 2018
DEO Charsadda intimated that reconstruction of Mardand school is being carried out through provincial ADP and has suggested reconstruction of GGPS Mian Sahib Ghari.
No Image
101
(OG)
GPS Mansooka (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
May - 2018
M7 - GF slab in progress. LB - footing completed. (previously local dispute).
No Image
101
(OG)
GGPS Samunat (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.194 0 0 0 0 3.7 3.7 18.194 - 20%
May - 2018
M3 - structure, BBM and joinery work completed. Flooring and plastering in progress.
No Image
101
(OG)
GGPS Jhoke Gumla (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
May - 2018
M7 - GF column completed. Slab in progress (previously mutation issue of existing land).
No Image
101
(OG)
GPS No.1 Yarak (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.009 0 0 0 0 0 0 21.009 - -
May - 2018
M7 - column completed in both modules. BBM in progress. BW in progress.
No Image
101
(OG)
GPS Jhoke Umary Wali (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
May - 2018
M7 - plinth beam done. Mutation issue at new site BW completed.
No Image
101
(OG)
GPS Rorra Now (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 1.77 1.77 13.1 - 14%
May - 2018
M7 - plaster work in progress. LB - slab done. Finishing in progress. Bore well completed.
No Image
101
(OG)
GPS Bairoon Sharqi (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
May - 2018
M7 - GF slab done. FF columns in progress. (Previously stay order issue at exisitng land).
No Image
101
(OG)
GPS Makkar (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.739 0 0 0 0 2.07 2.07 18.739 - 11%
May - 2018
M3 - plaster work in progress. LB - slab done. Finishing in progress.
No Image
101
(OG)
GGPS Raidgai (Militancy Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
May - 2018
M3 - excavation completed, ready for lean concrete. LB and dev works - dismantling of BW completed.
No Image
101
(OG)
GHS Maidan Bandai (Militancy Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 48.75 0 0 0 0 2.37 2.37 48.75 - 5%
May - 2018
U-Shape - plinth beam steel cutting in progress. M3 - footing concrete completed. LB - not yet started. Dev works - back side RRM in progress.
No Image
101
(OG)
GGHS Kumbar (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2018
Dropped.
No Image
101
(OG)
GHS Mirgam Bala (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 48.316 0 0 0 0 0.036 0.036 48.316 - 0%
May - 2018
Slow progress. Notice issue.
No Image
101
(OG)
GGMS Kotkay (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.351 0 0 0 0 1.76 1.76 21.351 - 8%
May - 2018
M3 - BB work in foundation in progress. LB - not yet started. Dev work - BW in progress.
No Image
101
(OG)
GHS Sadbar Kalay (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 36.786 0 0 0 0 14.36 14.36 36.786 - 39%
May - 2018
M6 - form work for the parapet wall for mumties in progress. M4 - form work for the parapet wall for mumties in progress. LB - slab casted. Dev works - BW at rear side of modules.
No Image
101
(OG)
GPS Raidgai (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.083 0 0 0 0 0.91 0.91 15.083 - 6%
May - 2018
M7 - form work for GF slab in progress. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GMS Asigi Kalay (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 30.097 0 0 0 0 0.036 0.036 30.097 - 0%
May - 2018
M3 - lean concrect in foundation casted. M7 - footing completed. LB -not yet started. Dev works - not yet started.
No Image
101
(OG)
GPS Maidan Bandai (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 29.994 0 0 0 0 0 0 29.994 - -
May - 2018
Plinth beam in progress.
No Image
101
(OG)
GPS Zaimdara (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 25.064 0 0 0 0 1.25 1.25 25.064 - 5%
May - 2018
T4 - plinth beam casted. T7 - module adjustment issue with commmunity. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GPS No.1 Sherkhanai (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.711 0 0 0 0 1.25 1.25 17.711 - 7%
May - 2018
M4 - GF columns steel cutting and fixing in progress. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GHS Maidan Bandai (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 48.75 0 0 0 0 0 0 48.75 - -
May - 2018
Work order issued.
No Image
101
(OG)
GHS Mian Brangola (Flood Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 60.225 0 0 0 0 0.036 0.036 60.225 - 0%
May - 2018
Steel fabrication in footing completed. Work not yet started due to space limitation.
No Image
101
(OG)
GGPS Gumbatai (Militancy Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
May - 2018
Dropped.
No Image
101
(OG)
GPS Meramai (Militancy Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
May - 2018
Tender floated, no body turned up.
No Image
101
(OG)
GPS Maidan Bandai (Militancy Affected)
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 29.994 0 0 0 0 6.91 6.91 29.994 - 23%
May - 2018
M3 - BB work FF completed. M4 - plinth beam completed. LB - layout given. Dev works - RW, bore well in progress.
No Image
101
(OG)
GPS Nihag (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
May - 2018
T3 - steel fixing for the PB in progress. LB and dev works - work not yet started.
No Image
101
(OG)
GPS Kass Barikot (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
May - 2018
T3 - form work for the GF slab concrete in progress. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GPS Remin Kass (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
May - 2018
T3 - form work for the GF slab concrete is in progress. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GPS Tangisar (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.119 0 0 0 0 1.97 1.97 21.119 - 9%
May - 2018
T3 - GF slab concrete casted and FF columns in progress. LB - not yet started. Dev works - not yet started.
No Image
101
(OG)
GPS Zakria (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 14.643 0 0 0 0 0 0 14.643 - -
May - 2018
T7 - BB work in foundation completed and back filling in progress. LB and dev works - work not yet started.
No Image
101
(OG)
GPS Sundrai (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.339 0 0 0 0 0 0 17.339 - -
May - 2018
T4 - prepartion for the lean concrete in footing. LB and dev works - not yet started.
No Image
101
(OG)
GPS Sundal (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 17.339 0 0 0 0 1.1 1.1 17.339 - 6%
May - 2018
T4 - GF slab formwork in progress. LB and dev works - not yet started.
No Image
101
(OG)
GHS Jan Batti (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 34.496 0 0 0 0 0 0 34.496 - -
May - 2018
T7 - BB work in foundation is completed and brick filling in progress. T13 - BB work in foundation completed and brick filling in progress. LB and dev works - work not yet started.
No Image
101
(OG)
GPS Shomnai (Flood Affected)
Dir Upper
30-11--1 30-11--1 - 30-11--1 Line Deptt 22.643 0 0 0 0 0 0 22.643 - -
May - 2018
Tender floated but No body turned-up.
No Image
101
(OG)
GPS Hisar Baba (Flood Affected)
Malakand
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.864 0 0 0 0 5.35 5.35 21.864 - 24%
May - 2018
M1 - long columns is completed. LB - not yet started. Dev works - RW right and left side has been completed.
No Image
101
(OG)
GPS Jalal Kot (Flood Affected)
Malakand
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.083 0 0 0 0 3.35 3.35 15.083 - 22%
May - 2018
M7 - brick work and plaster in GF and FF completed. Marble fixing completed. Electrical wiring is in progress. LB - brick work in super structure completed. Form work for beams and slab is in progress. Dev works - no activity is in progress.
No Image
101
(OG)
GHS Inzergai (Flood Affected)
Malakand
30-11--1 30-11--1 - 30-11--1 Line Deptt 33.537 0 0 0 0 1.79 1.79 33.537 - 5%
May - 2018
M4 - BB work in GF has been completed. Steel cutting for roof beam and slab is in progress. M11 - excavation in foundation is completed. LB and Dev works - M4 front side RW in progress and BW RRM has been completed.
No Image
101
(OG)
GPS Sherin Kotai (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 33.309 0 0 0 0 11.22 11.22 33.309 - 34%
May - 2018
Both M13 modules structure and BBM completed. Plastering and flooring in progress.
No Image
101
(OG)
GPS Shahab Khel Kaka Sahib (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 1.25 1.25 12.719 - 10%
May - 2018
M7 - FF slab completed. BBM work completed. Flooring and plastering work in progress.
No Image
101
(OG)
GPS Bab-e-Jadeed (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 8.725 0 0 0 0 1.72 1.72 8.725 - 20%
May - 2018
M7 - FF columns completed. BBM work in progress. FF slab in progress.
No Image
101
(OG)
GPS Kandi Tazaden (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.882 0 0 0 0 3.66 3.66 21.882 - 17%
May - 2018
M13 - flooring in progress. LB- finishing in progress. Bore well completed.
No Image
101
(OG)
GPS Tor Dherai (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 1.41 1.41 12.719 - 11%
May - 2018
M7 - FF columns completed. FF slab in progress. Dev bore well completed.
No Image
101
(OG)
GHSS Akbarpura (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 146.34 0 0 0 0 0 0 146.34 - -
May - 2018
Dismantling in progress. Work started.
No Image
101
(OG)
GGPS Pashtoon Garhi (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.938 0 0 0 0 3.28 3.28 15.938 - 21%
May - 2018
M13 - flooring in progress. Joinery and electrical work in progress.
No Image
101
(OG)
GGPS Maroba Nizampur (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.882 0 0 0 0 2.94 2.94 21.882 - 13%
May - 2018
M13 - GF columns and slab completed. Bore well completed.
No Image
101
(OG)
GPS No.1 Mishak (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.882 0 0 0 0 1.94 1.94 21.882 - 9%
May - 2018
M13 - FF columns completed. BBM in progress. Bore well completed.
No Image
101
(OG)
GPS No.1 Kotarpan (Flood Affected)
Nowshera
30-11--1 30-11--1 - 30-11--1 Line Deptt 19.172 0 0 0 0 2.12 2.12 19.172 - 11%
May - 2018
M13 - FF columns completed. FF slab in progress. LB - excavation done.
No Image
101
(OG)
120842-Establishment of Project Unit for PaRRSA/PDMA for USAID Projects in C&W Department.
Provincial
30-11--1 30-11--1 - 30-11--1 - 166.6 89.75 30.562 120.3 120.3 103.148 192.898 46.288 72% 100%
May - 2018
Work in progress.
No Image
101
(OG)
GGPS Qambari (Flood Affected)
Shangla
30-11--1 30-11--1 - 30-11--1 Line Deptt 16.085 0 0 0 0 0.04 0.04 16.085 - 0%
May - 2018
Excavation completed, work started.
No Image