Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018,

Showing Page Number : 42 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1279
(OG)
20665-Construction / Supervision of new Road Works.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 1104.58 908.354 100 85.5 35.5 35.5 943.854 96.226 91% 85%
January - 2018
Construction supervision of new road works.
1280
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 253.57 177.246 20 12.1 7.1 7.1 184.346 56.324 78% 73%
January - 2018
Conusltancy services for feasilbility study and design and framing PC-I.
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 498.16 140.75 20 12.1 7.1 7.1 147.85 337.41 32% 30%
January - 2018
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
1282
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
30-11--1 30-11--1 - 30-11--1 - 2759.858 509.99 100 261.638 236.638 236.638 746.628 2149.868 22% 27%
January - 2018
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
1283
(OG)
140629-Construcction of Swat Motorway (Land Acquisition).
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 6890.03 4668.987 50 30.25 30.25 30.25 4699.237 2171.043 68% 68%
January - 2018
Formation embankment 75% completed. Subgrade 12% completed. Sub-base 8% completed. Base course 4% completed. Alignment survey completed. 65 Km land has been handed over to FWO.
1284
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 2796.766 427.25 240 145.2 85.2 85.2 512.45 2129.516 24% 18%
January - 2018
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
1285
(OG)
160193-Project Directorate for Swat Expressway.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 67.401 32.596 34.061 25.546 17.031 17.031 49.627 0.744 99% 74%
January - 2018
Project directorate setup.
1286
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 59.318 14.25 5 4.275 3.025 3.025 17.275 40.068 32% 29%
January - 2018
PIU setup, staff deputed. Revised AA approved.
1287
(OG)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 104.815 0 82.995 82.995 0 0 0 0 - -
January - 2018
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1287
(OG)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 0.01 0 0.001 0.001 0 0 0 0 - -
January - 2018
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1288
(New)
170523-F/S & Construction of Southern Link Road (Circular Road), Bannu.
Bannu
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3000 0 30 30 0 0 0 0 - -
January - 2018
Feasibility study and detailed engineering design has been awarded to M/S AAA Karachi, M/S PCE (JV).
1289
(New)
150764-F/S, Design and Construction of Swabi By-pass Road (12 Km).
Swabi
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2266.44 0 50 50 0 0 0 0 - -
January - 2018
Feasibility study and detailed engineering design in porgress. PC-I/DCE submitted to competent forum for approval. PDWP held for approval.
1290
(New)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner.
Buner
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 600 0 5 5 0 0 0 0 - -
January - 2018
Feasibility study and detailed engineering design has been awarded to M/S AAA Karachi, M/S PCE (JV).
1291
(New)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 2000 0 10 10 0 0 0 0 - -
January - 2018
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress. PC-I/DCE submitted.
1292
(New)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir (SDG).
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 410.621 0 40 40 40 40 40 370.621 10% 10%
January - 2018
Pile boring in progress.
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 3100 0 20 20 0 0 0 0 - -
January - 2018
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design. DCE submitted for Rs.3384 m to PDWP. Pre-qualification calle on 26/02/2018.
1294
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 14567.928 0 5240.75 5240.75 0 0 0 9327.178 36% -
January - 2018
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1294
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
30-11--1 30-11--1 - 30-11--1 - 2535.072 0 72 72 0 0 0 2463.072 3% -
January - 2018
Approved. Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1295
(New)
170174-Construction of Swat Motorway SH: Provincial Equity (VGF) Phase-II.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 - 6000 0 0.001 5500.001 5500 5500 5500 0 - -
January - 2018
Formation of embankment 75 % completed. Sub grade 15% sub base 10 % base course 5 % asphaltic base course 2 km completed.
1296
(New)
170521-F/S & Dualization of Mardan-Swabi road.
Provincial
PKHA
30-11--1 30-11--1 - 30-11--1 Line Deptt 8000 0 195 195 0 0 0 0 - -
January - 2018
As per descision of the steering committee, the scheme will be financed under PRRP. ADB assistance.
1297
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
30-11--1 30-11--1 - 30-11--1 - 14594.25 12652.99 500 69.19 48.143 0 12652.99 1441.26 90% 87%
January - 2018
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km, Distt road 425.55 Km, 405.89 Km, Bridges length 699.55 mtrs (10 Nos), 482.25 mtr (9 Nos) completed.
18 districts of Khyber Pakhtunkhwa Upto till Release Jan-2016 Rs.1304.09 m
1297
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
30-11--1 30-11--1 - 30-11--1 - 100 10.81 84.19 15.747 0 0 10.81 5 95% 11%
January - 2018
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km, Distt road 425.55 Km, 405.89 Km, Bridges length 699.55 mtrs (10 Nos), 482.25 mtr (9 Nos) completed.
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 114.982 131.482 0 0 0 0 131.482 0 - 100%
January - 2018
Completed.
1) RCC Bridge Ghundakai (PK-72)
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Battagram
30-11--1 30-11--1 - 30-11--1 - 48.69 55.41 0 0 0 0 55.41 0 - 100%
January - 2018
Completed (bridge span 45 mtr).
RCC Bridge on Nandehar Khawar at Deshan Hotel PK-59
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 100.651 56 10 10 10 5.421 61.421 34.651 66% 61%
January - 2018
Bridge structure completed, approaches in progress.
1) RCC bridge on Barundu Khawar
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 103.908 122.015 0 0 0 0 122.015 0 - 100%
January - 2018
Completed.
a) RCC Bridge at Badin Khawar Summer Bagh
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 116.283 128.455 0 0 0 0 128.455 0 - 100%
January - 2018
Completed.
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 59.85 68.02 0 0 0 0 68.02 0 - 100%
January - 2018
Completed.
1) Mansehra City Bridge PK-53
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 349.12 298.184 10.55 10 10 7.391 305.575 40.386 88% 88%
January - 2018
5/6 bridges completed, 1 in progress (Mayar bridge) lauching completed.
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span 2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span) 3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span) 4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span 5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span 6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Nowshera
HW
30-11--1 30-11--1 - 30-11--1 - 45 48.737 0 0 0 0 48.737 0 - 100%
January - 2018
Completed.
1) RCC bridge at Qasim Ali Baig (Taru)
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 918.425 908.303 85 47.25 26 0 908.303 0 100% 99%
January - 2018
Work in progress (Umbrella).
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 49.569 38.5 0 0 0 0 38.5 11.069 - 78%
January - 2018
Completed.
1) Diyal bridge (200 feet span)
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 2.515 18.78 0 0 0 0 18.78 0 - 100%
January - 2018
1) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Dir Upper and Lower
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 22.285 18.78 0 0 0 0 18.78 3.505 - 84%
January - 2018
Completed.
1) Shomai bridge 2) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Dir Upper and Lower
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Provincial
30-11--1 30-11--1 - 30-11--1 - 764 262.615 50 12.607 37.5 0 262.615 0 - -
January - 2018
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 174.45 155.703 0 0 0 0 155.703 18.747 - 89%
January - 2018
Out of 7 bridges, 6 completed, 1 launching under process (Rahim Abad Bridge). Payment made to Pak Army 3 years ago.
1) Mula Baba Bridge 2) Amankot (Rahim Abad) Bridge 3) Rahim Abad Bridge 4) Barikot (Babaji Baba) Bridge 5) Faiz Abad Bridge 6) Kuz Kalay Khwaza Khela Bypass bridge 7) Chinkolai Faqira Bridge 8) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Swat
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Tank
30-11--1 30-11--1 - 30-11--1 - 67.825 30.852 0 0 0 0 30.852 36.973 - 45%
January - 2018
18/18 piles completed. Both abutments completed. Launching in progress.
1) Shah Alam bridge (180 feet)
1300
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 6.05 5.268 0 0 0 0 5.268 0.782 - 87%
January - 2018
PC-II approved. Consultant selected. Demand Rs.0.383 m.
1300
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 5.268 50 12.5 37.5 0 5.268 0 - -
January - 2018
PC-II approved.
1301
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 100 2.473 44.422 11.105 0 0 2.473 0 - -
January - 2018
PC-II approved.
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Buner
30-11--1 30-11--1 - 30-11--1 - 151.056 134 1.45 1.45 1.45 1.45 135.45 15.606 90% 90%
January - 2018
All 3 bridges completed.
1) Sura Bridge 2) Sunigrame Bridge 3) Bagra Baridara
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Chitral
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2018
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 127.977 95.837 0 0 0 0 95.837 32.14 - 75%
January - 2018
Completed (3 bridges).
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 122.148 97.57 7 7 7 7 104.57 17.578 86% 86%
January - 2018
Out of 4 bridges, 1 completed, 3 approach work in progress.
1) Steel bridge Sheringla Colony PK-92 2) Steel bridge Jan Bahtti PK-91 3) Steel bridge Sordam PK-92 4) Steel bridge Almas Dag Tarpatar PK-92
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Provincial
30-11--1 30-11--1 - 30-11--1 - 960.82 688.868 70 65 30 0 688.868 0 - -
January - 2018
Work in progress.
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Provincial
30-11--1 30-11--1 - 30-11--1 - 2972.23 0 22.873 65 30 0 0 0 - -
January - 2018
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Shangla
30-11--1 30-11--1 - 30-11--1 - 155.106 76.902 11 11 11 10.038 86.94 67.204 57% 56%
January - 2018
Alpuri Gandaow bridge - RW, approaches in progress. Demorai bridge - completed. Bilkanai Larai bridge - abutments completed, transportation of steel bridge in progress.
1) Alpuri Gandaow bridge 2) Damorai bridge 3) Kuz Kan Dunai bridge ST Bikanai Larai
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 332.611 284.559 0.4 0.4 0.4 0.4 284.959 47.652 86% 86%
January - 2018
Completed (7 bidges).
1303
(OG)
130574-Impt / Rehabilitation & Upgradation of 300 Km roads in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 451.062 281.208 0 30 30 26 307.208 169.854 - 68%
January - 2018
Length 49 Km (80 units) - work in progress.
1) PK-44 2) PK-45 3) PK-46 4) PK-47 5) PK-48
1303
(OG)
130574-Impt / Rehabilitation & Upgradation of 300 Km roads in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 75 80.119 1 1 1 1 81.119 0 100% 100%
January - 2018
Completed (8.5 Km).