Progressive Review for the month(s) of : December - 2016,

Showing Page Number : 2 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Abbottabad
15-03-15 - - 24-09-14 - 4.6 2.7 0 0 0 0 2.7 1.9 - 59%
December - 2016
Out of 4 units, 1 completed, 2 in progress, 1 work order issued.
1) Saint Mathew Church Nathiagali (2 rooms)
2) BW with Gate at Bhifaith Graveyard Abbottabad
3) St Mathew Church Natia Gali (renovation)
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Bannu
03-04-15 - - 24-09-14 - 5 5 0.437 0.437 0.437 0.437 5.437 0 100% 100%
December - 2016
Completed (4 units).
1) Mandar Nanga Bab Bannu
2) Balmik Mandar near General Bus Stand Bannu (2 rooms)
3) Church at Christian Compound Havaid Gate Bannu
4) Hall of Mandar at Havid Gate Bannu
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
D.I.Khan
02-02-15 - - 24-09-14 - 3.5 3.239 0 0 0 0 3.239 0.261 - 93%
December - 2016
Out of 4 units, 3 completed, 1 finishing stage.
1) Talla Kawel Sati Ram (10 bathrooms)
2) Cantt Mandar
3) Balmik Mandar Mohallah Jogi Wala
4) Catholic Church Qasim road DI.Khan (BW/Veranda/Inside Ceilings at Saint Helen's)
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Hangu
02-01-15 - - - - 2.5 2.5 0 0 0 0 2.5 0 - 100%
December - 2016
Completed (3 units).
1) Priest House at Thal Cantt
2) Sabzi Mandi near old Hospital Christian Mohallah Thal Hangu
3) Prim Nagar near FC Line Hangu
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Haripur
- - - 24-09-14 - 6 0.489 0 0 0 0 0.489 5.511 - 8%
December - 2016
Out of 2 units, all in progress.
1) Community Center for Christians, 1st floor St John's Church Haripur (civil work)
2) St John's Church near Eid Gah Haripur City (civil work)
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Kohat
25-02-15 - - 24-09-14 - 1.5 1.5 0 0 0 0 1.5 0 - 100%
December - 2016
Completed & H/O.
Shamshan Got Kohat
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Malakand
- - - 24-09-14 - 2.6 2 0 0 0 0 2 0.6 - 77%
December - 2016
Completed & H/O.
Mandar at Dargai Malakand
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Mansehra
- - - - - 2.5 0 0 0 0 0 0 2.5 - -
December - 2016
Dropped.
1) Shive Mandar Chati Gatti Ghandian Manshera (20 bathrooms)
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Mardan
25-02-15 - - 24-09-14 - 2 1.9 0 0 0 0 1.9 0.1 - 95%
December - 2016
Completed.
1) Shamshan Got Ram Bagh Mardan PK-24
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Nowshera
01-01-15 - - 24-09-14 - 3.5 1.668 0 0 0 0 1.668 1.832 - 48%
December - 2016
Completed (1 units). Mandar Grama Nowshera Cantt - site demarcation disputed. Pur Fazal Kalisaya - CGI sheet roofing completed. Revised PC-I/DCE submitted.
1) Community Hall at Sister Colony Risalpur
2) BW at Christian Colony Risalpur
3) Pur Fazal Kaliseya Church Khattak Colony Nowshera
4) Mandar at Risalpur
5) Mandar at Garama Nowshera Cantt
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Peshawar
BD-2
04-03-15 - - 24-09-14 - 26.3 15.579 3.142 3.142 3.142 1.913 17.492 7.579 71% 67%
December - 2016
Out of 9 units, 7 completed, 2 in progress.
1) Phando Church Chiragh Abad (Ghang) PK-02
2) Yousaf Abad Tehkal Payan Christian Colony
3) Saint Mathew School Yousaf Abad Tehkal Payan (2 rooms)
4) Jora Ghar Gurdwara Bhai Joga Singh PK-03
5) Daga Pir Ratan Nath PK-03
6) Father Colony Tehkal Payan PK-05
7) Saint Jan School Girls Section Kohati Gate
8) Face lifting of Cathederal Church 1-Sir Syed road Peshawar Cantt PK-04
9) Apostolic Church Banaras Abad Academy Town Christian Colony Peshawar PK-05
10) Seventh day Adventist Church Peshawar PK-04
47
(OG)
140584-Renovation of Mandars, Gordawaras and Churchs in Khyber Pakhtunkhwa.
Provincial
- - - 24-09-14 - 60 37.075 15 15 0 0 37.075 0 - -
December - 2016
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Abbottabad
- 30-06-17 - 24-09-14 - 5.192 0 1.2 1.2 1.2 0.832 0.832 3.992 23% 16%
December - 2016
Out of 4 units, 2 work started, 2 site not H/O.
1) Graveyard Municipal Committee Abbottabad
2) Gora Qabristan Abbottabad
3) Christian Graveyard Salhad
4) Christian Graveyard Abbottabad Cantt
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Buner
- 30-06-17 - 24-09-14 - 3.462 0.5 0 0 0 0 0.5 2.962 - 14%
December - 2016
Out of 2 units, 1 completed, 1 work order issued.
1) Shamshangot Gurghushto PK-77
2) Shamshangot Dewana Baba (veranda and bath room)
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Chitral
- 30-06-17 - 24-09-14 - 1 0 1 1 1 0 0 0 100% -
December - 2016
Broon Bumburate
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
D.I.Khan
02-02-15 30-06-17 - 24-09-14 - 0.6 0.6 0 0 0 0 0.6 0 - 100%
December - 2016
Completed & H/O.
1) Boundary wall of Gora Qabristan Tank road DI.Khan
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Haripur
- 30-06-17 - 24-09-14 - 2 0.684 0 0 0 0 0.684 1.316 - 34%
December - 2016
SS in progress.
New Christian Graveyard Bagh-e-Qadian near Sikandarpur UC Haripur (shad + guard room civil work)
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Kohat
06-11-15 30-06-17 - 24-09-14 - 3.108 3.108 0 0 0 0 3.108 0 - 100%
December - 2016
Completed & H/O.
1) Christian Graveyard Kohat Cantt
2) Gora Qabristan Kohat
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Malakand
- 30-06-17 - 24-09-14 - 1.23 0.63 0 0 0 0 0.63 0.6 - 51%
December - 2016
Completed & H/O.
Christian Community Graveyard at Dargai Malakand
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Mardan
09-02-15 30-06-17 - 24-09-14 - 3 2.317 0 0 0 0 2.317 0.683 - 77%
December - 2016
Completed & H/O.
1) Near Chatto Chowk
2) Near General Bus Stand PK-23
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Nowshera
13-01-15 30-06-17 - 24-09-14 - 4 1.213 0 0 0 0 1.213 2.787 - 30%
December - 2016
Out of 2 units, 1 completed, 1 in progress (work stopped by CB on Shoba Bazar, NOC awaited).
1) Jahangira Nowshera
2) Shoba Bazar Nowshera
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Peshawar
BD-2
05-11-15 30-06-17 - 24-09-14 - 8 2.113 3.585 3.585 3.585 0 2.113 2.302 71% 26%
December - 2016
Out of 2 units, 1 completed, 1 in progress.
1) Shade and Foot Path with bricks at Gora Qabristan Peshawar PK-04
2) Seventh day Graveyard Askari Five Peshawar Cantt PK-04
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Provincial
- 30-06-17 - 24-09-14 - 30 7.351 14.339 14.339 0 0 7.351 0 - -
December - 2016
1) Shade and Foot Path with bricks at Gora Qabristan Peshawar PK-04
2) Seventh day Graveyard Askari Five Peshawar Cantt PK-04
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Swat
- 30-06-17 - 24-09-14 - 2 0 0 0 0 0 0 2 - -
December - 2016
Work stopped due to non-availability of funds.
Shamshan Got Khwaza Khela Swat (room and water tank)
48
(OG)
141042-Construction of Boundry Wall arround Graveyard in Khyber Pakhtukhwa.
Tank
- 30-06-17 - 24-09-14 - 3 0 0 0 0 0 0 3 - -
December - 2016
600 rft (height 7 ft) - DPC laid of 120 ft road.
Minority Graveyard (boundary wall)
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
Charsadda
- 30-06-17 - 14-01-16 - 2 0 0 0 0 0 0 2 - -
December - 2016
Approved in DDWP on 14/01/2016.
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
D.I.Khan
- 30-06-17 - 14-01-16 - 3 0 0 0 0 0 0 3 - -
December - 2016
Tender approval under process.
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
Hangu
- 30-06-17 - 14-01-16 - 4 0 1 1 1 1 1 3 25% 25%
December - 2016
Work in progress.
Minority Colony Prem Nagar (repair of houses and pavement of street)
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
Mardan
- 30-06-17 - 14-01-16 - 3.915 0 1 1 1 0 0 2.915 26% -
December - 2016
Work order issued.
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
Peshawar
- 30-06-17 - 14-01-16 - 2.967 0 0 0 0 0 0 2.967 - -
December - 2016
Financial bid opened on 11/01/2017.
Janazgah for minorities at Warsak Christian Colony PK-07
49
(OG)
150167-Improvement and Rehabilitation of Residential Colonies for Minorities in Khyber Pakhtunkhwa (Phase-VI).
Provincial
- 30-06-17 - 14-01-16 - 15 0 15 15 0 0 0 0 - -
December - 2016
54
(OG)
130118-Improvement of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Bannu
18-04-14 30-06-17 - 23-08-13 - 4 3.625 0 0 0 0 3.625 0.375 - 91%
December - 2016
Completed.
1) Jamia Masjid Kotka Malangan near Bannu Woolen Mills
54
(OG)
130118-Improvement of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Mardan
14-01-15 30-06-17 - 23-08-13 - 1 0.94 0 0 0 0 0.94 0.06 - 94%
December - 2016
Completed & H/O.
Islamia Tafheem ul Quran Malakand road Mardan
54
(OG)
130118-Improvement of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
- 30-06-17 - 23-08-13 - 2.1 15.503 0 0 0 0 15.503 0 - 100%
December - 2016
Scope of work and sites not yet identified.
54
(OG)
130118-Improvement of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Provincial
- 30-06-17 - 23-08-13 - 4 0 6 6 0 0 0 0 100% -
December - 2016
Allocation changed from revenue to capital side dated 28/02/2014.
54
(OG)
130118-Improvement of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Tank
25-10-14 30-06-17 - 23-08-13 - 1.5 1.5 0 0 0 0 1.5 0 - 100%
December - 2016
Completed & H/O.
Ilyasi Masjid Kot Murtaza
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Abbottabad
- 30-06-17 - 23-08-13 - 0 0 0 0 0 0 0 0 - -
December - 2016
PC-I/DCE for Rs.2.360 m submitted on 02/06/2014. Dropped in DDWP.
1) Christian Colony Qalandarabad (BW of graveyard/guard room/store/gate)
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Buner
20-05-14 30-06-17 - 23-08-13 - 20.5 17.15 0 0 0 0 17.15 3.35 - 84%
December - 2016
Muqbara Cheena PK-78, Muqbara Kalpanai PK-78 - finishing in progress.
1) Muqbara at Cheena PK-78
2) Muqbara at Kalpani PK-78
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Dir Lower
22-06-16 30-06-17 - 23-08-13 - 6.1 6.056 0 0 0 0 6.056 0.044 - 99%
December - 2016
Completed (3 units).
1) Graveyard Chakdara
2) Graveyard Bishigram
3) Graveyard Damkata
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-1
14-08-14 30-06-17 - 23-08-13 - 11.6 7.13 0 0 0 0 7.13 4.47 - 61%
December - 2016
Out of 2 units, 1 completed, 1 in progress.
1) Graveyard of Shrine Ashab Baba Chagharmatti PK-07 (boundary wall)
2) Graveyard of Pakha Ghulam PK-09 (boundary wall)
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Provincial
- 30-06-17 - 23-08-13 - 40 38.133 6.8 6.8 0 0 38.133 0 - -
December - 2016
55
(OG)
130119-Construction of Boundary Wall around Graveyards in Khyber Pakhtunkhwa (Phase-II).
Tank
- 30-06-17 - 23-08-13 - 0 0 0 0 0 0 0 0 - -
December - 2016
PC-I/DCE submitted to SO Dev Auqaf on 04/03/2015. Tender under process.
29 Nos in District Tank
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Buner
15-04-15 30-06-17 - 24-09-14 - 6.9 6.9 5.4 5.4 5.4 0 6.9 0 100% 100%
December - 2016
Out of 2 units, all in progress.
1) Madrassa Lilbanat Al-Markaze Islami Rega Buner PK-78
2) Dar ul Zeayafat Al-Markaz Islami Rega Buner PK-78
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Hangu
12-02-15 30-06-17 - 24-09-14 - 1 1 0 0 0 0 1 0 - 100%
December - 2016
Completed & H/O.
Masjid Mardo Khel (toilets/ablution places)
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Haripur
04-06-15 30-06-17 - 24-09-14 - 3 0.4 0 0 0 0 0.4 2.6 - 13%
December - 2016
Roof laid.
1) 1st floor at Madrassa Ganja Kamala Haripur
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Mardan
- 30-06-17 - 24-09-14 - 0.6 0.6 0 0 0 0 0.6 0 - 100%
December - 2016
Completed & H/O.
Madrassa Jamia Islamia Tafheem-ul-Quran Malakand road Mardan (parda wall, main gate etc)
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Peshawar
BD-2
28-02-15 30-06-17 - 24-09-14 - 5 4.989 0 0 0 0 4.989 0.011 - 100%
December - 2016
Completed.
Jamia Masjid Chishtia Hanfia and Madrassa-tul-Madina Mohallah Baqir Shah Meena Bazaar Peshawar
57
(OG)
140851-Improvement and Rehabilitation of Madaaris and Mosques in Khyber Pakhtunkhwa.
Provincial
- 30-06-17 - 24-09-14 - 19 13.889 2.011 2.011 0 0 13.889 0 - -
December - 2016
Work in progress.
58
(OG)
150754-Improvement and Rehabilitation of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Bannu
- - - 14-01-16 - 4.5 1.5 3 3 3 2 3.5 0 100% 78%
December - 2016
Out of 2 units, 1 completed, 1 in progress.
58
(OG)
150754-Improvement and Rehabilitation of Deeni Madaris and Mosques in Khyber Pakhtunkhwa (Phase-II).
Battagram
- - - 14-01-16 - 0.5 0 0.25 0.25 0.25 0 0 0.25 50% -
December - 2016
Work started.
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43