Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : February - 2018,

Showing Page Number : 11 of 47

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
309
(New)
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 20.364 0 0 0 0 0 0 20.364 - -
February - 2018
Approved.
No Image
GPS Nasrat PK-91
309
(New)
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 79.765 0 0 0 0 0 0 79.765 - -
February - 2018
Approved.
No Image
1) GGPS Taru Jabba PK-12
2) GGPS Banda Sheikh Ismail PK-13
3) GGPS No.1 Dagi Qadeem PK-13
4) GGPS No.1 Manki Sharif PK-13
309
(New)
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 Line Deptt 1200 0 100 100 0 0 0 0 - -
February - 2018
No Image
309
(New)
170557-Reconstruction of 100 Primary Schools on need basis in Khyber Pakhtunkhwa.
Swabi
30-11--1 30-11--1 - 30-11--1 - 43.184 0 0 0 0 0 0 43.184 - -
February - 2018
Approved.
No Image
1) GPS Mughai Kot PK-31
2) GPS Spin Kani PK-32
3) GPS Tarkha Dobian PK-33
310
(OG)
110441-Establishment of one Cadet College in Lakki Marwat.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 777.245 0 50 50 25 25 25 727.245 6% 3%
February - 2018
LOA issued to consultant. Survey completed by consultant. Work order issued. Demand Rs.30 m.
No Image
Cadet College Lakki Marwat
311
(OG)
130486-Construction of a new block (consisting 30 rooms) in Government Higher Secondary School No.1 Peshawar City.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 57.719 0 57.718 57.718 0 0 0 0.001 100% -
February - 2018
Demolition completed in Jan-2017. Work order issued on 28/03/2017. Work stopped by Edu deptt during visit on 7/7/2017. Revised DCE to be prepared on new scope( scope still awaited from client deptt)
No Image
PK-02, Peshawar
312
(OG)
140190-Establishment of GGHS Comboh, GGHS Dir Colony, GGHS Hasan Garhi & Reconstruction of GHS Nanak Pura, Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 159.644 115.77 215.205 215.205 78 35.45 151.22 0 100% 95%
February - 2018
Out of 4 units, 3 in progress, 1 work order issued but sites not cleared).
No Image
1) GGHS Kambo
2) GGHS Hassan Garhi
3) GGHS Dir Colony
4) GHS Nanakpura
313
(OG)
150140-Establishment of Girls Primary cum Seondary School in one building at Qazi Killy Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 99.173 24 76.937 76.937 30.736 7.765 31.765 0 100% 32%
February - 2018
Land payment made. Site not H/O.
No Image
Qazi Killy Peshawar PK-01
314
(OG)
150147-Establishment of Model Secondary School Ring Road, Charsadda Road Portion, Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 261 66.462 203.064 203.064 25 7.741 74.203 0 100% 28%
February - 2018
Land payment made. Site not H/O.
No Image
PK-01, Peshawar
315
(OG)
150710-Establishment of Residential Girls Primary cum Secondary Model School Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 - 323.907 165.917 126.062 126.062 126.062 70.731 236.648 31.928 90% 73%
February - 2018
Admin block, examination hall, principal residence - foundation in progress.
ADP's Images
Mardan
316
(OG)
160525-Establishment of Girls Cadet College at Mardan.
Mardan
30-11--1 30-11--1 - 30-11--1 Line Deptt 30 0 55 55 55 1 1 0 100% 3%
February - 2018
PC-II for Rs.30 m approved in PDWP on 24/08/2016. LOA issued to M/S Structural Engineering Solution for FS, survey, soil investigation, master planning, architectural design and drawings. Work order issued.
No Image
Mardan
317
(OG)
110452-Estblishment of Bacha Khan Model School at Salarzai in District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 113.989 106.966 0.001 0.001 0.001 0 106.966 7.022 94% 94%
February - 2018
Deffered in PDWP 03/09/2015. M&E team visited the site on 20/10/2015. M&E report awaited.
No Image
PK-79 Buner
319
(OG)
70613-Establishment of Dir Model School at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 147.806 10.44 12 12 6 0 10.44 125.366 15% 7%
February - 2018
Structure and leveling dressing in progress.
No Image
Upper Dir PK-91
320
(OG)
130417-Construction of 100 students hostel for girls in Bumburate, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 99.213 37.425 67.394 67.394 49.54 13.842 51.267 0 100% 52%
February - 2018
GF roof level. BW SS level.
ADP's Images
Chitral
321
(OG)
150560-Establishment of Girls Primary cum Secondary School Oghi Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 0 75 75 19.314 0 0 0 - -
February - 2018
PC-I/DCE submitted. Land not handed over.
No Image
PK-56 Oghi, Mansehra
322
(OG)
150552-Rehabilitation of building of Directorate of Curriculum & Teacher Education, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 60 12.374 55 55 55 25.664 38.038 0 100% 63%
February - 2018
Block-A - flooring in progress. Block-B - FF roofing in progress.
No Image
ECTE, Abbottabad
323
(OG)
150711-Remodelling, Redesigning and Rehabilitation of Pilot High School for Girls in Haripur City.
Haripur
30-11--1 30-11--1 - 30-11--1 - 172.5 2.429 170 170 59.99 19.744 22.173 0 - -
February - 2018
PC-II submitted. Academic block - upto DPC completed. Admin block - excavation in progress.
ADP's Images
Haripur City
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Bannu
30-11--1 30-11--1 - 30-11--1 - 59.623 49.013 10 10 10 5.421 54.434 0.61 99% 91%
February - 2018
Out of 11 units, 6 completed, 5 in progress. Demand Rs.7 m.
No Image
1) GGHS Qamar Zaman Mandew
2) GGPS Sher Nawaz Lawan Derdariz
3) GGHS Bangish Khel PK-73
4) GPS Haibat Khan Sabo Khel Mandan
5) GGPS Mombati Barakzai PK-72
6) GGPS Shaikh Sarwar Mandew PK-72
7) GGHS Piran Khan Bad Shah
8) GHS Mandew Khass
9) GGMS Malik Kamal Khan Dardariz
10) GGPS Zaram Mandew
11) GGPS Akbar Ali Khan Nurar
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 50.762 48.941 0 0 0 0 48.941 1.821 - 96%
February - 2018
12 units - Completed & H/O (12 units).
No Image
1) GGPS Dosehra Sheikhan PK-18
2) GGMS Arenda Haleemzai PK-22
3) GGMs Ibrahim Zai PK-17
4) GPS Gundai Koroona ST Shahid Gul Koroona PK-22
5) GPS Mian Kally No.2 PK-22
6) GPS Rashaky PK-22
7) GPS Malka Dher PK-17
8) GPS Abbas Killi No.2 PK-17
9) GPS Ibrahim Zai PK-18
10) GPS Kabli Koroona PK-22
11) GPS Zarwar Koroona
12) GPS Shahib Gul Koroona PK-22
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 11.4 11.618 0 0 0 0 11.618 0 - 100%
February - 2018
Completed & H/O (2 units).
No Image
1) GGMS Kotla Saidan
2) GPS Dera Township
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Hangu
30-11--1 30-11--1 - 30-11--1 - 52.298 46.749 4.5 4.5 4.5 3.162 49.911 1.049 98% 95%
February - 2018
Out of 6 units, 3 completed, 3 in progress.
ADP's Images
1) GPS Regi Medi Khel
2) GGPS Shahu Khel
3) GGPS Kotki Payan
4) GHS Tora Wari PK-43
5) GPS Saro Khel Darsamand PK-43
6) GPS No.1 Karbogha
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 0.62 0 0 0 0 0 0 0.62 - -
February - 2018
Work started (1 unit).
No Image
GPS Kotka Sher Zaman Dalo Khel PK-76
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Mardan
30-11--1 30-11--1 - 30-11--1 - 170.569 174.747 0 0 0 0 174.747 0 - 100%
February - 2018
Out of 17 units, 16 completed, 1 in progress.
No Image
17 units
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 - 380.832 383.263 0 0 0 0 383.263 0 - 100%
February - 2018
Completed (27 units).
No Image
1) GPS Arat Baba Sherkera PK-10 2) GPS No.1 Mera Mattani 3) GPS Lohra Sherkera 4) GMS Mattani 5) GGMS Adezai 6) GHS Sherkera 7) GHSS Adezai 8) GPS Jani Ghari 9) GPS No.2 Adezai PK-10 10) GGMS Mattani No.2 PK-10 11) GGMS Feroz abad PK-10 12) GPS No.3 Maryam zai PK-10 13) GPS No.4 Mattani PK-10 14) GGPS Qadar Abad PK-10 15) GPS Adezai No.1 16) GPS Ghari Noor Khan PK-11 17) GPS Talab Koroona Badaber PK-11 18) GPS Mera Shiekhan 19) GGMS Khwaja Mir Killi PK-11 20) GGPS Masho Gaggar PK-11 21) GGPS Salman Khel PK-11 22) GGMS Masho Khel PK-11 23) GPS Mera Balarzai PK-11 24) GPS Masho Pake PK-11 25) GPS Miskeenabad Regi PK-07 26) GGPS Khwaja Mir Killi PK-11 27) GGHS Suleman Khel PK-11
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 - 11 383.263 5 5 5 0.803 384.066 0 100% 100%
February - 2018
Finishing stage.
No Image
GPS/GMS Palosi Athozai PK-05
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Provincial
30-11--1 30-11--1 - 30-11--1 - 632.552 345.642 44.015 44.015 0 0 345.642 242.895 62% 55%
February - 2018
Work in progress.
No Image
325
(OG)
110449-Reconstruction of Govt Schools damaged due to militancy / bomb blasts in the Province other than Malakand Division.
Swabi
30-11--1 30-11--1 - 30-11--1 - 34.476 33.682 0 0 0 0 33.682 0.794 - 98%
February - 2018
Completed & H/O (10 units).
No Image
1) GHS Marghuz No.2 PK-35 (4 class rooms)
2) GPS Kulalo Shewa PK-32 (3 class rooms)
3) GGPS Sher Din Banda PK-35 (2 class rooms)
4) GGPS Khalil Shewa PK-32 (2 class rooms)
5) GHS Kaddi PK-35 (1 class room + office)
6) GGPS Mian Dheri PK-31 (2 class rooms)
7) GGMS Mian Dheri PK-31
8) GGPS Murad Abad PK-32 (2 class rooms)
9) GPS No.3 KSK PK-32 (2 class rooms)
10) GPS Jalal Shewa PK-32 (2 class rooms)
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Battagram
30-11--1 30-11--1 - 30-11--1 - 184.387 22.683 11.869 11.869 11.869 11.869 34.552 149.835 19% 19%
February - 2018
Main building - SS in progress. BW 80% completed. Rs.20 m required to keep the tempo of work.
ADP's Images
Construction of Model School at Moza Chappergram, Battagram
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 197.598 21.073 11.869 11.869 11.869 0 21.073 164.656 17% 11%
February - 2018
Land acquisition under process. Work order issued to contractor on 15/06/2017.
No Image
Bacha Khan Model School Charsadda
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Hangu
30-11--1 30-11--1 - 30-11--1 - 125.915 0 2.522 2.522 2.522 0 0 123.393 2% -
February - 2018
PC-II approved. LOA issued to SHAZ consultants on 17/10/2016. Work order issued.
No Image
Establishment of Model School Hangu
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Haripur
30-11--1 30-11--1 - 30-11--1 - 215.623 5.898 21.869 21.869 21.869 11.866 17.764 187.856 13% 8%
February - 2018
Consultant selected. Plan under preparation. Pre-qualification of contractor submitted to consultants for scrutiny. Tender floated.
No Image
Establishment of Model School Haripur (215.623 15 and 16.230 revenue)
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Karak
30-11--1 30-11--1 - 30-11--1 - 199.217 67.046 11.869 11.869 11.869 11.869 78.915 120.302 40% 40%
February - 2018
Main building - GF column completed. BW - 33% completed. Tube well bore completed.
ADP's Images
Model School Karak
326
(OG)
120470-Establishment of 5 Model Schools in Khyber Pakhtunkhwa (Karak, Haripur, Charsadda, Hangu and Battagram).
Provincial
30-11--1 30-11--1 - 30-11--1 - 691.2 83.313 100 100 0 0 83.313 507.887 27% 12%
February - 2018
No Image
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Bannu
30-11--1 30-11--1 - 30-11--1 - 97.786 70.235 0 0 0 0 70.235 27.551 - 72%
February - 2018
Completed (6 units).
No Image
1) GGPS Kot Zafar
2) GGPS Bashir Ghoriwala
3) GGPS Manawar Khan Titer Khan
4) GGPS Mohmood Painda Khel
5) GGPS Lapri Killa
6) GGPS No.1 Jandu Khel
7) GGPS No.2 Jandu Khel
8)  GGPS Juma Gul Sauiful Khel
9) GGPS Rabnawaz Tarkhawala
10) Playground in District Bannu
11) GGMS Kotka Khan Sharin Shahbaz Azmat Khel
12) GGPS Jangi Killa Pirba Khel
13) GGPS Kotka Farid Painda Khel
14) GGPS Bizen Khel
15) GGPS Ghulam Mughel Khel
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Battagram
30-11--1 30-11--1 - 30-11--1 - 23.496 27.507 0 0 0 0 27.507 0 - 100%
February - 2018
Completed (2 units).
No Image
1) GGPS Banda Bala UC Kuzabanda
2) GGMS Thakot UC Thakot
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Buner
30-11--1 30-11--1 - 30-11--1 - 141.3 97.389 0 0 0 0 97.389 43.911 - 69%
February - 2018
Completed (12 units). 2 sites disputed.
No Image
1) GPS Gujar Abad PK-77
2) GGPs Kass Koroona No.2 PK-77 shifted to Dandmaira
3) GPS Badher PK-77
4) GPS Taremam PK-77
5) GGPS Nanseer PK-79
6) GGPS Hall PK-77
7) GGPS Nagrai PK-77
8) GMS Maina Kadal PK-77
9) GMS Jabba (Khadu Khail) PK-77
10) GMS Kangalai PK-77
11) GMS Chanal PK-77
12) GHS Jower PK-79 shifted to GHS Battai
13) GHS Koga PK-77
14) GHSS Ghazi Kot PK-77 shifted to GHS Swawai
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 106.075 69.645 0 0 0 0 69.645 36.43 - 66%
February - 2018
8 units - 1 completed, 5 in progress, 1 site not H/O (GGPS Biro Kally PK-19, PG not H/O).
No Image
1) GGPS Kuladher PK-17
2) GGPS Zarin Abad PK-17
3) GGPS Biro Kally PK-19
4) GGPS Qalandar Mian Killy PK-20
5) GPS No.2 Ocha Wala PK-22
6) GGMS Kaptan Kally PK-17
7) GGMS Maina Shakh No.6 PK-18
8) GMS Nawa Kally PK-19 (shifted to GMS Zarib Abad PK-17)
9) GHSS Dargai (Playground)
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 42.083 41.104 0 0 0 0 41.104 0.979 - 98%
February - 2018
Completed & H/O (3 units).
No Image
1) GPS Chah Hussain Khan (PS to MS level)
2) GGMS Wanda Lali ( MS to HS level)
3) GHS Bilot Sharif (Playground)
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 46.3 42.873 0 0 0 0 42.873 3.427 - 93%
February - 2018
Completed & H/O (4 units).
No Image
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 56.147 35.368 0 0 0 0 35.368 20.779 - 63%
February - 2018
Completed ( 3 untis).
No Image
1) GGPS Kair Dara PK-91 to middle level 2) GGPS Nawo PK-91 to middle level 3) GGMS Darora PK-91 to high level
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Hangu
30-11--1 30-11--1 - 30-11--1 - 37.99 36.274 0 0 0 0 36.274 1.716 - 95%
February - 2018
Completed (5 units).
ADP's Images
1) GGPS Shahu Khel
2) GPS Regi Madi Khel
3) GGPS Kotki Payan
4) GHS Tora Wari PK-43
5) GPS Saro Khel Darsamand PK-43
6) GPS No.1 Karbogha PK-43
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Haripur
30-11--1 30-11--1 - 30-11--1 - 21.766 21.915 0 0 0 0 21.915 0 - 100%
February - 2018
Completed (3 units).
No Image
1) GGPS Sawar Maira PK-52
2) GGMS Sawar Maira PK-52
3) GPS Pharosa PK-52
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Karak
30-11--1 30-11--1 - 30-11--1 - 40.334 21.1 0 0 0 0 21.1 19.234 - 52%
February - 2018
Out of 3 units, 2 completed, 1 financial bid under process (PG at GGHS Sabir Abad).
No Image
1) GGPS Kandu Khel to middle level
2) GGMS Sordog to high level
3) GGHS Sabir Abad (Playground)   
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 32.5 14.862 0 0 0 0 14.862 17.638 - 46%
February - 2018
Out of 2 units, 1 completed, 1 in progress.
No Image
1) GMS Khawer Kandian PK-63
2) GPS Kotia Pattan PK-61
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Mardan
30-11--1 30-11--1 - 30-11--1 - 69.181 67.312 0 0 0 0 67.312 1.869 - 97%
February - 2018
Completed (7 units).
No Image
7 units
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
No Image
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle Schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Provincial
30-11--1 30-11--1 - 30-11--1 - 1430 610.262 0.001 0.001 0 0 610.262 0 - -
February - 2018
No Image
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Shangla
30-11--1 30-11--1 - 30-11--1 - 56.017 70.921 0 0 0 0 70.921 0 - 100%
February - 2018
Out of 4 units, 1 completed, 3 in progress.
No Image
1) GGPS Arakh Kormang to middle level PK-87 2) GGPS Meman Peshlor to middle level PK-88 shifted to GGPS Aman Dehrai 3) GGMS Chowga to high level PK-88 4) PG GHS No.2 Alpuri
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Swabi
30-11--1 30-11--1 - 30-11--1 - 135.954 97.503 0 0 0 0 97.503 38.451 - 72%
February - 2018
Out of 11 units, 9 completed, 2 in progress.
ADP's Images
1) GGMS Jhada
2) GGMS Dagao Gadoon
3) GGPS Gulo Dheri PK-31
4) GPS Khesha Mir Ali PK-32
5) GGPS Managai PK-32
6) GGPS Masood Abad Dobian PK-33
7) GGPS Ouch Khwar PK-34
8) GGPS Lalo Dheri Bam Khel PK-35
9) GGPS Kaddi Dagai PK-31
10) GPS Katgram Gadoon PK-36 shifted to GPS Devel
11) PG at GHs Zaroobi PK-35
327
(OG)
120499-Up-gradation of 50 Primary & 50 Middle schools, construction of 20 playgrounds and 400 addl: C.rooms through PTCs.
Swat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
No Image
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47