Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : March - 2018,

Showing Page Number : 40 of 48

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1133
(OG)
140901-F/S, Design & Construction of Talash Kalpanai Bypass road (10 Km), Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 683.495 122.5 50 12.5 0 0 122.5 510.995 25% 18%
March - 2018
Land acquisition under process. Section-4 completed. Award not yet finalized. Earth work completed.
No Image
1) Package-1 (3 Km)
2) Package-2 (3 Km)
3) Package-3 (4 Km)
1134
(OG)
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 174.826 107.833 30 28.65 21.15 21.15 128.983 36.993 79% 74%
March - 2018
Out of 4 bridges, all in progress (Agharily, Arif Killi, Darangal Khwar, Markhani Maidan bridges).
No Image
1) Agherlay bridge
2) Arif Kalay bridge
3) Darangal Khwar bridge
4) Markhanai Maidan bridge
1135
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 450.485 0 50 42.237 29.737 29.737 29.737 400.485 11% 7%
March - 2018
Munjai Bridge - working pile in progress. Casting of girders in progress. 3 units tender in progress.
No Image
1) RCC Bridges in Dir Lower (4 Nos)
2) RCC Bridge at Munjai (210 mtr)
3) Haji Abad (210 mtr)
4) Nasafa (140 mtr)
5) Kano (70 mtr)
1136
(OG)
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 199.796 51.41 20 26.052 26.052 23.368 74.778 128.386 36% 37%
March - 2018
Length 12 Km - work in progress on all 6 units.
No Image
1) Gudar road
2) Takurro road
3) Denjarai to Ijara road
4) Naway Kalay road
5) Bota road
6) Qazi Abad Tatar road
1137
(OG)
150838-Construction of RCC bridges Raidgay (Kotkay) & Gul Khawarr Maidan Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 190.549 0 20 15.251 15.251 15.251 15.251 170.549 10% 8%
March - 2018
Piles, pile cap, piers in progress.
No Image
1) RCC Bridge at Raidgay (Kotkay) PK-96 (span 210 mtr)
2) RCC Bridge at Gul Khawar MaidanPK-96 (span 35 mtr)
1138
(OG)
Construction of Swat-Asbarn road (4 Km), Asbarn-Shursheen (4 Km), Ramial Ghazo Chat Pat road (3 Km), Jawaro Kashmir road (2 Km), Teso Dehrai Khonano Baba raod (3 Km), Naway Kalay Bochakai road (2 Km), Ramora Dara road (2 Km), Osakai road (1 Km), Leko road (1 Km), Hamza Banda road (1 Km), Mator Bout Qilla Shadam road (1 Km), Donga Kass Kasai road (1 Km), Alidadai Asbarn road (1 Km), Barimkai road (1 Km), Doga Gaz Dara Khadagzai road (1 Km), Gulabad Asbarn / Shah Alam Baba road (3 Km), Khairabad Kotigram road (2 Km), Khadagzai link / Obakhawar Shaheed road (1.65 Km), Chakdara Kamala road (Badwan) (3 Km) and Swat Asbarn Ragbanai road (3 Km) District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 550 130.829 50 55.634 55.634 55.634 186.463 369.171 33% 34%
March - 2018
27 Km road - 10 Km completed. 17 Km in progress.
No Image
1) Swat Asbanr road
2) Asbanr Shorshing road
3) Ramial Ghazo road
4) Chat Pat road
5) Jawro Kashmir road (2 Km)
6) Osakai road (1 Km)
7) Liko road (1 Km)
8) Nawa Kalay Bochake road (2 Km)
9) Ramora Dara road (1.8 Km)
10) Hamza Banda road (1 Km)
11) Asbanr Ali Dadai road (1 Km)
12) Asbar But Qilla Shadam road (1 Km)
13) Donga Kass-Kasai road (1 Km)
14) Brimkay road (1 Km)
15) Dherai Tesso Khunano Baba road
16) Doga Ghaz Dara road (1 Km)
17) Gul Abad Asbanr/Shah Alam Baba road (3 Km)
18) Khair Abad Kotigram Laram road (2 Km)
19) Khadagzai link/Obokhwar Shaheed road (1.65 Km)
20) Chakdara Kamal Badwan road (3 Km)
21) Swat Asbanr Raghbanai road (3 Km)
1139
(OG)
150963-Construction / Rehabiliation of roads Pato Atak & Barikot, Rabat Assigay Laram Danda, Sarbanda, Dod Khana, Shati, Mali, Watangay, Malakand Kohrey, Gadla, Banda, Karam Khel, Sparay, Danwa, Rani & Ghwaago Distt Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 369.278 200.136 50 64.153 64.153 61.463 261.599 119.142 68% 71%
March - 2018
Length 30 Km - 12 Km BT, work in progress in all 17 units.
No Image
1) Patto Attak road
2) Bari Kot road
3) Rabat Assigay road
4) Laram Danda road
5) Sar Banda road
6) Dood Khana road
7) Malai road
8) Watangai road
9) Gadala road
10) Malakand Kohery road
11) Karam Khail Malakand road
12) Safarai Malakandroad
13) Danwa road
14) Ghawgo Siar road
15) Rani road
16) Banda road
17) Shatay road
1140
(OG)
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 367.574 193.674 20 40.447 40.447 37.757 231.431 153.9 58% 63%
March - 2018
Length 31 Km (20 units) - 12 Km BT completed, 19 Km in progress.
No Image
1) Shaneey road
2) Mashoo road
3) Chinarono road
4) Banda road
5) Chinoo road
6) Dehrai road
7) Chinar Tangai road
8) Machoo road
9) Gumbat road
10) Katan road
11) Khonako road
12) Ahmad Galai road
13) Amlook Dara road
14) Siar Gatt road
15) Chaman Abad road
16) Yar Khan Banda road
17) Nagrai road
18) Gumbat Gai road
19) Anangoro road
20) Haji Abad road
1141
(OG)
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 275.308 37.942 10 27.251 27.251 27.251 65.193 227.366 17% 24%
March - 2018
Length 22 Km - 3 Km BT completed.
No Image
1) Construction/BT of Raindlay road UC Miskini
2) Construction/BT of Kakass road UC Miskini
3) BT of Zardar Banda raod UC Mayar
4) BT of Markhano to Nasir road UC Mayar
5) BT of Adam Shah and Juni Kalay road UC Mayar
6) BT of Khwar to Inzaro (Chaghrabs) road UC Mayar
7) BT of Pattan to Batoro raod UC Mayar
8) BT of Jabagai to Batoro road UC Mayar
9) Construction of PCC road Khara UC Kambat
10) Construction of PCC road Gatano UC Kambat
11) BT of Mandizo Damtal Malkano road UC Kambat
12) BT of Damtal Nekhan Bandaroad UC Kambat
13) BT of Asharkore Bala road UC Samarbagh
14) Construction of PCC road Shontala UC Samarbagh
15) BT of Gular road UC Samarbagh
16) BT of Qashodali road UC Samarbagh
17) BT of Dandono road UC Samarbagh
18) BT of Tatar Bala and Gul Dherai road UC Samarbagh
1142
(OG)
150966-Construciton of RCC Bridge at Matako Rahim Abad District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 170 29.656 26.733 22.857 16.168 16.168 45.824 113.611 33% 27%
March - 2018
Length 110 mtr - piling completed, pile caping completed, launching of girders in progress.
No Image
1) Construction of RCC Bridges at approach road Matako Rehim Abad (span 140 mtr)
2) Shukarta Mayar Bridge, Dir Lower (span 210 mtr)
1143
(OG)
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 278.061 77.079 20 49.136 49.136 49.134 126.213 180.982 35% 45%
March - 2018
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
No Image
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road
1144
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 255.368 162.76 15 16.795 16.795 9.075 171.835 77.608 70% 67%
March - 2018
Original scope - 10 Km (PCC 14 ft wide) - completed. Revised scope (4ft additional PCC) in progress.
No Image
PK-92 Dir Upper (Km-1 to 10)
1145
(OG)
140648-Construction of RCC Bridge at Khal Barkalay Bazaar PK-93 District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 69.934 53.174 21.251 21.251 21.249 15.906 69.08 0 100% 99%
March - 2018
Completed. Approaches completed. Railing in progress.
No Image
RCC Bridge at Khall Bar Kalay Bazaar PK-93 (span 135 mtr)
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 120 51.348 68.152 68.152 68.144 43.206 94.554 0.5 100% 79%
March - 2018
Length 8 Km - 6 Km BT completed.
No Image
 Dir Upper (Km-1 to 8)
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 150 47.905 101.345 101.345 76.008 48.115 96.02 0.75 100% 64%
March - 2018
Length 5 Km - 4 Km BT completed. Work order issued for new work 3 Km.
No Image
Dir Upper (5 Km)
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 26.75 20 24.058 24.058 21.368 48.118 253.25 16% 16%
March - 2018
Length 10 Km - cutting of 10 Km completed.
No Image
Dir Upper (Km-1 to 10)
1149
(OG)
140905-Construction of PCC Roads at Usherai Dara (10 Km), Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 450 62.25 30 32.608 32.608 32.608 94.858 357.75 21% 21%
March - 2018
Length 10 Km - 4 Km BT completed. Work stopped due to extreme cold weather being snow fall area.
No Image
Package-1 (Km-1 to 5)
Package-2 (Km-6 to 10)
1150
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 78.814 50 100.433 100.433 50.399 129.213 252.042 34% 34%
March - 2018
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed.
No Image
PK-93, Dir Upper (Gogyalto Karpat Abla 27 Km)
1151
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 597.77 78.812 50 71.477 71.477 68.088 146.9 468.958 22% 25%
March - 2018
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed, launching in progress (Kotkay bridge).
No Image
1) PK-91, Dir Upper (17.75 Km road)
2) RCC bridge Kotkay
1152
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 49.465 70 75.345 75.345 75.345 124.81 274.272 30% 32%
March - 2018
5 units - work in progress. Work stopped due to extreme cold weather/snow fall.
No Image
1. Ala Salamkot Road (06 Km)
2. Dobando Dara Road (10 km)
3. Nusrat Dara Road (9.80 Km)
4. Sharamkand Raod (4 Km)
5. Maj. General Sanaullah Shaheed Road (02 km)
1153
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 325.5 50.06 40 41.158 41.158 33.681 83.741 235.44 28% 26%
March - 2018
6 units (34.5 Km) - all in progress. Work stopped due to extreme cold weather/snow fall.
No Image
1) Kumrat road (8 Km)
2) Badgoai road (7 Km)
3) Jandrai road (4.5 Km)
4) Doog Dara road (7 Km)
5) Osorai Dara road (4 Km)
6) Kadi Khel Dara road (4 Km)
1154
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 19.5 10 16.362 16.362 7.95 27.45 270.5 10% 9%
March - 2018
Out of 8 units, all in progress. Work stopped due to extreme cold weather/snow fall.
No Image
1) Sultan Khel Dara left Molvi road BT road (4 Km)
2) Sultan Khel Dara right Kass Banda to Patwo road (4 Km)
3) Roghano Dara right Nasir Abad toJilar road (3 Km BT)
4) Karo Dara left Bandagai to Mastai Dehrai (3 Km BT)
5) Karo Dara right Gulibagh raod (2 Km BT)
6) Luqman Banda Adhoky Payeen and Bala road (2 Km)
7) Luqman Banda Safary road (3 Km BT)
8) Luqman Banda Main and Kamar Tall road (4 Km BT)
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 40 30 39.75 0.25 100% 80%
March - 2018
Length 2.5 Km - PCC 1 Km completed. Work stopped due to extreme cold weather/snow fall.
No Image
PK-91, Dir Upper (PCC road 25 Km)
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.55 48.55 48.55 58.05 180.5 10% 29%
March - 2018
Length 13 Km - earth work completed. Work stopped due to extreme cold weather/snow fall.
No Image
PK-93, Dir Upper (13 Km)
1157
(OG)
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 24.712 0 14.612 14.612 14.248 10.959 10.959 10.1 59% 44%
March - 2018
Piling and pile cap completed. Girder casted (single span bridge). Work stopped due to extreme cold weather/snow fall.
No Image
PK-92, Dir Upper
1158
(OG)
70210-Construction of Khan Abdul Wali Khan By-pass road District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 788.857 725.328 62.743 33.429 2.058 2.058 727.386 0.786 100% 92%
March - 2018
Completed (3.6 Km).
No Image
Khan Abdul Wali Khan By-pass road, Chitral
(3.6 Km Roads
RCC Bridge Gole (35 m)
RCC Bridge Molen (24 m))
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
30-11--1 30-11--1 - 30-11--1 - 1108.42 312.274 10 3 0.5 0 312.274 786.146 29% 28%
March - 2018
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension.
No Image
Booni Buzand Torkhow road (28 Km), Chitral
(Roads+
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen)
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
30-11--1 30-11--1 - 30-11--1 - 1108.42 0 100 100 0 0 0 1008.42 9% -
March - 2018
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/3 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension.
No Image
Booni Buzand Torkhow road (28 Km), Chitral
(Roads +
RCC Bridge Stan Gole
RCC Bridge WerkupGole
RCC Bridge Rayeen)
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
30-11--1 30-11--1 - 30-11--1 - 115.656 31.698 5.325 10.163 5.235 0 31.698 78.633 32% 27%
March - 2018
RCC bridge (1 span) in progress, 2 Km road work in progress (snowbound).
No Image
Garam Chashma Kandujal road i/c 2 brides
(2 Km Shingle Roads
RCC Bridge - 2 Nos
Land Acquisition)
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
30-11--1 30-11--1 - 30-11--1 - 199.75 20.183 30 20.325 5.325 0 20.183 0 - -
March - 2018
No Image
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 69.75 47.933 5.325 10.162 5.325 5.325 53.258 16.492 76% 76%
March - 2018
Length 4.5 Km - 3 Km BT completed.
No Image
Chamtalai to Toroghai road (4.50 Km)
1161
(OG)
140984-F/S, Design and Construction of RCC Bridge at Ayun, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 84.002 15 20 17.1 12.1 7.1 22.1 49.002 42% 26%
March - 2018
RCC Bridge (span 110 mtr), 24/32 piles, 1/4 pile cap completed, approach road 200 mtr completed.
No Image
RCC Bridge at Ayun, Chitral
1162
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 125.302 21.25 20 17.424 12.1 12.1 33.35 84.052 33% 27%
March - 2018
3 units: S# 1. Complted. S# 2 & 3: EW in progress (snow bound)
No Image
1) Construction of incomplete Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road
1163
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 423.106 42.805 21.503 69.591 69.591 19.1 61.905 358.798 15% 15%
March - 2018
3 units: S# 1: Finishing in progress S# 2 # 3: Cutting in progress
No Image
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads
1164
(OG)
170170-Rehabilitation of Internal Roads in Chitral and Drosh Cities District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 41.24 4.5 21.24 52.115 46.815 31.4 35.9 15.5 62% 87%
March - 2018
Length 5.5 Km (width 12 ft ) - 5 Km completed.
No Image
1) Chitral Sub Division Internal roads
2) Dorsh Sub Division Internal roads
1165
(OG)
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 550 128.143 179 185.914 141.164 109.74 237.883 242.857 56% 43%
March - 2018
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
1166
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 58.52 30 25.65 18.15 18.15 76.67 317.938 22% 19%
March - 2018
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
No Image
1) Bataira to Mirbat Road PK-62 (BW 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (BW 7 Km)
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
March - 2018
Length 210 m tr - 35/48 piles, 6/9 girder, left and right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
No Image
Dassu Kohistan
1168
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 17.5 20 17.1 7.1 7.1 24.6 62.5 38% 25%
March - 2018
Length 6 Km - Shingle road - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress.
No Image
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1169
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 19.3 30 43.584 43.584 34.108 53.408 150.7 25% 27%
March - 2018
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
No Image
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
3) BT of Pattan Bazar Road 4 Km
4) Construction of Baily/Wooden bridges in Dubair Nullah and Simo Darra Valley
5) Construction of shingle road Bankad in Rural area
6) Construction of Suspension Bridge over Sindh River in Jijal Mehreen (215 mtr)
1170
(OG)
150875-Construction of road from Shaha to Sput Valley, Gabar Naala Road and Dong Naala Road District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 80 8.402 10 8.55 6.05 6.05 14.452 61.598 23% 18%
March - 2018
Length 7 Km (shingle road) - 3 units - 1 earth work 100% completed, 2 work order issued (site disputed).
No Image
1) Construction of road from Soha to Sput 3 Km
2) Construction of Gabber Nullah road 2 Km
3) Construction of Dong Nullah road 2 Km
1171
(OG)
141025-F/S, Design and Construction of Road from Darman Tangay to Pashto Road, Battagram (5 Kms).
Battagram
30-11--1 30-11--1 - 30-11--1 - 69.8 35.87 33.05 33.05 33.05 16.525 52.395 0.88 99% 75%
March - 2018
Length 5 Km - 4 Km BT completed. 1 Km PCC in progress.
No Image
Battagram
1172
(OG)
150845-Construction / Improvement and Black topping of internal roads of Tehsil Battagram District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 136 0 15 23.189 23.189 23.189 23.189 121 11% 17%
March - 2018
22 units (14.6 Km) (PCC componenets) - all work in progress.
No Image
1) Beshkot Peza road UC Thakot 1 Km
2) Berser Peza road UC Thakot 1 Km
3) Shingli Bala approach rado UC Gijbori 1 Km
4) Oughaz Banda road UC Peshora 0.50 Km
5) Pomong road UC Peshora 0.70 Km
6) Tamai road UC Ajmera 0.40 Km
7) Gandoori road UC Ajmera 0.80 Km
8) Jabri Phagora road UC Rajdahari 0.80 Km
9) Kolai road UC Rajdahari 0.40 Km
10) Sarmast Kathora road UC Rajdahari 0.50 Km
11) Andarwali Neelishang road 0.50 Km
12) Sandasary Arghashori, Battagram approach road UC Battagram
13) Kotwal, Kot Ghari Bensar road Trand 0.90 Km
14) Hill, Kamola Battangi road UC Shamlai 0.90 Km
15) Shah Murad, Largam road UC Paimal Sharif 0.90 Km
16) Markhani Gat road UC Paimal Sharif 0.50 Km
17) Behram Abad Paimal road UC Paimal Sharif 0.40 Km
18) Jabri Paimal road UC Paimal Sharif 0.40 Km
19) Chatto Banda road UC Paimal Sharif 0.80 Km
20) Shalkhay Banda road UC Banian
21) Taya Jadeed road UC Banian 0.50 Km
22) Matta Joobar road 0.50 Km
1173
(OG)
150873-Construction / rehabilitation / widening road Chata Bata, Landay road, Chilar Sokadr, Sarkheli Banda, Chapar Gram Markhani and Batangi road District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 80 41.999 20 17.1 17.1 17.1 59.099 18.001 77% 74%
March - 2018
6 unit (6 Km) - earth work, PCC road, masonry work in progress.
No Image
1) Chata Bata road 1 Km
2) Landay road 1 Km
3) Chilar Sokar road 1 Km
4) ChappargramMarkhani road 1 Km
5) Batangi road 1 Km
6) Sarkhalai Banda road 1 Km
1174
(OG)
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 249.995 0 20 17.1 12.1 12.098 12.098 229.995 8% 5%
March - 2018
Length 13 Km (width 18 ft ) - work in progress (Km-7 to 13). Km 1-6 not started due to CPEC usage Bridge - 40 m - left abutment Work in progress.
No Image
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar
1175
(OG)
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 31.2 8.4 8.4 8.4 6.3 37.5 10.4 79% 75%
March - 2018
Length 4.8 Km - 2.5 Km completed. Remaining 2.3 Km WBM in progress.
No Image
PK-55, Mansehra
1176
(OG)
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Manshera.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 122.187 39.695 35.7 30.523 21.599 21.563 61.258 46.792 62% 50%
March - 2018
125.43 mtr -100 m bridge completed. Approach in progress.
No Image
PK-55, Mansehra
1177
(OG)
140676-F/S, Design and Construction of Sum Bridge, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 77.945 43.893 23.462 23.462 23.462 11.731 55.624 10.59 86% 71%
March - 2018
62.35 mtr - 12 working piles, 4 girders completed. Original scope of work completed. Revised scope (additional 2 spans) in progresss.
No Image
PK-55, Mansehra
1178
(OG)
140707-F/S, Design and Improvement of Road from Khaki to Fazalabad, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 65.692 39.058 39.058 39.058 19.529 85.221 0 100% 100%
March - 2018
Length 6.7 Km (width 18 ft) - BT completed.
No Image
PK-55, Mansehra (6.70 Km)
1179
(OG)
140920-F/S, design and Construction of (a) Chor Kalan road & (b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 46.818 20 17.1 17.1 12.1 58.918 53.182 56% 49%
March - 2018
Length 7.6 Km - (a) Chor Kalan road 3.6 Km - earth work (b) Jabbori to Methal Kayan road - 2 Km WBM completed. 1700 mtr site cut, earth work cutting 1.7 Km completed.
No Image
PK-56, Mansehra
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48