Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1000 (OG) |
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu. |
Hangu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 35.12 | 24.647 | 26.623 | 26.623 | 21.761 | 56.881 | 90.233 | 40% |
38% February - 2018 |
4 units - 1.5 Km BT completed. WBM in progress on rest. |
ADP's Images |
1) Bangash Chapper road (4.50 Km - 12 ft)
2) Link road at Shanawari to Wrasta (1.10 Km - 18 ft)
3) Darr Makhadu Quba road Samana (2.10 Km - 21 ft)
4) Mula Tabi road Samana (1 Km - 18 ft)
5) Navai Killay Samana road (1 Km - 12 ft) | |||||||||||||||||||
1001 (OG) |
140628-Rehabilitation of Road from Chamkani to PAF Camp Badaber District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 160.238 | 0 | 20 | 17.1 | 7.1 | 7.1 | 7.1 | 140.238 | 12% |
4% February - 2018 |
Work on drain and sub-base in progress. |
No Image |
Peshawar | |||||||||||||||||||
1002 (OG) |
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.933 | 31.173 | 18.01 | 18.01 | 13.508 | 13.508 | 44.681 | 0.75 | 98% |
89% February - 2018 |
Bridge 60 mtr - bridge structure work and base course completed. Rs.8.500 m demanded for completion. |
No Image |
Peshawar | |||||||||||||||||||
1003 (OG) |
140942-Construction / Rehabilitation of Roads (a) Urmar Payan towards Kaskai Warsak Canal (b) Urmar Miana to Warsak Canal (c) Urmar Payan via Qasim Ali Baig to GT Road and (d) Urmar Payan to Mashan Khel, Peshawar (10 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 95.896 | 61.962 | 33.434 | 33.434 | 33.434 | 30.851 | 92.813 | 0.5 | 99% |
97% February - 2018 |
Length 10 Km - 10 Km asphalt completed. Rs.5 m demanded for completion. |
No Image |
Peshawar | |||||||||||||||||||
1004 (OG) |
140943-F/S, Design, Improvement & BT of Road from Mustajab Ghari to Shahibala (20 Km), Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 188.067 | 83.021 | 50 | 71.433 | 71.433 | 71.433 | 154.454 | 55.046 | 71% |
82% February - 2018 |
Length 20 Km - 12 Km asphalt, 8 Km base course completed. Structure work in progress. Rs.40 m demanded for tempo of work. |
No Image |
1) Mustajab Garhi roda 3.3 Km
2) Feroq Pur Gujar Dand road 2.7 Km
3) Bridge Dheri Nasir Bagh road | |||||||||||||||||||
1005 (OG) |
140944-F/S, Design and Construction of Road from Nothia Stop to Kohat Road and from Nothia Phattak to Swati Phattak, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.907 | 79.284 | 70.123 | 70.123 | 35.062 | 35.062 | 114.346 | 0.5 | 100% |
76% February - 2018 |
Length 10 Km - 6 Km asphalt completed, drain both side in progress. Rs.7.9 m demanded for completion. |
No Image |
1) Swati Patak to Urmar road
2) Nothia Stop to Kohat road
3) Nothia Stop to Swati Patak | |||||||||||||||||||
1006 (OG) |
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 149.814 | 59 | 10 | 8.55 | 6.05 | 6.05 | 65.05 | 80.814 | 46% |
43% February - 2018 |
Length 13 Km - 10 Km asphalt completed. Rs.92 m demanded for completion. |
No Image |
1) Afghan Colony and Sardar Ahmad Jan Colony
2) Afrid Garhi
3) Chandni Chowk
4) Din Behar Colony
5) Ghani Colony
6) Kachkol Abad road with 5 Nos link road
7) Liaqat Abad and Larma BW road
8) Dur-e-Kamal Zaryab Colony with 3 Nos link road
9) Maulana Fazal-e-Rehman Madrass rod with 3 Nos link
10) Shinwari Town with 4 Nos link | |||||||||||||||||||
1007 (OG) |
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1046 | 397.815 | 100 | 108 | 108 | 105.885 | 503.7 | 548.185 | 48% |
48% February - 2018 |
8 Km asphaltic base completed on 4 Nos bridges, in progress. Rs.150 m demanded for tempo of work. |
No Image |
Package-1
Package-2
Bridge-1 at RD
Bridge-2 at RD | |||||||||||||||||||
1008 (OG) |
140951-Construction / Rehabilitation of 10 Km roads in PK-05, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 109.326 | 71.75 | 42.826 | 62.826 | 41.413 | 41.413 | 113.163 | 0 | 100% |
100% February - 2018 |
Length 10 Km - 10 Km asphalt completed. Rs.1 m demanded for completion. |
No Image |
1) Abdara road to Tango Adda 1.125 Km
2) Danish Abad to Board Bazar 1.850 Km
3) Fouji Foundation Hospital to Tehkal Bus Stop 2.100 Km
4) Palosai to Tehkal Payan 2.100 Km
5) Town Thana to Friends CNG 1.750 Km | |||||||||||||||||||
1009 (OG) |
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km). |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 195.896 | 107.803 | 25 | 29.058 | 29.058 | 29.058 | 136.861 | 63.093 | 68% |
70% February - 2018 |
Length 20 Km - 16 Km asphalt completed, on remaining base course, structure work in progress. Rs.69.35 m demanded for completion. |
No Image |
1) Talkht Abad road 4 Km
2) Wadpaga Jala Bela road 2 Km
3) Dalazak Jala Bela road 2 Km
4) Butai Rano Garhi road 2 Km
5) GT road to Jogani road 1 Km
6) Charsadda road to Moora road 1 Km
7) GT road Chughal Pura Arbab Haroon Stand
8) Nothern Bypass to Kukar via Baddu Samarbagh
9) Village Daman Hindki to Norhtern Bypass
10) Jhalarian road 1 Km
11) Shakar Pur road 1 Km
12) Dalazak road to Yasin Abad Bridge | |||||||||||||||||||
1010 (OG) |
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 64.655 | 61.345 | 61.345 | 61.344 | 61.2 | 125.855 | 0 | 100% |
100% February - 2018 |
Length 11 Km - 10 Km asphalt completed and structure work in progress. Rs.6.045 m demanded for completion. |
No Image |
1) Hazrat Baba to Wali Abad road 1.6 Km
2) Mohallah Haya Khel to Rind road 0.70 Km
3) Insaf road to Ghafoor Abad 0.50 Km
4) Insaf road to Gharib Abad 0.50 Km
5) Bazid Khel road
6) Canal road to Merozai raod 3.30 Km | |||||||||||||||||||
1011 (OG) |
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 9.5 | 10 | 18.794 | 18.794 | 15 | 24.5 | 130.5 | 13% |
16% February - 2018 |
Length 10 Km - 1.7 Km WB completed. Rs.60 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1012 (OG) |
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.882 | 28.405 | 10 | 13.672 | 13.672 | 13.672 | 42.077 | 61.477 | 38% |
42% February - 2018 |
Length 10 Km - 1.4 Km asphalt completed, drain work on all packages in progress. Rs.55 m demanded for tempo of work. |
No Image |
PK-04 Peshawar | |||||||||||||||||||
1013 (OG) |
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.736 | 59.998 | 10 | 21.355 | 21.355 | 21.355 | 81.353 | 29.738 | 70% |
82% February - 2018 |
Length 10 Km - 9 Km asphalt completed and structure work in progress. Rs.31 m demanded for tempo of work. |
No Image |
PK-05 Peshawar | |||||||||||||||||||
1014 (OG) |
150794-Construction / Rehabilitation of Deh Bahadar, Chalozan Colony, Achni Bala Pishtakhara Bala, Sufaid Dheri roads, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.81 | 23.655 | 30 | 35.894 | 35.894 | 34.879 | 58.534 | 46.155 | 54% |
59% February - 2018 |
Length 9 Km - 6 Km asphalt completed. Structure work in progress. Rs.40.261 m demanded. |
No Image |
PK-06 Peshawar | |||||||||||||||||||
1015 (OG) |
150796-Construction / Rehabilitation of (a) warsak road People Stop to Chagharmatti and in UC Mathra (b) Badizi UC Reggi and (c) Hindu Kasay UC Panam Dheri District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 99.91 | 21.386 | 30 | 30.772 | 30.772 | 30.772 | 52.158 | 48.524 | 51% |
52% February - 2018 |
Length 9 Km - 3.8 Km asphalt completed. Structure work in progress. Rs.52.500 m demanded for tempo of work. |
No Image |
Peshawar | |||||||||||||||||||
1016 (OG) |
150799-Construction and Blacktopping of roads from Yousafabad to Gohi Arat Mera road, Nasapa Bala road, Toda to Muslim Abad, Mandra Khel road, Landi Sarak, Choli to Khurasan road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 15 | 15 | 7.5 | 7.5 | 22.5 | 0 | 100% |
75% February - 2018 |
Length 4 Km - substanially completed. Rs.7.5 m demanded for completion. |
No Image |
1) Nasapa Payan road 800 mtr
2) Mandra Khel road 1.5 Km
3) Choli to Khurasan rao 400 mtr
4) Tauda to Muslim Abad 1 Km | |||||||||||||||||||
1017 (OG) |
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 88 | 50 | 72.628 | 72.628 | 46.58 | 134.58 | 62 | 69% |
67% February - 2018 |
Length 17 Km - 9 Km asphalt completed and on remaining structure work, base course work in progress. Rs.69.500 m demanded for tempo of work. |
No Image |
PK-09/PK-13 Peshawar | |||||||||||||||||||
1018 (OG) |
150802-(a) Const / Rehab Adezay to Sherkera (Ithad Chowk) to Hameed Khan (Machine) road (b) Rehabilitation of internal roads of UC Badaber Maira Korizay and construction of Maryam Zai Deli Dher road alongwith RCC Bridge, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 250 | 170.351 | 67.649 | 67.649 | 67.648 | 55.6 | 225.951 | 12 | 95% |
90% February - 2018 |
Length 20 Km - 19 Km asphalt completed and on remaining base course, structure work in progress. Tender approval of balance work under process. |
No Image |
1) Deli Dherain road Peshawar road 2.9 Km
2) Maira Khorizay Badaber 3.70 Km
3) Adizai Sharky 7 Km | |||||||||||||||||||
1019 (OG) |
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 13.962 | 35.788 | 35.788 | 32.132 | 30.788 | 44.75 | 0.25 | 100% |
90% February - 2018 |
Completed (4.5 Km). |
No Image |
1) Sheikhano Main raod 1.1 Km
2) Khan Bahadar Mosque to Frontier road via Och W 1.9 Km
3) Masezai Canal road 1.3 Km | |||||||||||||||||||
1020 (OG) |
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 10 | 20 | 20 | 15 | 15 | 25 | 0 | 100% |
83% February - 2018 |
Completed (4 Km). |
No Image |
1) Garhi Taj Muhammad to Garhi Mir Tayyab road 1.4 Km
2) Tuewell Koroona road, Mamo Khatki Koroona road 350 mtr
3) Mamo Khatki to Bela Baramad Khel Haryana Bala road to Garhi Sher Afzal 1 Km
4) Maqsood Abad Banglow road | |||||||||||||||||||
1021 (OG) |
150952-Construction / Rehabilitation of Haji Jalndhar Graveyard towards Warsak Canal, Police Chowki Afridi Abad towards Speen Qabar, Zangli Nehr Towards Sheen Rang, Sheikh Muhammadi Main road Towards Kohat road Toheedabad, Warsak Canal towards Kagawal, Peshawar. |
Peshawar HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 50 | 15.212 | 34.538 | 34.538 | 29.618 | 26.19 | 41.402 | 0.25 | 100% |
83% February - 2018 |
Completed (4 Km). |
No Image |
1) Haji Jalindher Graveyard towards Warsak Canal
2) Police Chowki Afridi Abad towards Speen Qabar
3) Zanli Nehr towards Sheen Rang
4) Sheikhan Muhammadi Mian road towards Kohat road Toheed Abad
5) Warsak Canal towards Kagawal Peshawar | |||||||||||||||||||
1022 (OG) |
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 401.195 | 251.375 | 60 | 67.663 | 67.683 | 67.683 | 319.058 | 89.82 | 78% |
80% February - 2018 |
Length 10 Km (width 12 ft) - 4 Km asphalt completed. |
ADP's Images |
1. Kangra Road (6 Km) width 12 ft
2. Byapss road from Pir Kally to Major Kally (Length - 6 Km width 18 ft ) | |||||||||||||||||||
1023 (OG) |
140890-F/S, Design, Reconstruction and Rehabilitation of Roads (a) from Alladad Khel to Village Kani Teshil Shabqadar (b) from Ziam Rest House to Salgaray via Gud Killi Chowk Shamsabad (c) from Village Cheena to Dildar Ghari, Charsadda (12 Km). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 120 | 84.506 | 40.44 | 42.259 | 42.259 | 42.259 | 126.765 | 0 | 100% |
100% February - 2018 |
Length 12 Km - 6 Km asphalt completed. Revised PC-I/DCE for Rs.250 m approved. \AA Awaited. Summmary for Change of Nomenclature submittd to CA. |
No Image |
1) Allah Dad Khel to village Kani Tehil Shabqadar (Length- 2.5 width 12ft )
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad (length 2.5 km Width 12 ft )
3) Village Cheena to Dildar Garhi Charsadda (length 7 km Width 18 ft ) | |||||||||||||||||||
1024 (OG) |
150818-Construction / rehabilitation / widening of road (a) Umerzai Yakhkoi to Turangzai, (b) Damdam to Hayat Gul Kalli Dedar Abad UC Sarki Titara, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 90 | 43.835 | 45.905 | 45.905 | 34.428 | 32.62 | 76.455 | 0.26 | 100% |
85% February - 2018 |
Length 6 Km - 4.5 Km asphalt completed. |
No Image |
1. Umarzai to Yakh Koi ( 2km - Width 12 ft )
2. Damadam to Hayat Gul kallya 9 4km - width 12 ft ) | |||||||||||||||||||
1025 (OG) |
150820-Construction of road from Harichand to Hayat Khan Banda and Bashir Khan Banda to Said Imran Kalay and Shakoor to Pumbaoosha via Kirmu, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 230.917 | 42.06 | 54.69 | 46.76 | 33.087 | 33.087 | 75.147 | 134.167 | 42% |
33% February - 2018 |
Length 7 Km - 4 Km asphalt completed. |
No Image |
1. Hari Chand to Hayat Khan Banda ( length 3 km ) (width 12 ft )
2. Bashir Khan Banda to Said Imran Kallay (length 2 km ) 9 !2 ft wide )
3. Shahkur to Bumboo Shaha ( Length 2km ) ( width 12 ft ) | |||||||||||||||||||
1026 (OG) |
150823-Construction and Blacktopping of roads (a) Jandai Pul to Kakakhelo Dheri U/C Umerzai (b) Jangai to Shaberra U/C Agra, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 125 | 135.06 | 13.75 | 13.75 | 6.875 | 4.881 | 139.941 | 0 | 100% |
100% February - 2018 |
8.5 Km - completed. |
No Image |
1. Janadai Pul to Kakkhaloo Deri ( 2km ) ( 12 ft Wide )
2. Jnagai to Shahdara ( length 6.5 km ) ( Width 12 ft ) | |||||||||||||||||||
1027 (OG) |
150825-Construction and Blacktopping of roads (a) Shabqadar Chowk to Matta including Bridge, (b) Haji Zai to Yaqhi Band via Tarkha and Masal Qila to road via Mian Essa, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 350 | 40 | 60 | 133.064 | 118.064 | 67.137 | 107.137 | 250 | 29% |
31% February - 2018 |
Length 7 Km - 2 Km asphalt completed. |
No Image |
1. Shabqadar Chowk to Mtta ( L 7m ) (W-24 ft )
2. Mirzai to Nusarat Zai ( L- 3 km ) ( w- 12 ft )
3. Haji Zai to Tarkha (2.5 km ) (12 ft )
4. Haji Zai to Gundha ( 6.5 km ) ( 12 ft )
5. Shab qaadr Matt aroad to Khair aabd ( 1.5 km ) ( 12 ft )
| |||||||||||||||||||
1028 (OG) |
150881-Construction of road from Sardheri to Dosehra road, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.5 | 12.25 | 28 | 28 | 21 | 16.94 | 29.19 | 0.25 | 99% |
72% February - 2018 |
Length 5 Km - 3 Km asphalt completed. |
No Image |
Sardheri to Dosehra road (5 km ) ( 12 ft ) | |||||||||||||||||||
1029 (OG) |
150948-Reconstruction & Rehabilitation of roads from Haryana to Hajizai, Nazimabad to Gujar Kali, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 150 | 45.076 | 3.478 | 2.974 | 1.235 | 1.235 | 46.311 | 101.446 | 32% |
31% February - 2018 |
4 Km (original scope) - 4 Km asphalt completed. Revised scope - work order issued. |
No Image |
Charsadda | |||||||||||||||||||
1030 (OG) |
150954-Construction and BT of road (a) Peshawar road to Kodai UC Agra (b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 325 | 51.755 | 43.867 | 46.468 | 46.468 | 46.468 | 98.223 | 229.378 | 29% |
30% February - 2018 |
8.5 Km (original scope) - 8.5 Km asphalt completed.
Revised scope - Work started |
No Image |
Charsadda | |||||||||||||||||||
1031 (OG) |
150980-Construction of Sarwar Abad Umarzai Road and Road from Shakh No.4 to Shakh No.5 via Zarbab Ghari Maira Umarzai, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 188.669 | 36.598 | 43.152 | 36.895 | 26.107 | 26.107 | 62.705 | 108.919 | 42% |
33% February - 2018 |
6.5 Km - 3 Km asphalt completed. |
No Image |
Charsadda | |||||||||||||||||||
1032 (OG) |
151069-Construction of Sro Kalay Road from Yaka Ghund Road to Subhan Khwar, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 8.5 | 11.25 | 11.25 | 8.438 | 7.139 | 15.639 | 0.25 | 99% |
78% February - 2018 |
2 Km - 1 Km asphalt completed. |
No Image |
Charsadda | |||||||||||||||||||
1033 (OG) |
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 206.95 | 76.996 | 70 | 117.683 | 117.683 | 14.923 | 91.919 | 59.954 | 71% |
44% February - 2018 |
Length 2.4 km (width 24 ft ) Land paymnet made. Dispute resolved. Work in progress. |
No Image |
Charsadda | |||||||||||||||||||
1034 (OG) |
140672-Feasibility Study, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Ghari on Right Bank and Kheshgi on Left Bank, District Nowshera i/c construction of Bypass road from main GT road to Pashtoon Garhi Bridge (3 Km), District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 680.592 | 503.643 | 40 | 50.61 | 50.61 | 12.045 | 515.688 | 136.949 | 80% |
76% February - 2018 |
Original scope bridge and approaches, Bridge (450 mtr) completed, opened to Traffic. Revised scope. Land acquisation under process. Work in progress on Pashtun Ghari Bypass. |
No Image |
Nowshera | |||||||||||||||||||
1035 (OG) |
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1009.995 | 426.892 | 164.997 | 302.563 | 302.563 | 272.852 | 699.744 | 418.106 | 59% |
69% February - 2018 |
Original scope - 27 Km completed. Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
1036 (OG) |
140936-F/S, Design and BT of internal roads Pirpiai - Azakhel Bala - Payan - Dagai - Banda Nabi, Badrashi, Nowshera. SH: Const of internal road in UCs Dagai-Banda Nabi, Pirpiai, Badrashi, Azakhel Bala & Payan, District Nowshera (Phase-II). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 1050 | 427.927 | 200 | 261.967 | 261.967 | 151.851 | 579.778 | 422.073 | 60% |
55% February - 2018 |
Original scope + 1st Revised scope completed (35 Km). 2nd and 3rd revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
1037 (OG) |
140938-F/S, Design & Improvement / BT of Internal 16 Km road at Kheshgi Bala and Payan, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 849.997 | 168.772 | 100 | 305.719 | 305.719 | 303.595 | 472.367 | 581.225 | 32% |
56% February - 2018 |
Original scope completed (16 Km). 1st Revised scope - work in progress. 2nd revised scope. Work order issued. |
No Image |
Nowshera | |||||||||||||||||||
1038 (OG) |
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 400 | 183.001 | 100 | 59.146 | 59.146 | 22.161 | 205.162 | 116.999 | 71% |
51% February - 2018 |
Length 6.7 Km - completed (original scope). Revised scope - work started. |
No Image |
Nowshera | |||||||||||||||||||
1039 (OG) |
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 369.986 | 33.933 | 37.406 | 54.092 | 54.092 | 11.456 | 45.389 | 298.647 | 19% |
12% February - 2018 |
Contract agreement sanctioned by CA. FWO mobilized. 60% work completed. |
No Image |
Nowshera | |||||||||||||||||||
1040 (OG) |
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 124.99 | 118.494 | 30 | 11.887 | 11.887 | 0 | 118.494 | 0 | 100% |
95% February - 2018 |
Length 8.3 Km - 8.3 Km completed. Summary approved. Revised PC-I/DCE for Rs.200 m submitted to SOR on 08/02/2018. |
No Image |
Nowshera | |||||||||||||||||||
1041 (OG) |
141019-F/S, Design & Construction / Rehabilitation of Roads (a) GT road to Said Akbar Koroona (b) Ayub Abad to Essori Bala (c) Jehangira Kati Maina (d) Pitao Payan to Dargai village (e) GT road Khwar Mohallah Shen Bagh Koroona, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.551 | 206.956 | 20 | 10.122 | 10.122 | 3.001 | 209.957 | 67.595 | 77% |
71% February - 2018 |
Original scope - completed (12 Km). Revisded scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
1042 (OG) |
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km). |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 284 | 172.57 | 19.994 | 39.118 | 39.118 | 14.823 | 187.393 | 91.436 | 68% |
66% February - 2018 |
Original scope - completed (10 Km). Revisded scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
1043 (OG) |
141024-F/S, Design & Construction / Rehabilitation of roads (a) Gajoo Khel Ameero road (b) Jabbi road (c) Piran Bala and Payan & (d) From Duran to Masamkhel via Malikhel Bala Payan, District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 144.501 | 36.326 | 44.009 | 44.009 | 0 | 144.501 | 19.173 | 90% |
72% February - 2018 |
Original scope - completed (11 Km). Revisded scope in progress. |
No Image |
Nowshera | |||||||||||||||||||
1044 (OG) |
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru Distt Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 749.744 | 173.693 | 60 | 176.829 | 176.829 | 125.226 | 298.919 | 516.051 | 31% |
40% February - 2018 |
Length 23 Km - completed (original scope). Revised scope - in progress. |
No Image |
Nowshera | |||||||||||||||||||
1045 (OG) |
150809-Construction / Pavement of roads / streets alongwith allied works in UCs Aman Kot, Mohib Banda, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 599.984 | 191.93 | 100 | 168.266 | 168.266 | 148.252 | 340.182 | 308.054 | 49% |
57% February - 2018 |
Length 17.5 Km - 13 Km completed. Revised scope - in progress. |
No Image |
Nowshera | |||||||||||||||||||
1046 (OG) |
150810-Construction / pavement of roads / streets in UC?s Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 549.577 | 175.272 | 100 | 104.341 | 104.341 | 71.767 | 247.039 | 274.305 | 50% |
45% February - 2018 |
Length 15 Km - structure work, street pavement in progress. |
No Image |
1) Kheshgi Payan
2) Kheshgi Bala
3) Aman Garh
4) Gandheri
5) UC Aman Garh and Gandheri
6) UC Kheshgi Payan & Bala
7) UC Kheshgi Payan
8) Kheshgi Bala UC Aman Garh UC Gandheri | |||||||||||||||||||
1047 (OG) |
150813-Construction / Rehabilitation of Road from Inzari to Hisartang and Shaidu Khwar to Shinwari Koroona via Eidgah District Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 200 | 6.384 | 90 | 29.433 | 29.433 | 9.139 | 15.523 | 103.616 | 48% |
8% February - 2018 |
Length 6.2 Km - Earth work, structure work in progress. Revised scope- Summary approved. Work order issued. Revised PC-I/DCE for Rs.200 m submitted to SOR on 08/02/2018. |
No Image |
Nowshera | |||||||||||||||||||
1048 (OG) |
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, GT Road to Fazal Gange and Hassan Abad Risalpur GT Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.899 | 117.52 | 53.483 | 169.52 | 169.52 | 166.674 | 284.194 | 228.896 | 43% |
71% February - 2018 |
Length 8.5 Km - completed. Revised scope - in progress. |
No Image |
Nowshera | |||||||||||||||||||
1049 (OG) |
150955-Construction of drains, pavement of streets and internal roads of Dak Ismail Khel, Shah Kot, Dak Besud, Balu, Spin Khak and Jalozai Distt Nowshera. |
Nowshera HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 700.09 | 199.993 | 100 | 191.207 | 191.207 | 142.314 | 342.307 | 400.097 | 43% |
49% February - 2018 |
Length 18.5 Km - completed. Revised scope in progress. |
No Image |
Nowshera | |||||||||||||||||||