Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : February - 2018,

Showing Page Number : 40 of 47

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1150
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 380.856 78.814 50 50.433 50.433 30.216 109.03 252.042 34% 29%
February - 2018
Length 27 Km - cutting of 27 Km completed, WB of 5 Km completed.
ADP's Images
1151
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 597.77 78.812 50 68.787 68.787 30.0897 108.9017 468.958 22% 18%
February - 2018
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed, launching in progress (Kotkay bridge).
No Image
1152
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 393.737 49.465 70 55.155 55.155 42.35 91.815 274.272 30% 23%
February - 2018
5 units - work in progress.
ADP's Images
PK-91
1153
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 325.5 50.06 40 38.468 38.468 24.19 74.25 235.44 28% 23%
February - 2018
6 units - all in progress.
ADP's Images
PK-92
1154
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 300 19.5 10 13.672 13.672 6.05 25.55 270.5 10% 9%
February - 2018
Out of 8 units, all in progress.
No Image
PK-93
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 50 9.75 40 40 30 30 39.75 0.25 100% 80%
February - 2018
Length 2.5 Km - PCC 1 Km completed.
No Image
PK-91
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 200 9.5 10 48.544 46.05 46 55.5 180.5 10% 28%
February - 2018
Length 13 Km - earth work completed.
No Image
PK-93
1157
(OG)
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper.
Dir Upper
30-11--1 30-11--1 - 30-11--1 - 24.712 0 14.612 14.612 10.959 10.959 10.959 10.1 59% 44%
February - 2018
Piling and pile cap completed. Girder casted (single span bridge).
No Image
PK-92
1158
(OG)
70210-Construction of Khan Abdul Wali Khan By-pass road District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 788.857 725.328 62.743 33.429 2.058 2.058 727.386 0.786 100% 92%
February - 2018
Completed (3.6 Km).
No Image
Chitral
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
30-11--1 30-11--1 - 30-11--1 - 1108.42 312.274 10 3 0.5 0 312.274 786.146 29% 28%
February - 2018
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 Km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension.
ADP's Images
Chitral
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
30-11--1 30-11--1 - 30-11--1 - 1108.42 0 0 0 0 0 0 1108.42 - -
February - 2018
Original approval for Rs.279.922 m. PSDP sha.re - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 17 km completed, structure work 60% in progress. Land clearnce 6 km not yet cleared by DC office. Work on 2/4 No. RCC bridge in progress. Work on 5 km cutting in progress. Time extension submitted to CDWP. Releases will be made after approval of time extension.
ADP's Images
Chitral
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
30-11--1 30-11--1 - 30-11--1 - 115.656 5.142 5.325 10.163 5.235 0 5.142 105.189 9% 4%
February - 2018
RCC bridge (1 span ) in progress, 2 Km road work in progress (snowbound)
ADP's Images
Garam Chashma Kandujal road i/c 2 brides
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
30-11--1 30-11--1 - 30-11--1 - 199.75 20.183 30 20.325 5.325 0 20.183 0 - -
February - 2018
No Image
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 69.75 47.933 5.325 10.162 5.325 5.325 53.258 16.492 76% 76%
February - 2018
Length 4.5 Km - 3 Km BT completed.
No Image
Chamtali to Toroghai road Swat
1161
(OG)
140984-F/S, Design and Construction of RCC Bridge at Ayun, Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 84.002 15 20 17.1 12.1 7.1 22.1 49.002 42% 26%
February - 2018
RCC Bridge Span 110 m , 24/32 piles , 1/4 pile cap complted , Appropach road 200 m complted
ADP's Images
Chitral
1162
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 125.302 21.25 20 17.424 7.1 7.1 28.35 84.052 33% 23%
February - 2018
Out of 3 units, 1 unit complted . 2 unit in progress (snow bound )
No Image
1) Mulkow road
2) Boni Bridge to Boni Bazar Chowk
3) Boni Bazar Chowk to Govt Rest House road
1163
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 423.106 42.805 21.503 39.591 39.591 16.034 58.839 358.798 15% 14%
February - 2018
Out of 3 units, 2 units complted 1 unit in progress
ADP's Images
1) Wajijun to Terich road (2 Km)
2) Kosht to Lone road (3 Km)
3) Junjerat to Junjerat Koh road (7 Km)
1164
(OG)
170170-Rehabilitation of Internal Roads in Chitral and Drosh Cities District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 41.24 4.5 21.24 52.115 46.815 31.4 35.9 15.5 62% 87%
February - 2018
Length 5.5 Km (width 12 ft ) - 5 km completed.
ADP's Images
1) Chitral Sub Division Internal roads
2) Dorsh Sub Division Internal roads
1165
(OG)
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral.
Chitral
30-11--1 30-11--1 - 30-11--1 - 550 128.143 179 185.914 96.414 96.414 224.557 242.857 56% 41%
February - 2018
9/9 roads completed. 2/9 bridges completed. 6/9 bridges in progress. 1 retendering (Osiak) 5th time.
ADP's Images
1) 9 Nos Bridges
2) 9 Nos Roads
1166
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 406.458 58.52 30 25.65 18.15 18.15 76.67 317.938 22% 19%
February - 2018
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
ADP's Images
1) Bataira to Mirbat Road PK-62 (B/W 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (B/W 7 KM)
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 322.534 153.755 112.653 112.653 56.327 6.859 160.614 56.126 83% 50%
February - 2018
length 210 m - 35/48 piles, 6/9 girder, left and Right abutment completed. Right approach road earth work completed. 1/2 pier in progress.
ADP's Images
1168
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 100 17.5 20 17.1 7.1 7.1 24.6 62.5 38% 25%
February - 2018
Length 6 Km- Shingl road- - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress.
ADP's Images
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1169
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 200 19.3 30 40.894 40.894 34.108 53.408 150.7 25% 27%
February - 2018
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
ADP's Images
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
1170
(OG)
150875-Construction of road from Shaha to Sput Valley, Gabar Naala Road and Dong Naala Road District Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 80 8.402 10 8.55 6.05 6.05 14.452 61.598 23% 18%
February - 2018
Length 7 Km (shingle Road ) - 3 units - 1 earth work 100% completed, 2 work order issued (site disputed).
ADP's Images
1) Construction of road from Soha to Sput 3 Km
2) Construction of Gabber Nullah road 2 Km
3) Construction of Dong Nullah road 2 Km
1171
(OG)
141025-F/S, Design and Construction of Road from Darman Tangay to Pashto Road, Battagram (5 Kms).
Battagram
30-11--1 30-11--1 - 30-11--1 - 69.8 35.87 33.05 33.05 16.525 16.525 52.395 0.88 99% 75%
February - 2018
Length 5 Km - 4 Km BT completed. 1 Km PCC in progress.
ADP's Images
Battagram
1172
(OG)
150845-Construction / Improvement and Black topping of internal roads of Tehsil Battagram District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 136 0 15 20.508 20.508 20.508 20.508 121 11% 15%
February - 2018
22 units(14.6 Km) (PCC componenets all) - work in progress.
ADP's Images
1) Beshkot Peza road UC Thakot 1 Km
2) Berser Peza road UC Thakot 1 Km
3) Shingli Bala approach rado UC Gijbori 1 Km
4) Oughaz Banda road UC Peshora 0.50 Km
5) Pomong road UC Peshora 0.70 Km
6) Tamai road UC Ajmera 0.40 Km
7) Gandoori road UC Ajmera 0.80 Km
8) Jabri Phagora road UC Rajdahari 0.80 Km
9) Kolai road UC Rajdahari 0.40 Km
10) Sarmast Kathora road UC Rajdahari 0.50 Km
11) Andarwali Neelishang road 0.50 Km
12) Sandasary Arghashori, Battagram approach road UC Battagram
13) Kotwal, Kot Ghari Bensar road Trand 0.90 Km
14) Hill, Kamola Battangi road UC Shamlai 0.90 Km
15) Shah Murad, Largam road UC Paimal Sharif 0.90 Km
16) Markhani Gat road UC Paimal Sharif 0.50 Km
17) Behram Abad Paimal road UC Paimal Sharif 0.40 Km
18) Jabri Paimal road UC Paimal Sharif 0.40 Km
19) Chatto Banda road UC Paimal Sharif 0.80 Km
20) Shalkhay Banda road UC Banian
21) Taya Jadeed road UC Banian 0.50 Km
22) Matta Joobar road 0.50 Km
1173
(OG)
150873-Construction / rehabilitation / widening road Chata Bata, Landay road, Chilar Sokadr, Sarkheli Banda, Chapar Gram Markhani and Batangi road District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 80 41.999 20 17.1 12.1 12.1 54.099 18.001 77% 68%
February - 2018
6 unit (6 Km) - earth work, PCC road, masonry work in progress.
ADP's Images
1) Chata Bata road 1 Km
2) Landay road 1 Km
3) Chilar Sokar road 1 Km
4) ChappargramMarkhani road 1 Km
5) Batangi road 1 Km
6) Sarkhalai Banda road 1 Km
1174
(OG)
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram.
Battagram
30-11--1 30-11--1 - 30-11--1 - 249.995 0 20 17.1 12.1 12.098 12.098 229.995 8% 5%
February - 2018
Length 13 Km (width 18 ft ) - Work in progress (Km-7 to 13). KM 1-6 not stated due to CPEC usage Bridge - 40 m - left abutment Work in progress.
ADP's Images
1) Design and supervision charges etc
2) Improvement/rehabilitation of Oghi Battagram road 13 Km
3) Construction of RCC Bridge at Biari Khawar
1175
(OG)
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 50 31.2 8.4 8.4 6.3 6.3 37.5 10.4 79% 75%
February - 2018
Length 4.8 Km - 2.5 Km completed. Remaining 2.3 Km WBM in progress.
No Image
PK-55, Mansehra
1176
(OG)
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Manshera.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 122.187 39.695 35.7 30.523 21.599 21.54 61.235 46.792 62% 50%
February - 2018
125.43 mtr -100 m bridge completed. Approach in progress.
No Image
PK-55, Mansehra
1177
(OG)
140676-F/S, Design and Construction of Sum Bridge, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 77.945 43.893 23.462 23.462 11.731 11.731 55.624 10.59 86% 71%
February - 2018
62.35 mtr - 12 working piles, 4 girders completed. Original scope of work completed. Revised Scope (additional 2 spans ) in progresss,
No Image
PK-55, Mansehra
1178
(OG)
140707-F/S, Design and Improvement of Road from Khaki to Fazalabad, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 80 65.692 39.058 39.058 19.529 19.529 85.221 0 100% 100%
February - 2018
Length 6.7 Km 9width 18 ft) - BT completed.
No Image
PK-55, Mansehra (6.70 Km)
1179
(OG)
140920-F/S, design and Construction of (a) Chor Kalan road & (b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 120 46.818 20 17.1 12.1 12.1 58.918 53.182 56% 49%
February - 2018
Length 7.6 Km - (a) Chor Kalan road 3.6 Km - earth work (b) Jabbori to Methal Kayan road - 2 Km WBM completed. 1700 mtr site cut, earth work cutting 1.7 Km completed.
No Image
PK-56, Mansehra
1180
(OG)
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 35 7.75 20 20 10 10 17.75 7.25 79% 51%
February - 2018
length - 3.6 km (width 18 ft ) 3 units - earth work 80% completed, structure work in progress.
No Image
1) Construction/BT of road Darband to Kandran UC Shanaya (2 Km) PK-57
2) Construction/BT of road Gali Badral to Labor UC Perhina (0.60 Km) PK-57
3) Construction/BT of road Lassan to Khamian UC Sawan Mera (1 Km) PK-57
1181
(OG)
150843-Construction of PCC Roads (a) Seri Goria (b) Batkarar (c) village Manshera Miangan (d) village Pondnial (e) Tambeela (f) Ismail Bandi and Shingle road village Ramkot UC Shergarh, Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 17 10.212 6.538 6.538 4.904 4.904 15.116 0.25 99% 89%
February - 2018
Completed (2.2 Km) ( 4 units) PCC roads
No Image
1) Construction of PCC road Darband to Mehran UC Darband UC Darband (0.40 Km) PK-57
2) Construction of PCC road Karori to Kharyala UC Karori (0.40 Km) PK-57
3) Construction of PCC road Kotla Batsangar Gali UC Bandi Shungli (0.65 Km) PK-57
4) Construction of PCC road Mohar to Lassan UC Sawan Mera (0.75 Km) PK-57
1182
(OG)
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 100 12.25 10 8.55 6.05 6.05 18.3 77.75 22% 18%
February - 2018
Length 7 Km (2 units ) - 3 km BT complted.
No Image
PK-53, Mansehra
1183
(OG)
150870-Improvement / carpeting of road from Dhodial to Shatay Road, Baffa Doraha to Khwajgan and Dhodial to Shatay Road PK-55 District Manshera.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 100 19.65 10 12.1 9.6 9.6 29.25 70.35 30% 29%
February - 2018
Length 7 Km - 4.9 km completed.
No Image
PK-55, Mansehra
1184
(OG)
150871-Construction / Rehabilitation of Oghi to Ahl, Malkan Bridge Kalban ? Shakora Gali and Lal Wali, Shahkot Chulandrain and Jishkot, Chattar - Raitra, Khabal Nambal Gali - Bangla, Khabal near HQ Malaik Fazal, Patarian - Patarian Mor - Kangan Shairf, Chappra Bala and Jacha Road Chajri, District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 103.5 33.436 70.114 70.114 35.057 34.715 68.151 0 100% 66%
February - 2018
Length 9 Km (10 units) - earth work structure work, road work in progress.
No Image
1) BT/rehabilitation of Oghi to Ahl road UC Kathai (1 Km) PK-56
2) PCC Chulandrian road UC Battal (1 Km) PK-56
3) PCC Jiskot road UC Dilbori (1 Km) PK-56
4) PCC Retira road UC Chattar Plain (1 Km) PK-56
5) BT/rehabilitation of Chapra Bala and Payen road UC Battal (1 Km) PK-56
6) PCC Jacha road UC Jabbar Devli (1 Km) PK-56
7) PCC Chijri road UC Belian (1 Km) PK-56
8) PCC Khabal road UC Dilbori (1 Km) PK-56
9) PCC Shahkot and Chulandrian road UC Kathai (2 Km) PK-56
1185
(OG)
150949-Construction / Rehabilitation of roads Sufaida, Ghania Kangu, Arbora Batta Syedan, Deedwar Tarwai, Sheikh Abad, Guldheri, Titoli, Gorian and Belian road District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 100 44.905 20 27.283 27.283 26.116 71.021 35.095 65% 71%
February - 2018
Length 9 Km - 4 Km completed, earth work completed, structure work 80% completed, road work 50% completed.
No Image
1) BT/rehabilitation of Safaida road UC Oghi (1 Km) PK-56
2) PCC Ghania Kango road UC Dilbori (1 Km) PK-56
3) PCC Arbora Batta Sydan road UC Oghi (1 Km) PK-56
4) PCC Deedwar/Tarwi road UC Dilbori (1 Km) PK-56
5) BT/rehabilitation of Tatoli road UC Kathai (1 Km) PK-56
6) BT/rehabilitation of Belian road UC Belian (2 Km) PK-56
7) BT/rehabilitation of Hawagali road UC Shamdara (1 Km) PK-56
8) PCC Sheikh Abad/Guldhery road UC Belina (1 Km) PK-56
9) PCC Gorian road UC Dilbori (1 Km) PK-56
1186
(OG)
160190-Rehabilitation of Saiful Malook Road (8.55 Kms), District Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 152 101.995 10 2.5 0 0 101.995 40.005 74% 67%
February - 2018
2nd Revised PC-I/DCE for Rs.263.331 m submitted to SOR on 27/07/2016. DG M&E conducted inspection through DMO and submitted their report. Report submitted by DMO. Under process with TC-KP.
No Image
Mansehra
1187
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 80 56.95 30 27.357 27.357 24.17 81.12 0 100% 100%
February - 2018
Length 5 Km - earth work 100%, structure work 80%, road work 20%, WBM completed.
No Image
PK-47, Abbottabad
1188
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 324.287 77.5 10 38.55 36.05 36.05 113.55 236.787 27% 35%
February - 2018
Length 26 Km (5-units) - earth work, structure work in progress.
No Image
1) Improvement/expansion and BT of Kahu to Julial road (2 Km) PK-45
2) Construction of road from Jandal to Lower Palak road (6 Km) PK-45
3) Improvement and BT of road from Mumbal to Kurli road (4 Km) PK-45
4) Improvement and BT of road from Butti to Lower Surjal Dana raod (10 Km) PK-45
5) Rehabilitation of flood damage road i/c bridge at Hoterol to BHU Mohra (4 Km) PK-45
1189
(OG)
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 65 0 63.478 63.478 31.739 25.853 25.853 1.522 98% 40%
February - 2018
2 Packages - earth work completed. Sub base in progress. Site disputed by locals regarding land. Site disputed.
No Image
1) Package-1 - 0+00 - 2+00 (2 Km)
2) Package-2 - 2.2+00 - 3+500 (1.50 Km)
1190
(OG)
140880-PPC / Imp / Rehab / Widening of (a) Maira Kalan Village road (b) Parr Nakkar to Kahala Kai Surmalagali Helipad road, (c) Jaster Village road, (d) Noormang Village road and (e) GGMS Tharyati road, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 57.166 32.25 25 25.854 25.854 18.034 50.284 0 100% 88%
February - 2018
Length 7.5 Km - work in progress (5 units).
No Image
1) Improvement and pavement of Maira Kalan village road PK-48
2) Construction/improvement and pavement of Parr Nakkar to Kohala Kai Surmagali Helipad road PK-48
3) Improvement and pavement of Jaster village road
4) Improvement and pavement of Noormong village road
5) PCC/widening/improvement of road from GMS Tharyati
1191
(OG)
140881-F/S, Design, BT and Extention of road from Sujal Kot to Thesi (8 Km), Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 80 33.136 50 44.884 44.884 28.078 61.214 0 100% 77%
February - 2018
Length 8 Km - earth work 80%, masnory work 45% completed. Revised DCE for Rs. 126 M submitted to P&D
No Image
Abbottabad
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 28.92 21.69 21.69 41.06 0.75 98% 84%
February - 2018
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46, Abbottabad
1193
(OG)
140883-F/S, Design & BT of roads (a) Nakka Galli Khuthialla to Mubaraka (b) Chaitri to Sher Bai Mangal Bridge viz Bandi Matrach (c) Gramry including Siyal Sargal UC Pawa, District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 228.89 37.932 40 39.322 39.322 24.73 62.662 150.958 34% 27%
February - 2018
Length 19.5 Km - out of 4 units, all 4 in progress.
No Image
1) Nakka Galli Khutialla to Murbaraka (5 Km) PK-46
2) Gramry UC Pawa (6 Km) PK-46
3) Siyal UC Pawa (4 Km) PK-46
4) SargalUC Pawa (3.5 Km) PK-46
1194
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi ? Chanali road via Seri, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 180.78 47.28 20 20.515 20.515 20.514 67.794 113.5 37% 38%
February - 2018
Length 8 Km - out of 3 units, all in progress.
No Image
1) Arro Kas Summa to Lora viaa Banwari PK-48
2) Improvement/widening and BT of Tajwal to Bagan road PK-48
3) Garhi - Chanali road via Seri, Abbottabad PK-48
1195
(OG)
140981-Construction / Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in PK-44, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 219.66 80.25 50 65.152 65.152 58.04 138.29 89.41 59% 63%
February - 2018
Length 20 Km - all 22 units, all in progress.
No Image
1) Construction of road from near Modern Public School (1 Km) PK-44
2) Sir Syed Colony road Street No.8 and 9 (0.550 mtr) PK-44
3) Shahzada Masjid to Banda Sinjilan (2 Km) PK-44
4) Karbala Chowk Kehal to Usmania Masjid (1 Km) PK-44
5) Narduba road (1 Km) PK-44
6) Banni to Maira Mandroach road (1 Km) PK-44
7) Township Basali road (dozer work) (1 Km) PK-44
8) Lambi Dehri to Banda Dilazak road (1 Km) PK-44
9) Sheikhulbandi road (1 Km) PK-44
10) Gojre Maira road (1 Km) PK-44
11) Hassa Zai Mansoor road Orash Colony road (1 Km) PK-44
12) Main link road Pul to Masjid Narriyan (1 Km) PK-44
13) Kunj Mirpur road (0.650 mtr) PK-44
14) Sarban Kothera road (3.25 Km) PK-44
15) Kala Pul Chona road (2.25 Km) PK-44
16) Main line road Dhamtor (1 Km) PK-44
17) PCC with sewerage line Oresh Colony road PK-44
18) PCC road sewerage line Jogan PK-44
19) PCC road sewerage line Dhodial PK-44
20) Construction of Comsat University road PK-44
21) Construction of sewerage line Kehal Ward-10 to 15 road PK-44
22) PCC with sewerage line from Kehal Chowk to Qabristan PK-44
1196
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islamkot road, Booji road, Mirpura road, Blolia / Dana road, Dna Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 200.064 54.62 50 49.152 49.152 40.464 95.084 95.444 52% 48%
February - 2018
Out of 9 units, 9 units in progress.
No Image
1) Guldok Dhamtour Bridge Span 30 m
2) Beer Banda Nabi road
3) Maira Muzaffar raad
4) Lower Islam Kot road
5) Booji road
6) Mirpur road
7) Bilolia/Danna road
8) Danna Maira Mandroch
9) Mandroch
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47