Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : April - 2017,

Showing Page Number : 45 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
88224
(OG)
GPS Jhoke Umary Wali (Flood Affected)
D.I.Khan
04-11-06 - - - Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
April - 2017
Plinth beam in progress. Mutation issue at new site.
88225
(OG)
GPS No.1 Yarak (Flood Affected)
D.I.Khan
28-11-16 - - - Line Deptt 21.009 0 0 0 0 0 0 21.009 - -
April - 2017
Plinth beam, RW in progress.
88226
(OG)
GGPS Jhoke Gumla (Flood Affected)
D.I.Khan
01-12-16 - - - Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
April - 2017
Plinth in progress. (previously mutation issue of existing land).
88331
(OG)
GHS Maidan Bandai (Flood Affected)
Dir Lower
14-10-16 - - - Line Deptt 48.75 0 0 0 0 0 0 48.75 - -
April - 2017
Work order issued.
88332
(OG)
GPS Maidan Bandai (Flood Affected)
Dir Lower
08-08-16 - - - Line Deptt 29.994 0 0 0 0 0 0 29.994 - -
April - 2017
Plinth beam in progress.
88333
(OG)
GMS Asigi Kalay (Flood Affected)
Dir Lower
12-08-16 - - - Line Deptt 30.097 0 0 0 0 0.036 0.036 30.097 - 0%
April - 2017
M3 - lean concrect in foundation casted. M7 - footing completed. LB -not yet started. Dev works - not yet started.
88334
(OG)
GPS No.1 Sherkhanai (Flood Affected)
Dir Lower
12-10-16 - - - Line Deptt 17.711 0 0 0 0 1.25 1.25 17.711 - 7%
April - 2017
M4 - BB work in foundation completed. LB - not yet started. Dev works - not yet started.
88335
(OG)
GPS Raidgai (Flood Affected)
Dir Lower
15-12-16 - - - Line Deptt 15.083 0 0 0 0 0.91 0.91 15.083 - 6%
April - 2017
M7 - BB work in foundation completed, plinth beam steel in progress. LB - not yet started. Dev works - not yet started.
88336
(OG)
GHS Sadbar Kalay (Flood Affected)
Dir Lower
16-08-16 - - - Line Deptt 36.786 0 0 0 0 14.36 14.36 36.786 - 39%
April - 2017
M6 - form work for the parapet wall for mumties in progress. M4 - form work for the parapet wall for mumties in progress. LB - slab casted. Dev works - BW at rear side of modules.
88337
(OG)
GGMS Kotkay (Flood Affected)
Dir Lower
08-12-16 - - - Line Deptt 21.351 0 0 0 0 1.76 1.76 21.351 - 8%
April - 2017
M3 - BB work in foundation in progress. LB - not yet started. Dev work - BW in progress.
88338
(OG)
GHS Mirgam Bala (Flood Affected)
Dir Lower
08-11-16 - - - Line Deptt 48.316 0 0 0 0 0.036 0.036 48.316 - 0%
April - 2017
Slow progress. Notice issue.
88339
(OG)
GPS Zaimdara (Flood Affected)
Dir Lower
08-11-16 - - - Line Deptt 25.064 0 0 0 0 1.25 1.25 25.064 - 5%
April - 2017
T4 - plinth beam casted. T7 - module adjustment issue with commmunity. LB - not yet started. Dev works - not yet started.
88340
(OG)
GGHS Kumbar (Flood Affected)
Dir Lower
- - - - Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2017
Dropped.
88340
(OG)
GHS Mian Brangola (Flood Affected)
Dir Lower
13-10-16 - - - Line Deptt 60.225 0 0 0 0 0.036 0.036 60.225 - 0%
April - 2017
Steel fabrication in footing completed. Work not yet started due to space limitation.
88511
(OG)
GPS Shomnai (Flood Affected)
Dir Upper
- - - - Line Deptt 22.643 0 0 0 0 0 0 22.643 - -
April - 2017
Tender floated but No body turned-up.
88512
(OG)
GHS Jan Batti (Flood Affected)
Dir Upper
08-11-16 - - - Line Deptt 34.496 0 0 0 0 0 0 34.496 - -
April - 2017
T7 - footing coneret completed. T13 - steel fixing in footing is in progress. LB and Dev works - not yet started.
88513
(OG)
GPS Sundal (Flood Affected)
Dir Upper
08-11-16 - - - Line Deptt 17.339 0 0 0 0 1.1 1.1 17.339 - 6%
April - 2017
T4 - Fabricatin of MS in progress. LB and Dev works - nick columns completed.
88514
(OG)
GPS Sundrai (Flood Affected)
Dir Upper
- - - - Line Deptt 17.339 0 0 0 0 0 0 17.339 - -
April - 2017
Dismantling completed. Excavation in foundation in progress.
88515
(OG)
GPS Nihag (Flood Affected)
Dir Upper
07-11-16 - - - Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
April - 2017
T3 - neck columns completed. LB and Dev works - not yet started.
88516
(OG)
GPS Zakria (Flood Affected)
Dir Upper
07-11-16 - - - Line Deptt 14.643 0 0 0 0 0 0 14.643 - -
April - 2017
T7 - steel cutting for footing is in progress. LB and Dev works - not yet started.
88517
(OG)
GPS Tangisar (Flood Affected)
Dir Upper
28-10-16 - - - Line Deptt 21.119 0 0 0 0 1.97 1.97 21.119 - 9%
April - 2017
T3 - GF columns concrete poured. LB and Dev works - not yet started.
88518
(OG)
GPS Remin Kass (Flood Affected)
Dir Upper
28-10-16 - - - Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
April - 2017
T3 - neck columns in progress. LB - nt yet started. Dev works - not yet started.
88519
(OG)
GPS Kass Barikot (Flood Affected)
Dir Upper
28-10-16 - - - Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
April - 2017
T3 - BB work in foundation in progress. LB - not yet started. Dev works - not yet started.
88611
(OG)
GPS Hisar Baba (Flood Affected)
Malakand
15-08-16 - - - Line Deptt 21.864 0 0 0 0 5.35 5.35 21.864 - 24%
April - 2017
M1 - long columns is completed. LB - not yet started. Dev works - RW right and left side has been completed.
88612
(OG)
GHS Inzergai (Flood Affected)
Malakand
24-11-16 - - - Line Deptt 33.537 0 0 0 0 1.79 1.79 33.537 - 5%
April - 2017
M4 - BB work in GF has been completed. Steel cutting for roof beam and slab is in progress. M11 - excavation in foundation is completed. LB and Dev works - M4 front side RW in progress and BW RRM has been completed.
88613
(OG)
GPS Jalal Kot (Flood Affected)
Malakand
15-08-16 - - - Line Deptt 15.083 0 0 0 0 3.35 3.35 15.083 - 22%
April - 2017
M7 - mumty slab and parafit wall concrete poured. LB - long columns in progress. Dev works - not yet started.
88711
(OG)
GPS No.1 Mishak (Flood Affected)
Nowshera
23-08-16 - - - Line Deptt 21.882 0 0 0 0 1.94 1.94 21.882 - 9%
April - 2017
Slab in progress.
88712
(OG)
GGPS Maroba Nizampur (Flood Affected)
Nowshera
20-08-16 - - - Line Deptt 21.882 0 0 0 0 2.94 2.94 21.882 - 13%
April - 2017
Plinth beam done.
88713
(OG)
GGPS Pashtoon Garhi (Flood Affected)
Nowshera
01-09-16 - - - Line Deptt 15.938 0 0 0 0 3.28 3.28 15.938 - 21%
April - 2017
Flooring in progress. Electrical work in progress. BW completed.
88714
(OG)
GPS Kandi Tazaden (Flood Affected)
Nowshera
28-08-16 - - - Line Deptt 21.882 0 0 0 0 3.66 3.66 21.882 - 17%
April - 2017
Flooring in progress. Electrical work in progress.
88715
(OG)
GPS Bab-e-Jadeed (Flood Affected)
Nowshera
02-10-16 - - - Line Deptt 8.725 0 0 0 0 1.72 1.72 8.725 - 20%
April - 2017
Slab in progress.
88716
(OG)
GPS No.1 Kotarpan (Flood Affected)
Nowshera
16-10-16 - - - Line Deptt 19.172 0 0 0 0 2.12 2.12 19.172 - 11%
April - 2017
GF slab completed. LB excavation done.
88717
(OG)
GPS Tor Dherai (Flood Affected)
Nowshera
03-09-16 - - - Line Deptt 12.719 0 0 0 0 1.41 1.41 12.719 - 11%
April - 2017
GF slab completed.
88718
(OG)
GPS Sherin Kotai (Flood Affected)
Nowshera
18-08-16 - - - Line Deptt 33.309 0 0 0 0 11.22 11.22 33.309 - 34%
April - 2017
M13 both modules structure, BBM completed. Plaster in progress.
88719
(OG)
GPS Shahab Khel Kaka Sahib (Flood Affected)
Nowshera
29-08-16 - - - Line Deptt 12.719 0 0 0 0 1.25 1.25 12.719 - 10%
April - 2017
GF slab, FF columns completed, BBM work in progress.
88719
(OG)
GHSS Akbarpura (Flood Affected)
Nowshera
26-07-16 - - - Line Deptt 146.34 0 0 0 0 0 0 146.34 - -
April - 2017
Dismentling done. Drawing issued on 08/05/2017.
88719
(OG)
Package No.1 (Flood Affected) Tehsil Complex Kabal Swat
Swat
- - - - Line Deptt 110.239 0 0 0 0 0 0 110.239 - -
April - 2017
Structural design finalized, electrical works and sewerage design finalized.
88719
(OG)
Package No.2 (Flood Affected) Tehsil Complex Kabal Swat
Swat
- - - - Line Deptt 132.576 0 0 0 0 0 0 132.576 - -
April - 2017
Structural design finalized, electrical works and sewerage design finalized residential quarters layout given.
88811
(OG)
GHS Amnavi (Flood Affected)
Shangla
28-11-16 - - - Line Deptt 51.392 0 0 0 0 0 0 51.392 - -
April - 2017
T3, T6 - no other activity due to snow bond area. T11, LB aand Dev works - not yet started.
88812
(OG)
GGPS Begumar Lahore (Flood Affected)
Shangla
28-07-16 - - - Line Deptt 18.78 0 0 0 0 1.09 1.09 18.78 - 6%
April - 2017
T4 - plinth beam casted. LB and Dev works - not yet started.
88813
(OG)
GMS Bilkanai (Flood Affected)
Shangla
20-07-16 - - - Line Deptt 26.97 0 0 0 0 1.39 1.39 26.97 - 5%
April - 2017
T7 - plinth beam concrete poured and back fill is in progress. T4 - excavation is in progress. LB and Dev works - not yet started.
88814
(OG)
GGPS Shalmano Chakasar (Flood Affected)
Shangla
25-07-16 - - - Line Deptt 18.78 0 0 0 0 0 0 18.78 - -
April - 2017
T4 - excavation in foundation completed. LB - no activity found in the reporting period. Dev works - RW of front and back side has been completed.
88815
(OG)
GHS Shang (Flood Affected)
Shangla
28-11-16 - - - Line Deptt 62.528 0 0 0 0 1.05 1.05 62.528 - 2%
April - 2017
T3 - lean concrete completed. T6 - plinth beam steel fabrication has been completed. T4 and T11 - not yet started. LB and Dev works - not yet started.
88816
(OG)
GGPS Shalmano Kotkai (Flood Affected)
Shangla
20-09-16 - - - Line Deptt 22.56 0 0 0 0 0.045 0.045 22.56 - 0%
April - 2017
T3 - no activity found in the reporting period. LB - not yet started.
88817
(OG)
GGPS Qambari (Flood Affected)
Shangla
24-10-16 - - - Line Deptt 16.085 0 0 0 0 0.04 0.04 16.085 - 0%
April - 2017
Site levelling and dressing completed. Layout given.
88911
(OG)
GGPS Bara Bandai (Flood Affected)
Swat
06-09-16 - - - Line Deptt 15.263 0 0 0 0 0.035 0.035 15.263 - 0%
April - 2017
M13 - footing concrete completed. LB & Dev works - no activity.
88912
(OG)
GPS Muraday (Flood Affected)
Swat
17-09-16 - - - Line Deptt 20.735 0 0 0 0 1.48 1.48 20.735 - 7%
April - 2017
T3 - BW in progress, neck columns and BB work in foundation completed. LB - not yet started. Dev works - not yet started.
88913
(OG)
GGPS Serai Gut (Flood Affected)
Swat
03-10-16 - - - Line Deptt 20.735 0 0 0 0 1.84 1.84 20.735 - 9%
April - 2017
No activity in the reporting period, notice issued.
88914
(OG)
GGMS Laikho Qayum Abad (Flood Affected)
Swat
29-07-16 - - - Line Deptt 14.377 0 0 0 0 3.31 3.31 14.377 - 23%
April - 2017
T4 - gable wall in progress. FF BB in progress. LB and Dev Works - nNot yet started.
88915
(OG)
GPS Biha (Flood Affected)
Swat
26-09-16 - - - Line Deptt 25.064 0 0 0 0 5.12 5.12 25.064 - 20%
April - 2017
T7 - plinth beam casted. LB - not yet started. Dev works - no activity found in the reporting period.
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46