Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : March - 2018,

Showing Page Number : 42 of 48

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1228
(New)
170571-Improvement / Rehabilitation of Black Topped road from Gurguri Bypass road to Manji Khel via Gurguri Bazar Tehsil Banda Daud Shah PK-40 (205 Km), District Karak.
Karak
30-11--1 30-11--1 - 30-11--1 - 42.134 0 5 5 5 1.25 1.25 37.134 12% 3%
March - 2018
Length 2.51 Km (width -12 ft ) - work strated.
No Image
Karak
1229
(New)
170576-Improvement /Widening / Rehabilitation of road from main Hangu thall road (Mamoo Banda to Dallan Gurguri Road (22 Km), District Hangu.
Hangu
30-11--1 30-11--1 - 30-11--1 Line Deptt 349 0 5 5 1.25 0 0 0 - -
March - 2018
PC-II for Rs.6.980 m approved on 10/08/2017. LOA issued to AA Associates. PC-I/DCE submitted to P&D on 2/1/2018. Discussed in PDWp on 8/3/2018. Deffered.
No Image
Hangu
1230
(New)
170578-F/S, Design & Construction of / Improvement of Hangu Samana Main Road (7 K m) District Hangu (Phase-II).
Hangu
30-11--1 30-11--1 - 30-11--1 - 184.122 0 5 5 1.25 0 0 179.122 3% -
March - 2018
Tender floated, opening on 15/03/2018. Financial bid opened on 29/03/2018, approval under process.
No Image
Hangu
1231
(New)
170658-Const of internal roads in PK-10, Distt. Peshawar.
Peshawar
HW
30-11--1 30-11--1 - 30-11--1 - 200 0 100 100 75 54.59 54.59 100 50% 27%
March - 2018
Internal roads 20 Km - sub base completed, base course and structure work in progress.
No Image
1) Construction of road from Jazz Tower Imdad Mir Koroona Talatan Ghalib Khel road and link road to BHU Ghali Khel 2.30 Km
2) Construction of road from Aza Khel to Naak Band 3 Km
3) Rehabilitation of road from Nawab Chowk Khanow UC Sherkara 2.90 Km
4) Construction of Sam No.1 road taking off from Zangali Canal to GPS Garhi Ghulam Muhammad 2.80 Km
5) Construction of Garhi Mumtaz road taking off from Hazar Khwani Canal 2 Km
6) Rehabilitation/construction of Kulu Daag Lara road at Badabera 2 Km
7) Improvement/rehabilitation of Ghaz Chowk to Rural Health Center Aza Khel Village 1 Km
8) Construction of road from Banat Kalay to Major House Mair Surizai 1.20 Km
1232
(New)
170580-Construction of roads in PK-17 a) 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,b) 2 Km road from Nowshera to Karoona UC Dheri Zardad, c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 105.593 0 10 18.963 18.963 0 0 95.593 9% -
March - 2018
3 units - Length 7.5 Km - width 24 ft. Earth Work in progress
No Image
a. 205 Km road from Mill Pump Nowshera to Sattibad UC Mera Pang,
b) 2 Km road from Nowshera to Karoona UC Dheri Zardad,
c) 2.5 Km road from Prang Majokay to faqir abad Majokay MC-II,
1233
(New)
170659-Consruction, Rehabilitation, Black Topping of Roads / PCC Roads Drain Culverts Retainingwall, Ucs Sherpao, Ziam, Abazai, Katozai, Battagram, Kangra, Daulat Pura, Hassanzai, Mirza Dher, Tangi, Mandani, Nisatta, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 300 0 10 10 2.5 0 0 290 3% -
March - 2018
19 units (PCC) - work order issued.
No Image
1) UC Abazai
2) UC Battagram
3) UC Kangra and UC Daulat Pura
4) UC Hassanzai and UC Katozai
5) UC Mandani
6) UC Nisatta
7) UC Sherpao
8) UC Tangi
9) UC Ziam
1234
(New)
170581-Construction of Army Camp Koroona Sartaj Abad Akora Khattak road (1 KM) and village Khawrai Jehangira Abad, District Nowshera.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 150 0 10 60 60 41.697 41.697 140 7% 28%
March - 2018
7 Km - in progress.
No Image
Nowshera
1235
(New)
170582-Construction of 10 Km Road in PK-35, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 163.7 0 10 7.5 0 0 0 153.7 6% -
March - 2018
Length 3.2 Km - earth work, sub base, base course structure work in progress.
No Image
1) BT of Hund Lar Zaida Road 1.20 Km
2) Construction of Babinin Road 1 Km
3) Rehabilitation of Gar Aka Khel Road 1 Km
4) Rehabilitation of Zaida Bypass Road 3.60 Km
5) Improvement/Widening of Swabi Jhanda Road 3.62 Km
1236
(New)
170583-Construction of Access road form Col: Sher Interchange to Jehangira Swabi Road at Tordher, District Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 100.03 0 10 7.5 0 0 0 90.03 10% -
March - 2018
Length 6 Km - work order issued.
No Image
Tordher District Swabi 6 Km
1237
(New)
170625-Construction of 5Km road & its drains from Swabi Interchange to Swabi University (New Campus) Swabi.
Swabi
30-11--1 30-11--1 - 30-11--1 - 80 0 9.084 6.813 0 0 0 70.916 11% -
March - 2018
Length 5 Km - work order issued.
No Image
Swabi 5 Km
1238
(New)
170584-Construction of Ganga Lar Sawaldher Road/Rehabilitation and Improvement of Ganga Lar Swaldher Road (3 Km) PK-29, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 56.4 0 5 5 1.25 1.25 1.25 51.4 9% 2%
March - 2018
Structure work 40% completed.
No Image
PK-29, Mardan
1239
(New)
170661-Rehabilitation of Road from Kandaro Kalay to Asif Kalay (2 KM), Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 20 0 10 15.251 15.251 9.916 9.916 10 50% 50%
March - 2018
RW completed. Sub base in trench both side completed. Pipe culverts in progress. WBM 85% completed.
No Image
Kandaro Kalay to Asif Kalay (2 Km) Mardan
1240
(New)
170668-F/S, Design & BT of remaining portion of Road from Manzaray Baba to Khanoray, Malakand (Phase-II).
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.917 0 0.001 0.001 0 0 0 199.916 0% -
March - 2018
Summary approved for waiver off consultant. Scheme approved. Tender called on 25/04/2018.
No Image
Manzaray Baba to Khanoray Malakand
1241
(New)
170627-Rehabilitation of Karora to Ajmir Road (12Km) District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 150 0 10 10 2.5 0 0 140 7% -
March - 2018
Work stared
No Image
Karora to Ajmir road (12 Km) Shangla
1242
(New)
170177-Construction of Road namely Kohistangat Saidu Sharif to Loe Banr District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 199.9 0 5 5 1.25 0 0 0 - -
March - 2018
Approved AA Awaited.
No Image
PK-80, 81 Swat
1243
(New)
170179-Construction of road from Kuza Bandai to New Cannt Swat (2.40 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 Line Deptt 506.12 0 10 10 2.5 0 0 0 - -
March - 2018
PC-II approved for Rs.3.997 m in DDWP on 18/07/2017. LOA issued to Creative Consultants. PC-I/DCE for Rs.780.270 m submitted to Chief Infra P&D on 23/01/2018. PDWP held on 08/02/2018. Deferred for want of presentation to Secretary C&W. Prsenatation made to Secreatray C&W . DCE resubmitted to P&D Department
No Image
PK-83, Swat
1244
(New)
170180-Construction and Improvement of Sigram Bypass Road, Swat (3.25 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 174.76 0 10 10 2.5 0 0 164.76 6% -
March - 2018
Land acquisition under process by district administration.
No Image
PK-83, Swat
1245
(New)
170568-Construction of 2 Km Bypass Road in Barikot District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 112.9 0 8.814 8.814 2.203 0 0 104.086 8% -
March - 2018
Land acquisition under process by district administration.
No Image
PK-82, Swat
1246
(New)
170669-Const/BT of rd from Baryam-Nazarbad, Airport-Mamdhera, Gorra-Tangai Shah,Totanu Bandai, Tangai Cheena,Sigram,Mahak-Narang pura, Venai-Ochrai & Sijban-Sperdar. Reconst. Of rd Kalakaly-Nasrat Chowk,Giga Tangbanr,Bara Bandai-Ghurejo, Shawar Gat- Landysar Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 449.995 0 15 17.561 17.561 3.75 3.75 434.995 3% 1%
March - 2018
Package-1, Package-2 - work order issued. Package-3 - WBM in progress.
No Image
1) Construction/BT of Beryum to Nazar Abad road (3 Km) Package-1
2) Construction/BT of Airport Mamdherai road (5 Km) Package-1
3) Construction/BT of Gorra Tangai Shah road (1 Km) Package-1
4) Construction/BT of Totano Bandai road (2 Km) Package-1
5) Construction/widening/BT of Tangai Cheena road (1 Km) Package-2
6) Improvement/widening/BT of Sigram Mehak Narangpura road (3 Km) Package-2
7) Construction/BT of Venai Ocharai road (3.5 Km) Package-2
8) Construction/BT of Sijbanr Sperdar road (4.275 Km) Package-2
9) Reconstruction of road Kalakalay to Nasrat Chowk (0.90 Km) Package-2
10) Reconstruction of Giga Tangbanr road (2 Km) Package-3
11) Reconstruction of Bara Bandai to Ghurijo road (2 Km) Package-3
12) Reconstruction of Shawargat Landaysar road (7.5 Km) Package-3
1247
(New)
170670-Construction of different roads (11 KM) at Tehsil Matta District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 171.995 0 10 10 2.5 0 0 161.995 6% -
March - 2018
Package-1, Package-2, Package-3, Package-4, Package-5 - in progress.
No Image
1) Karenona Sakhra road (1.50 Km) Package-1
2) Baidara Maqbara road (0.50 Km) Package-1
3) Kohistani Banda road (1 Km) Package-2
4) Kuz Lalkoo road (0.50 Km) Pacakge-2
5) Toora Satta Bara Kharkai road, Sakhara (1.5 Km) Package-3
6) Bagh Sar road (1 Km) Package-3
7) Matta Shomai Mandai Dag raod (1 Km) Package-4
8) Said Abad Chuprial road (1 Km) Package-4
9) Ragastoon road Darmai (1 Km) Package-4
10) Said Koma road Kakakot  (1 Km) Package-5
11) Madyat road Asharay (1 Km) Package-5
1248
(New)
170573-Construction/ Rehabilitation of Road Bakht Bilanda, Atack, Nagrai Payeen, Pangral Shati Chinar, Kano Ghumbat Kai and Zual Baba Hajiabad Road Asilo District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.85 0 20 15 0 0 0 154.85 11% -
March - 2018
Work order issued.
No Image
1) Bakht Biland road (2 Km)
2) Attack road (2 Km)
3) Nagrai Payeen road (1 Km)
4) Pingal road (2 Km)
5) Shatai road (2 Km)
6) Chinar road (1 Km)
7) Kano Gumbat Kai road (1 Km)
8) Zual Baba road (1 Km)
9) Haji Abad road (0.8 Km)
10) Asilo road (1 Km)
1249
(New)
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 157.708 0 10 10 0 0 0 147.708 6% -
March - 2018
Work in progress. Demand Rs. 45 M
No Image
1) Swauser Kasai
2) Gulbagh
3) Sromanzai
1250
(New)
170575-Construction of RCC Bridge at Duryal Karo Darra in PK-93 District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 30.617 0 5 5 1.25 0 0 25.617 16% -
March - 2018
Work in progress.
No Image
PK-93, Dir Upper
1251
(New)
170175-F/S, Design and Construction / Improvement and BT of Thakot-Banna Road via Kar Kally Koz Cheena District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 275 0 5 3.75 0 0 0 0 - -
March - 2018
PC-II for Rs.5.50 m approved in DDWP on 18/07/2017. LOA issued to AA Associates Approved in PDWP. AA Awaited .
No Image
Battagram
1252
(New)
170579-F/S, Desig / Construction of RCC Bridges a) Qanjobori, b) Kakar Shang, c) Banda Akhoon Zadgan Shari Khwar Alai and Reqpair of Battagram Paimal Road (12 Km), District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 218.054 0 5 3.75 0 0 0 213.054 2% -
March - 2018
DCE prepared by PCE Consultant . Approved. Tender approval under process. RFP re-flaoted for supervisiory consultanat. Technical Proposal Submitted to DST
No Image
Battagram
1253
(New)
170565-Construction of Roads from Phalra to Tamad Serian & Sehra Gali to Darband (5 Km), District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 0 0 0 0 - -
March - 2018
Approved in PDWP on 02/11/2017 for Rs.71 m. AA awaited. Summary for inclusion of additional 10 components from savings (Rs.150 m ADP cost) submitted to CA.
No Image
Mansehra
1254
(New)
170618-F/S Design and Improvement of Road from Dub Gohar Abad to Shanai District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 0 5 5 5 5 5 45 10% 10%
March - 2018
Length 5 Km (width 18 ft) - earth work in progress.
No Image
Mansehra
1255
(New)
170569-Construction of Road Bangara Malkot to Khan Dana Road (5 Km). District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 150 0 5 5 1.25 0 0 145 3% -
March - 2018
Work order issued. Spervsisiory consultant selected (Spectra Consultants).
No Image
Abbottabad
1256
(New)
170572-Construction of Qalandarabad Bypass Road, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 239.642 0 10 10 2.5 0 0 229.642 4% -
March - 2018
Work order issued.
No Image
Abbottabad
1257
(New)
170574-BT/PCC Road 25 Km in PK-46, District Abbottabad
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 250 0 5 5 1.25 0 0 245 2% -
March - 2018
Layout given.
No Image
1) Improvement/PCC/BT of Qalandar Abad to Tanawal road with link Tahairli UC Banda Pir Khan
2) Improvement/PCC/BT of Tarhana Bala with link to Basti Khawas Khan UC Banda Pir Khan
3) Rehabilitation of PCC road Abdalto Banda Pir Khan UC Banda Pir Khan
4) PCC road Mangal to Chittal Maira with link to Katha Mangal UC Baldheri
5) Improvement of PCC road More Kalan UC Baldheri
6) Construction of road Choonry Ahlan Kaloor UC Banda Pir Khan
7) Construction of road from Karlan to Bucha Gali Bagh Dara UC Chamad
8) Improvement/PCC/BT o Shah De Gali to Bal Gojri via Kasakki Kalan UC Salhad
9) Improvement and PCC of road Ban Seri to Kasakki Hurd i/c Butial road UC Chamad
10) Improvement/PCC/BT of Kuthial Gali toToda Maira road UC Kuthiala
11) Improvement/PCC of road Sabzi Mandi to Gravity Tank Upper Darra UC Salhad
12) Improvement of Banda Sinjlian to JabrianKutakian road UC Salhad
13) Improvement/PCC of rod from Lalgah to Kandar Jandakka road UC Salhad
14) Improvement/BT of Banda Qazian to Gajjal road UC Havelian Urban
15) Improvement/PCC of road from Dobahar to Boi Di Gali UC Jhangi
16) Improvement/PCCof road Thanda Maira Ziarat UC Salhad
17) Construction of road Dohabla to Darriaya UC Havelian Urban
18) Improvement/BT of road Kakaot to Shahkot UC Pawa
19) Rehabilitatoin of akian to Pind Gali Beer road via Khanda Khoo UC Pind Kargo Khan
1258
(New)
170626-F/S of Improvement / Widening of road from Kalabagh bazar to Charrain Kalpani (2 Km), Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 Line Deptt 1.05 0 1.05 1.05 0 0 0 0 - -
March - 2018
PC-II deffered. PC-I with summary submitted on 15/09/2017 for removal of consultant and change of nomenclature to CA.
No Image
Abbottabad
1259
(New)
170628-Construction of BT road from Takia Shekhan to Ghora Baz Garan road (5 KM) via Rajoya, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 69.085 0 5 5 0 0 0 0 - -
March - 2018
Approved. AA awaited due to EPA report. Tender appoval under process.
No Image
Abbottabad
1260
(New)
170182- onstruction of Internal Road, in U/Cs Central, South, North, Rehana, Shah Maqsood, Ali Khan, Darwesh, Pandak, Mankrai, Pind Hashim Khan, Sarai Saleh, Sarai Naimat Khan and Sikanderpura, Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 400 0 10 199.38 199.38 196.446 196.446 390 3% 49%
March - 2018
145 units - (PCC/BT) 50% work completed.
No Image
1) Construction of road from village Pind Hashim Khan to Teer UC Pind Hashim Khan
2) Construction of internal road Sarai Saleh Maira UC Sarai Saleh
3) Construction of Changi Bandi Main Road UC Sarai Saleh
4) Construction of road at Gheba Maira UC Shah Maqsood
5) Widening of Pharari road UC Pind Hashim Khan
6) Rehabilitation of Paswal to Bandi Mian Pir Dad UC Sarai Naimat Khan
7) Rehabilitation of Sheran Wala Gate to Chappar road UC North
8) Rehabilitation of old Adda road UC Central
9) Construction of internal road Naseem Town UC Darwesh
10) Construction of internal road TIP Housing UC South
11) Construction of Model Town UC Darwesh
12) Rehabilitation of Kachi Road UC South
13) Construction of road at Ali Khan village
14) Construction of culvert at Gehar Khan road UC Pandak
15) Construction of culvert road at Talorkar new Talokar Town UC Pandak
16) Construction of road Mohallah Shamali Noordi UC Rehana
17) Construction of Jama road UC Rehana
18) Construction of internal road at Sikandarpur
19) Construction Mohallah Haji Imam Pir road UC Sarai Saleh
20) Construction of culvert Sameer Ayub Colony UC Ali Khan
21) Construction of culvert Mohara Ali Khan UC Ali Khan
22) Construction of culvert at Murad Abad UC Ali Khan
23) Construction of internal road Chak Shah Muhammad UC Ali Khan
24) Construction of Chak Shah Muhammad Main Road at UC Ali Khan
25) Rehabilitation of road Jahaz Chowk to Central Jail UC Central
26) Construction of culvert village Darwesh UC Darwesh
27) Rehabilitation of Afzal Abad road UC South
28) Construction of culvert/road Talokar road UC Pandak
29) Construction of internal road at Gher Khan UC Pandak
30) Construction of road at Niazabad UC Pandak
31) Construction of Thanda Choa and Mohari No.1 road UC Shah Maqsood
32) Construction of Babu Mohallah road UC North
33) Construction of internal raod of Changi Bandi UC Sarai Saleh
34) Construction of road at UC Sarai Saleh
35) Construction of Gheba road Shah Maqsood UC Shah Maqsood
36) Rehabilitation of Khakka road UC Mankarai
37) Construction of internal road Maira Ali Khan UC Ali Khan
38) Construction of internal road Nartoa UC Pind Hashim Khan
39) Construction of road Mohallah Naigar UC Pind Hashim Khan
40) Construction of road at Teer UC Pind Hashim Khan
41) Rehabilitation of Suba Nullah road UC Pind Hashim Khan
42) Construction of road/street at Mohallah Granda village Nartopa UC Pind Hashim Khan
43) Construction of road Mah Da Nakka UC Sarai Naimat Khan
44) Construction of internal Magri road UC Pind Hashim Khan
45) Construction of Mankarai road UC Mankarai
46) Construction of Sunger road UC Sarai Naimat Khan
47) Construction of Sarrara road UC Sarai Naimat Khan
48) Construction of Mangloor Colony road UC Sarai Naimat Khan
49) Rehabilitation of Shingri road UC Sarai Naimat Khan
50) Construction of Mohallah Jandra road UC Sarai Saleh
51) Construction of Mohallah Gul Bahar Colony road UC Sarai Saleh
52) Construction of internal road Changi Bandi
53) Construction of internal road Kheba Maira UC Shah Maqsood
54) Construction of rehabilitation of Sehra Wala Gate to Chapra, 2 Babu Mohallah UC North
55) Construction of rehabilitation of road Jahaz Chowk to Central Jail
56) Construction of rehabilitation of raod Adha road work
57) Construction of road Model Town Darwesh
58) Construction of rehabilitation of Khoi road UC South
59) Construction of internal raod Ghar Khan
60) Constrution of internal road Mohallah Sahamali Noordi
61) Construction of Juma Abad Rehana road
62) Construction of Mohallah Haji Peer Imam road
63) Construction of culvert Sameer Ayub Colony
64) Construction of culvert at Mohra Ali Khan
65) Construction of culvert at Morad Abad
66) Construction of internal road Chak Shah Muhammad
67) Construction of road at village Darwesh
68) Construction of culvert at Gher Khan
69) Construction of internal raod at Thanda Choha Mohri No.1 UC Shah Maqsood
70) Construction of internal road Maira Ali Khan UC Ali Khan
71) Construction of internal road Maira Ali Ali Khan
72) Construction of internal road Nartope UC Pind Hashim Khan
73) Construction of internal road village Teer UC Pind Hashim Khan
74) Construction of internal road Teer road
75) Construction of road village Teer Pind Hashim Khan
76) Construction of internal road Magri road
77) Construction of internal road Magri raod UC Pind Hashim Khan
78) Construction of internal road/street Sunger
79) Construction of road Mohallah Jandarran
80) Construction of road Mohallah Jandaran
81) Construction of road Gul Bahar Colony
82) Construction of internal raod at Sikandarabad
83) Construction of road/street at VC Meelum UC Darwesh
84) Construction of road/sreet at VC Darwesh UC Darwesh
85) Construction of road/street at NHC City 13 (Ali Noor Colony Khyber Adda Mohallah Banda) UC Darwesh
86) Construction jof road/sreet at Mughal Abad Dar-ul-Aloom UC Sikandarpur
87) Constructiono f road/street at village Dheri Sikandarpur UC Sikandarpur
88) Construction of road/street at Makhan Colony UC Sikandarpur
89) Construction of road/street at VC Sikandarpur UC Sikandarpur
90) Construction of road/street at VC Gujjar Mohra UC Sikandarpur
91) Construction of road/street at Kahka UC Mankarai
92) Construction of road/street at Pharallah UC Mankarai
93) Construction of road/street at Mohara Muhammado related Abadies UC Mankarai
94) Construction of road/street at Mankarai UC Mankarai
95) Construction of road/street at Mankarai Maira UC Mankarai
96) Construction of road/street at Bayian Ahmed Ali Khan
97) Construction of road/street at Bandi Mian Pir Dad
98) Construction of road/street at Paswal
99) Construction of road/street at Kandal UC Sarai Nimat Khan
100) Construction of road/street at VC Noorpur
101) Construction of road/street at Karrach
102) Construction of road/street at Shingri Bagh UC Sarai Nimat Khan
103) Construction of road/street at Banda Munir Khan
104) Consruction of road/street at Sarai Nimat Khan village Mangloor Colony
105) Construction of road/street at Serian Mohara Karia UC Sarai Nimat Khan
106) Construction of road/street at Dharam Pani
107) Construction of culvert at Banda Munir Khan Mohallah Palasi Maira
108) Construction of culvert at Mohallah Mistriyan Mohriyan C/O Babul Asghar
109) Construction of RCC culvert at Kajal Pull to Lahar Darra
110) Construction of road/street at Talhad UC Sarai Nimat Khan
111) Construction of road/street at different mohallahs of City-III
112) Construction of road/street at different mohallahs of City-II UC North
113) Construction of road/street at Mohallah Babu UC North
114) Construction of road/street at different mohallahs of City Haripur
115) Construction of road/street at different mohallahs of City-IV Haripur
116) Construction of road/street at different mohallahs of City Haripur UC North
117) Construction of road/street at Aslam and Naeem Khan Colony
118) Construction of road/street at Mohallah Eidgah
119) Construction of road/street at Rehmaniayan Town and Sabzi Mandi UC Central
120) Consruction of road/street at different mohallahs of City Haripur
121) Construction of road/street at Mohallah Kund
122) Construction of road/street at Near Abbass Khan House UC Central
123) Construction of road/street at Mohallah Soha and Risaldarian
124) Construction of nallah/street at Mohallah Sherazi UC Central
125) Construction of road/street at Mohallah village Pharrai UC Pind Hashim Khan
126) Construction of road/street at village Teer
127) Construction of road/street of different street at village Pharrai UC Pind Hashim Khan
128) Construction of road/street at village Pind Hashim Khan
129) Construction of road/street at Mohallah Awan Mohra Rajgan village Nartopa
130) Construction of road/street at Mohallah  Narian village Nartopa UC Pind Hashim Khan
131) Construction of road/street at Mohallah Magryal village Nartopa
132) Construction of road/street at Mohallah Kargawal village Nartopa
133) Construction of road/street at village Nartopa
134) Construction of road/street at Mohallah Dangri village Nartopa
135) Construction of road/street at Mohallah Syeddan Maira village Nartopa
136) Construction of road/street at Bhatiyan village Pharrai UC Pind Hashim Khan
137) Construction of road/street at Mohallah Saeed Abad, Ameen Abad
138) Construction and sanitation of road/street at Mohallah Roshan Abad UC South
139) Construction of road/street at Karim Abad and Alam Abad
140) Construction of street/sanitation of street at Saeed Town Chongi No.11
141) Construction and sanitation of street at Qazi Abad UC South
142) Construction of road/street at Afzal Abad, Raja Abad and Aziz Colony
143) Construction of road/street at Noor Colony Mohallah Banda UC South
1261
(New)
170183-Construction of a) Makhnial to Kharian Neelan Poto road (9Km) b) Gandian Kamawa Chapra Road (12 Km), District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 250 0 10 29.763 29.763 0 0 240 4% -
March - 2018
Work Started.
No Image
Haripur
1262
(New)
170577-Construction of Thalikot Bridge at Jhari Kass Road, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 Line Deptt 80 0 10 10 2.5 0 0 0 - -
March - 2018
Spectra consultant. PC-I/DCE submitted to P&D Approved in PDWP , AA and MOM Awaited. .
No Image
PK-52, Haripur
1263
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
30-11--1 30-11--1 - 30-11--1 - 798.06 119 40 40 14.2 14.2 133.2 639.06 20% 17%
March - 2018
Length 19.925 Km - road work, embankement, subm base, WBM, WC, structure work, pipe culverts, box culverts, causeway in progress.
No Image
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.925 Km)
1264
(OG)
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km).
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 294.598 217 74.598 74.598 55.949 55.949 272.949 3 99% 93%
March - 2018
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress.
No Image
1265
(OG)
140879-Improvement & Rehabilitation of road from Gulshanabad to Janana Mill via Hangu Pattak and Dualization of Old Bannu Road from Janana Mill to Kohat University (Indus Highway Juncation) (17.90-Km) i/c Construction of New Bridge of Jerma, District Kohat.
Kohat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1403.483 446 59.75 59.75 21.211 21.211 467.211 897.733 36% 33%
March - 2018
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
No Image
1) Package-1 (Gulshan Chowk to Hangu Phatak)
2) Package-2 (Hangu Phatak to Saif CNG)
3) Package-3 (Saif CNG to Jerma Bridge Start Point)
4) Package-4 (Jerma Bridge via KUST to Main Indus Highway)
1266
(OG)
120282-Improvement and Widening of Road from Mufti Mehmood Flyover to old Budni Bridge upto Wahid Garhi 9 Km on PH S-I i/c reconstruction of old Budhni Bridge District Peshawar.
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 1119.959 469.033 50 50 17.75 17.75 486.783 600.926 46% 43%
March - 2018
Bridge completed and opened for traffic. Section-1 (1550 mtr) - asphalt overlay both side completed, drain in progress. Section-2 (1000 mtr)- sub base, aggregate base, RCC pipe culvert completed, asphalt base course, asphalt WC in progress. Financial evauation proposals of bidder opened for balance approach road.
No Image
1) 2.5 Km
1267
(OG)
170186-Reconstruction of bridge at Tauheed Abad, District Peshawar on Peshawar - Naguman of Provincial Highway S-1.
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 77.559 0 10 8.55 3.55 3.55 3.55 67.559 13% 5%
March - 2018
LOA issued to contractor. Test pile inp progress.
No Image
1268
(OG)
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1394 1066.5 30 30 10.65 10.65 1077.15 297.5 79% 77%
March - 2018
10/14 Km completed, Dargai bypass (3 Km) in progress.
No Image
Package-1
Package-2
Package-3
Package-4
Package-5
1269
(OG)
140621-Dualization of Naguman Shabqadar Section of Provincial Highway S-A, District Charsadda (13 Km).
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1609.96 507 90 90 31.95 31.95 538.95 1012.96 37% 33%
March - 2018
Land acquisition in progress. 6 Nos culverts, clearing and grubbing in progress.
No Image
Package-1 (Naguman Chowk to Hajizai
Package-2 (Bridge at Km 4+420 and Bridge at Km 4+010 at Hajizai)
Package-3 (Hajizai to Ocha Wala)
Package-4 (Ocha Wala to Shabqadar Chowk)
1270
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
30-11--1 30-11--1 - 30-11--1 - 1498.019 47.5 40 40 14.2 14.2 61.7 1410.519 6% 4%
March - 2018
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
No Image
Package-1 (Ghani Khan Road to Munaf Kali)
Package-2 (Munaf Kali to Ahmadabad)
Package-3 (Ahmadabad to Saro Shah Bridge)
1271
(OG)
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera.
Nowshera
PKHA
30-11--1 30-11--1 - 30-11--1 - 1726.703 1208.5 240 240 85.2 85.2 1293.7 278.203 84% 75%
March - 2018
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress.
No Image
Package-1 (Malang to Kana Khel)
Package-2 (Kana Khel to Sadu Khel)
Package-3 (Sadu Khel to Gajo Khel)
1272
(OG)
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner.
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 - 1017.223 79.879 30 30 10.65 10.65 90.529 907.344 11% 9%
March - 2018
Bridge - completed. Road - earth work, structure in progress. PC-II for Rs.43.750 m approved in DDWP on 19/06/2017 for construction supervision.
No Image
Package-1 (Bridge at Tor Warsak Daggar)
Package-2 (Swarai Pir Qilla Puran Road)
1273
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 192.5 30 30 10.65 10.65 203.15 467.499 32% 29%
March - 2018
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress. Approved for Rs.689.999 m in PDWP on 08/02/2018.
No Image
Package-1
Package-2
1274
(OG)
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 1798.521 1659.087 40 40 14.2 14.2 1673.287 99.434 94% 93%
March - 2018
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed.
No Image
1) Package-1 Km-0 to 9 (9 Km)
2) Package-2 Km-9 to 16 (7 Km)
3) Package-3 Km-17 to 24 (7 Km)
4) Package-4 Km-24 to 31+797 m (7.8 Km)
5) Package-5 3 Nos bridges
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 988.52 247.5 70 70 24.85 24.85 272.35 671.02 32% 28%
March - 2018
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
No Image
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top)
1276
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 344.978 167.5 40 40 14.2 14.2 181.7 137.478 60% 53%
March - 2018
Structure/road work in progress.
No Image
1277
(OG)
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad.
Abbottabad
PKHA
30-11--1 30-11--1 - 30-11--1 - 983.904 472.5 55 55 19.525 19.525 492.025 456.404 54% 50%
March - 2018
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress.
No Image
Package-1
Package-2
Package-3
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48