Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : November - 2016,

Showing Page Number : 24 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Dir Upper
- - - 14-04-15 - 10 0 0 0 0 0 0 10 - -
November - 2016
Consultant selected. PC-I/DCE to be resubmitted to HE.
1) GGDC Bandi Tehsil Barawal
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Karak
- - - 14-04-15 - 0 0 0 0 0 0 0 0 - -
November - 2016
Site acquisation under progress. PC-II approved. Consultant selected. PC-I/DCE for Rs.425.012 m submitted to Director Colleges on 15/12/2015.
1) GGDC Latamber PK-41
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Kohat
- - - 14-04-15 - 237.727 0 20 20 20 0 0 217.727 8% -
November - 2016
Admin block, academic block, cafetaria, BW in progress.
1) GDC Shakardara Kohat
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Mardan
- - - 14-04-15 - 244.525 8.505 30 30 30 0 8.505 206.02 16% 3%
November - 2016
Work in progress.
1) GGDC Gujrat Mardan PK-30
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Nowshera
- - - 14-04-15 - 20 3.901 39 39 39 0 3.901 0 100% 20%
November - 2016
Out of 2 units, 1 work order issued, site demarcation awaited (GDC Manki Sharif PK-13), 1 financial bid evaluation under process (GGDC Nowshera PK-15).
1) GDC Manki Sharif PK-13
2) GGDC Nowshera PK-15
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Provincial
- - - 14-04-15 - 2500 12.406 200 200 0 0 12.406 0 - -
November - 2016
524
(OG)
140589-Establishment of 10 Govt. Colleges in Khyber Pakhtunkhwa.
Swabi
- - - 14-04-15 - 10 0 0 0 0 0 0 10 - -
November - 2016
PC-I/DCDE approved. AA awaited.
1) GDC Swabi PK-32
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Abbottabad
01-06-15 30-06-16 - 23-12-14 - 17.24 9.24 7.625 7.625 3 0 9.24 0.375 98% 54%
November - 2016
Out of 3 units, 2 in progress, 1 revised PC-I submitted to CPO HE Deptt.
GGDC No.1 Abbottabad (tube well, boundary wall)
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Battagram
21-04-15 30-06-16 - 23-12-14 - 14.18 14.18 0 0 0 0 14.18 0 - 100%
November - 2016
Completed (2 units).
1) GGDC Battagram (boundary wall)
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Karak
16-06-15 30-06-16 - 23-12-14 - 10.8 11.165 0.323 0.323 0.323 0 11.165 0 100% 100%
November - 2016
Completed & H/O (2 units).
1) GDC BD Shah
2) GDC Ahmad Abad
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Lakki Marwat
23-04-15 30-06-16 - 23-12-14 - 5.122 5.615 0 0 0 0 5.615 0 - 100%
November - 2016
Completed & H/O (2 units).
1) GDC Ghazni Khel PK-75
2) GGDC Lakki Marwat PK-76
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Mansehra
- 30-06-16 - 23-12-14 - 19.381 19.85 0 0 0 0 19.85 0 - 100%
November - 2016
Out of 3 units, 2 completed, 1 in progress.
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Nowshera
02-10-15 30-06-16 - 23-12-14 - 14.172 16.362 0 0 0 0 16.362 0 - 100%
November - 2016
Completed.
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Provincial
- 30-06-17 - 23-12-14 - 87.625 82.387 0 0 0 0 82.387 0 - -
November - 2016
526
(OG)
140715-Construction / Re-Construction of boundary walls and provision of water supply to Govt Colleges in Khyber Pakhtunkhwa.
Swat
- 30-06-16 - 23-12-14 - 6.73 5.975 0 0 0 0 5.975 0.755 - 89%
November - 2016
Completed & H/O.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Abbottabad
- - - 11-03-16 - 250 4.5 10.276 10.276 10.276 5.276 9.776 235.224 6% 4%
November - 2016
4 units - 2 in progress, 1 work order issued, 1 financial bid opened on 23/09/2016.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Bannu
- - - 11-03-16 - 16.93 0 12.961 12.961 12.961 6.319 6.319 3.969 77% 37%
November - 2016
FF in progress.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Charsadda
- - - 11-03-16 - 4.057 1.2 2.638 2.638 2.638 0.524 1.724 0.219 95% 42%
November - 2016
Finishing in progress.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
D.I.Khan
- - - 11-03-16 - 14.057 0 1.319 1.319 1.319 0 0 12.738 9% -
November - 2016
Work order issued. Occupied by Pak Army.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Dir Lower
- - - 11-03-16 - 14.4 0 7.319 7.319 7.319 1.319 1.319 7.081 51% 9%
November - 2016
Work in progress.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Haripur
- - - 11-03-16 - 0 0 5.276 5.276 5.276 0 0 0 - -
November - 2016
Work started.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Lakki Marwat
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE submitted to P&D on 13/10/2015.
1) GDC Ghazni Khel (Group Latrin) PK-75
2) GDC Tajori (50 staff/student hostels, boring of tube well)
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Malakand
- - - 11-03-16 - 28.774 0 1.319 1.319 1.319 0 0 27.455 5% -
November - 2016
Excavation in progress.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Mansehra
- - - 11-03-16 - 39.496 1.5 7.319 7.319 7.319 1.319 2.819 30.677 22% 7%
November - 2016
DPC level.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Mardan
- - - 11-03-16 - 15.112 0 0 0 0 0 0 15.112 - -
November - 2016
Tender opened on 07/11/2016. Technical evaluation approval under process.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Peshawar
BD-2
- - - 11-03-16 - 3 0 1.32 1.32 1.32 0 0 1.68 44% -
November - 2016
AA received. Financial bid opened on 02/11/2016.
527
(OG)
150024-Construction of additional acedamic infrastructure in Govt colleges.
Provincial
- - - 11-03-16 - 244.242 7.2 100.242 100.242 0 0 7.2 0 - -
November - 2016
PC-I/DCE submitted.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Buner
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE for Rs.367.272 m submitted to CPO HE Deptt on 19/09/2016.
Establishment of Degree College for Girls at UC Chalbandai
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Charsadda
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
Acquisition of land under process by HE Deptt.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Chitral
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE for Rs.374 m re-submitted according to rev scope of work.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
D.I.Khan
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-II for Rs.26.082 m submitted to CPO HE Deptt on 16/11/2015. Purchase of land under process by HE deptt.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Dir Lower
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
Out of 2 units, 1 technical evaluation under process, 1 site not H/O.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Dir Upper
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE under preparation. Site not H/O.
Farid Khan College , Patrak Kalkot
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Lakki Marwat
- - - 11-03-16 - 255.271 0 0 0 0 0 0 255.271 - -
November - 2016
Approved. AA awaited. NIT floated.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Provincial
- - - 11-03-16 - 5400 0 210 210 0 0 0 0 - -
November - 2016
PC-I/DCE submitted.
528
(OG)
150031-Establishment of Government Degree Colleges in Khyber Pakhtunkhwa on need basis.
Swat
- - - 11-03-16 - 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE under preparation.
1) GDC (Boys) Kanju
2) GDC Matta
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Abbottabad
- 30-06-17 - - Line Deptt 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE submitted to CPO HE Deptt on 30/07/2015. Dropped in DDWP on 09/2015.
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Battagram
- 30-06-17 - - Line Deptt 12 0 0 0 0 0 0 12 - -
November - 2016
20% work completed.
1) GDC Battagram
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Charsadda
- 30-06-17 - - Line Deptt 3.12 2.439 0 0 0 0 2.439 0.681 - 78%
November - 2016
Completed.
1) GDC Tangi Charsadda
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Haripur
- 30-06-17 - - Line Deptt 0.351 0 0 0 0 0 0 0.351 - -
November - 2016
1) GGDC Mankari Haripur
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Karak
12-04-16 30-06-17 - - Line Deptt 10.063 10.063 0 0 0 0 10.063 0 - 100%
November - 2016
Completed & H/O.
1) GDC Banda Daud Shah Karak
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Kohat
20-05-16 30-06-17 - - Line Deptt 8.26 8.26 6.897 6.897 6.897 0 8.26 0 100% 100%
November - 2016
Completed.
1) GDC Lachi Kohat
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Lakki Marwat
- 30-06-17 - - Line Deptt 0 0 0 0 0 0 0 0 - -
November - 2016
PC-I/DCE submitted to CPO HE Peshawar on 02/10/2015.
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Mansehra
- 30-06-17 - - Line Deptt 13.652 9.309 0 0 0 0 9.309 4.343 - 68%
November - 2016
Completed.
1) GDC Balakot Mansehra
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Mardan
- 30-06-17 - - Line Deptt 6.897 2 0 0 0 0 2 4.897 - 29%
November - 2016
Work in progress.
1) GDC Toru Mardan
530
(OG)
150036-Construction / repair / embracement of Boundary walls, main gates, guard room and security pickets etc in Govt colleges.
Provincial
- 30-06-17 - - Line Deptt 50 32.072 6.897 6.897 0 0 32.072 0 - -
November - 2016
531
(OG)
150037-Repair of the buildings of Govt. Colleges in Khyber Pakhtunkhwa through college council.
Provincial
- - - 07-08-15 - 50 0 50 50 0 0 0 0 - -
November - 2016
534
(New)
150028-Strengthening of Govt. Postgraduate Jehanzeb College Swat.
Swat
- - - - Line Deptt 70 0 10 10 0 0 0 0 - -
November - 2016
Rev DCE for Rs.380 m cleared in PDWP. Summary for enhancement of cost and change of nomenclature submitted to CA.
535
(New)
150034-Construction of building for Directorate of Higher Education.
Peshawar
BD-2
- - - - Line Deptt 150 0 10 10 0 0 0 0 - -
November - 2016
PC-I/DCE submitted to client deptt. PDWP to be held on 02/12/2016.
536
(New)
150035-Establishment of building for HETTA.
Peshawar
BD-2
- - - - Line Deptt 250 0 10 10 0 0 0 0 - -
November - 2016
Site/scope of work awaited.
PK-05
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43