Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : December - 2016,

Showing Page Number : 35 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
992
(OG)
150787-Widening / BT of Road from (a) Shahpoor to Logay (1.85 Km) (b) Banr Khuwargai Bazaar to Banr Kalay, District Shangla.
Shangla
- - - 07-04-16 - 50 0 5 5 2.5 0.477 0.477 45 10% 1%
December - 2016
Work started.
993
(OG)
150789-Construction of Butyal to Khattak Sar (1 Km), Koz Kanra to Uch Lass road (1 Km) District Shangla.
Shangla
- - - 07-04-16 - 50 0 5 5 2.5 0.515 0.515 45 10% 1%
December - 2016
2 units - 1 work started, 1 site disputed.
994
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
- - - 02-11-15 - 148.761 16.139 5 18.655 16.155 16.155 32.294 127.622 14% 22%
December - 2016
4 units - all earth work in progress.
Namenclature changed.
995
(OG)
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km).
Swat
HW
28-07-14 - - 03-04-14 - 838.228 538.73 60 141.427 111.427 111.427 650.157 239.498 71% 78%
December - 2016
Out of 59 Km, 55 Km completed. Matta Fazil Banda Section - (12/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress.
1) Matta Fazal Banda (Km-1 & 2)
2) Matta Fazal Banda (Km-3 to 23.5)
3) Matta Fazal Banda constn of 16 meter span bridge at Km-5 & 8
4) Bagh Dehrai Rahat Kot Road (2.50-KMs)
5) Ghari Lalkoo Road (KM-1)
6) Ghari Lalkoo Road (KM-2 to 4) 3-KMs
7) Rehabilitation of BerYum Shawar Gat Road (22-KMs)
996
(OG)
140682-F/S, Design and Construction of Baryam to Gat Serai Road, Arkot to Biakand Road and Kabal to Kalla Kallay Road (20 Km), District Swat.
Swat
HW
04-06-15 - - - - 219.095 111.25 150 150 62.5 62.5 173.75 0 100% 79%
December - 2016
Length 20 Km - 10.5 Km completed, structure work in progress. Revised DCE submitted to CE North for Rs.300 m (ADP cost) on 07/09/2016. Approved. AA awaited.
997
(OG)
140688-F/S, Design, Construction and Improvement / Rehabilitation of Mingora City Road i/c Bridge, District Swat.
Swat
HW
06-08-15 - - 30-04-15 - 80 23.067 5 42.31 39.81 28.015 51.082 51.933 35% 64%
December - 2016
Length 4.8 Km - 5/5 packages - in progress. 0.6 Km BT completed. Road and structure work in progress.
998
(OG)
140963-F/S, Design & Rehabilitation of Marghuzar to Mingora Road, Swat.
Swat
HW
01-07-15 30-06-17 - 13-02-15 - 50 24.197 25.803 28.391 15.488 14.773 38.97 0 100% 78%
December - 2016
Length 4 Km - WC completed, PCC drains and shoulders in progress.
999
(OG)
140964-F/S, Design & Rehabilitation / BT of Kalam to Gujar Gabral road (flood damaged), Swat.
Swat
HW
- - - 03-11-16 - 414.267 0 200 149.25 0.5 0 0 214.267 48% -
December - 2016
Pre-qualification invited on 20/12/2016, sent to consultant for evaluation.
1000
(OG)
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat.
Swat
HW
- - - 03-11-16 - 135.93 0 5 14.674 12.174 0 0 130.93 4% -
December - 2016
Pre-qualification of contractors approved on 10/01/2017. Tender invited for pre-qualified contractor.
1001
(OG)
140968-F/S, Design & Construction of (a) Chapryal to Balasoor road, (b) Kherarai to Mandoor road, (c) Durash Khela to Baz Khela, (d) Mandal Daag Road & (e) Venai to Aghal road, (f) Dedpanai Village Road, Swat.
Swat
HW
01-06-15 - - 07-01-15 - 140 30.123 5 5 2.5 2.5 32.623 104.877 25% 23%
December - 2016
Length 14 Km - BT 2.8 Km completed. Pack-1 - structure work, road work in progress. Pack-2 - structure work, road work in progress. Pack-3 - structure work, WBM in progress.
1002
(OG)
140969-F/S, Design & Construction of (a) Qalagy road UC Qalagy (b) Tall Chor Road UC Tall (c) Taran Road UC Kaley & (d) Talang Churkhai Road UC Kota, Swat (5 Km).
Swat
HW
28-08-15 - - 30-04-15 - 100 15 5 37.772 35.272 2.5 17.5 80 20% 18%
December - 2016
Length 5 Km - 2 Km completed, Work in progress (4 units). Revised PC-I/DCE for Rs.89.980 m submitted to SE on 15/08/2016.
1003
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat.
Swat
HW
04-04-16 - - 02-11-15 - 450 25 25 39.937 27.437 27.437 52.437 400 11% 12%
December - 2016
Pack-1 (Km-1 to 7) - WBM Km-1 and 2 started, 1.3 Km BT. Pack-2 (Km-8 to 14) - earth work in progerss. Pack-3 (Km-15 to 20.75) - earth work in progress.
1004
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
HW
03-08-15 - - 11-02-15 - 628.354 22.733 30 139.24 124.24 13.24 35.973 575.621 8% 6%
December - 2016
Length 35 Km - earth work in progress. Court case.
1005
(OG)
150805-Const / Repr / Reh / BT of Rahmabd Chwk-Watky Chwk, Main Gulkda, Sharifabad Quanj, Sharifabad Dheri, Hayatabad Internal, Shahidabad, Shahedabad from DAEWO Terml, Qambr Bypass-Marghozar Twn, Bhrma Khwargi, Sarinagar Twn, Yusafabad, Latifabad Mahronsh Twn, SKHA Clina, Landi Kas Swat.
Swat
HW
08-06-16 - - 09-02-16 - 199.99 0 5 10.462 7.962 7.913 7.913 194.99 3% 4%
December - 2016
14 units - 12 work order issued, 2 work started.
a) Rahim abad Chowk Amankot to Watkay Chowk
b) Main Road Gulkada UC Gulkada
c) Sharif Abad Quanj Road UC Gulkada
d) Sharif Abad Dherai Road UC Gulkada
e) Hayatabad Internal Roads UC Shahdara
f) Shahid Abad Road
g) Shaheed Abad road from Daewoo Bus Terminal UC Rahim Abad
h) Qambar Bypass to Marghazar Town Road UC Rahim Abad
i) Bharama Khwargai Road UC Rangmohallah
j) Sarinagar Town UC Rangmohallah
k) Yousaf Abad Road UC Banr
l) Latif Abad Road Mahronesh Town UC Banr
m) Skha China Road UC Amankot
n) Landikass Road UC Landikass
 
1006
(OG)
150811-Const of road Ghalagay Dara Bypass, Balokaly to Jurbdy, Shingray to Zaray, Gogdara to Left Panjigrm, Rashaka to Topsin Sabonay, Amlok Dara to Sar Paty, Manglawar to Kas Shingral, Kas to Zary Kachakor, Ogahz, Jabba Bishbanr Gat, Sher Atraf Karbakar, Challganoray road, Qambar Road, Swat.
Swat
HW
22-04-16 - - 03-11-16 - 198.41 15 5 19.373 16.873 16.873 31.873 178.41 10% 16%
December - 2016
Length 19.5 Km (16 components) - 15 in progress, 1 financial bids approval under process.
1007
(OG)
150812-Construction of road from Nusrat Chowk to Langarr Chowk, Shamozai Jabbagai road District Swat.
Swat
HW
- - - 03-11-16 - 200 0 5 3.095 0.595 0 0 195 3% -
December - 2016
Pre-qualification of contractors approved on 10/01/2017. Tender invited.
1008
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction/Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
01-03-16 - - 10-09-15 - 280 3.75 15 61 51 22.114 25.864 261.25 7% 9%
December - 2016
5 units - in progress. Revised PC-I/DCE for Rs.280 m submitted to Chief Infra on 22/12/2016. Pre-PDWP held.
1009
(OG)
150817-Construction / Rehabilitation / BT of Koray to Deran Patay Road, Hakeem Abad Darmay road, Sardan Road, Gamser road, Batkoo road, Azad Banda Road, Kharkai Koat road, Mula Patay road, Swat.
Swat
HW
10-02-16 - - 10-09-15 - 200 17.55 5 8.75 6.25 6.25 23.8 177.45 11% 12%
December - 2016
Length 15.9 Km - 8 units - in progress.
1010
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 0 5 15.924 10.924 0 0 226.52 2% -
December - 2016
Pre-qualification of contractors approved on 10/01/2017, tender invited.
1011
(OG)
150947-Construction of Mingora Kokray Marghuzar road District Swat.
Swat
HW
10-02-16 - - 20-08-15 - 45 10 20 20 10 10 20 15 67% 44%
December - 2016
Length 2.6 Km - WC completed. Ancillary works in finishing stage.
1012
(OG)
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II).
Dir Lower
24-10-14 - - 10-10-13 - 126.085 74.194 5 3.75 1.25 1.25 75.444 46.891 63% 60%
December - 2016
Length 7.8 Km - 2.8 Km completed. 2 Km sub base, WBM completed.
1013
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 117.735 30 58.193 58.193 58.083 175.818 1062.835 12% 15%
December - 2016
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km.
1014
(OG)
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower.
Dir Lower
19-08-15 - - 28-01-15 - 162.54 20 10 10 5 5 25 132.54 18% 15%
December - 2016
Length 15 Km - out of 4 packages, all in progress.
1015
(OG)
140901-F/S, Design & Construction of Talash Kalpanai Bypass road (10 Km), Dir Lower.
Dir Lower
- - - 11-02-15 - 350 7.5 10 5 0 0 7.5 332.5 5% 2%
December - 2016
Land acquisition under process. Section-4 completed. Award not yet finalized.
1016
(OG)
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower.
Dir Lower
06-08-15 - - 28-01-15 - 174.826 65.25 15 36.833 29.333 25.597 90.847 94.576 46% 52%
December - 2016
Out of 4 bridges, all in progress (Agharily, Arif Killi, Darangal Khwar, Markhani Maidan bridges).
1017
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
- - - 03-11-16 - 99.296 0 5 5 0 0 0 94.296 5% -
December - 2016
Pre-qualification invited on 28/12/2016. Revised PC-I/DCE submitted.
RCC Bridges in Dir Lower (4 Nos) (a) RCC Bridge at Munjai
1018
(OG)
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower.
Dir Lower
- - - 02-11-15 - 199.796 10 5 16.36 17.61 16.25 26.25 184.796 8% 13%
December - 2016
Length 12 Km - work in progress on all 6 units.
1019
(OG)
150838-Construction of RCC bridges Raidgay (Kotkay) & Gul Khawarr Maidan Dir Lower.
Dir Lower
- - - 03-11-16 - 190.549 0 5 5 0 0 0 185.549 3% -
December - 2016
Pre-qualifcation called on 28/12/2016.
RCC Bridges in Dir Lower (a) RCC Bridge at Raidgay (Kotkay) (b) RCC Bridge at Gul Khawar Maidan
1020
(OG)
150839-Const of (a) Asband Swat (3 Km) (b) Shursheen (c) Joro Kashmir (2 Km) (d) Ghazo Chat Pat (e) Deghan (1 Km) (f) Dheri Tesko (3 Km) (g) Oskai (1.5 Km) (i) Laiko (1 Km) (j) Naw Kalay Bochake (2 Km) (k) Mayar Dogha (2 Km) Dir Lower.
Dir Lower
- - - - - 139.251 8.75 250 234.579 72.079 48.17 56.92 0 100% 41%
December - 2016
Out of 4 roads, all in progress. Rev DCE approved on 02/12/2016. AA awaited.
1021
(OG)
150963-Construction / Rehabiliation of roads Pato Atak & Barikot, Rabat Assigay Laram Danda, Sarbanda, Dod Khana, Shati, Mali, Watangay, Malakand Kohrey, Gadla, Banda, Karam Khel, Sparay, Danwa, Rani & Ghwaago Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 369.278 15 20 78.886 60.136 59.936 74.936 334.278 9% 20%
December - 2016
Out of 17 units, work in progress in all 17 units.
1022
(OG)
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 367.574 15 20 73.424 54.674 53.754 68.754 332.574 10% 19%
December - 2016
Out of 20 units, all in progress.
1023
(OG)
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower.
Dir Lower
- - - 02-11-15 - 275.308 5 5 13.193 10.693 10.693 15.693 265.308 4% 6%
December - 2016
Out of 18 units, all in progress.
1024
(OG)
150966-Construciton of RCC Bridge at Matako Rahim Abad District Dir Lower.
Dir Lower
- - - 08-08-16 - 49.733 0 15 15 3.75 3.75 3.75 34.733 30% 8%
December - 2016
Work started.
1025
(OG)
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower.
Dir Lower
- - - 02-11-15 - 278.061 12.5 5 29.579 30.829 27.287 39.787 260.561 6% 14%
December - 2016
Out of 6 units, work in progress on all units.
1026
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper.
Dir Upper
11-10-12 - - 11-02-15 - 255.368 157.004 5 5 2.5 0 157.004 93.364 63% 61%
December - 2016
10 Km - earth, structure, road work completed. 5 Km road surfacing PCC completed.
PK-92 (Km-1 to 10)
1027
(OG)
130577-Construction of 3 Nos RCC Bridges i.e. Surbat, Dogai and Garonai District Dir Upper.
Dir Upper
- 30-06-17 - 03-12-14 - 81.095 57.176 23.919 23.919 11.958 11.924 69.1 0 100% 85%
December - 2016
All 3 bridges in progress. Abutmnet completed. Launching in progress.
1) Surbat bridge
2) Dogal bridge
3) Garawonai bridge
1028
(OG)
140648-Construction of RCC Bridge at Khal Barkalay Bazaar PK-93 District Dir Upper.
Dir Upper
- 30-06-17 - 16-12-14 - 53.699 43.158 10.541 10.541 5.27 5.27 48.428 0 100% 90%
December - 2016
36/36 pile, 23/23 piles, right side abutment, 2/2 pile shift, 8/20 girders completed, 15 girders casted.
1029
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 - - 22-01-15 - 120 20 10 31.848 26.848 26.347 46.347 90 25% 39%
December - 2016
Length 8 Km - earth work, structure work in progress.
1030
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 - - 22-01-15 - 100 20 15 28.655 21.155 12.527 32.527 65 35% 33%
December - 2016
Length 5 Km - structure work on both side in progress.
1031
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 166.565 20 5 5 2.5 2.05 22.05 141.565 15% 13%
December - 2016
Length 10 Km - earth, structure work in progress.
1032
(OG)
140905-Construction of PCC Roads at Usherai Dara (10 Km), Dir Upper.
Dir Upper
01-07-15 - - - - 166.99 20 50 50 25 25 45 96.99 42% 27%
December - 2016
Length 10 Km - structure work on both side, PCC road in progress.
1033
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
- - - 11-02-15 - 380.856 66.7 10 10 5 4.067 70.767 304.156 20% 19%
December - 2016
Length 27 Km - earth work, structure work, sub base in progress.
1034
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
- - - 25-03-15 - 597.77 65.359 10 15.462 10.462 7.959 73.318 522.411 13% 12%
December - 2016
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed (Kotkay bridge).
1035
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
- - - 02-11-15 - 279 3.75 5 45.965 43.465 42.964 46.714 270.25 3% 17%
December - 2016
5 units - work in progress.
PK-91
1036
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
- - - 02-11-15 - 325.5 15 5 32.31 29.81 26.924 41.924 305.5 6% 13%
December - 2016
6 units - all in progress.
PK-92
1037
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
- - - 21-01-16 - 300 10 10 10 7.5 7.493 17.493 280 7% 6%
December - 2016
Out of 8 units, all in progress.
PK-93
1038
(OG)
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper.
Dir Upper
- - - - Line Deptt 100 0 5 5 0 0 0 0 - -
December - 2016
Fresh directive issued for 3 bridges on 24/11/2016, summary submitted to CA for approval for enhancement of ADP cost. Decision awaited.
PK-91
1039
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
- - - 16-10-15 - 50 5 5 5 2.5 2.5 7.5 40 20% 15%
December - 2016
Length 25 Km - earth work, structure work in progress.
PK-91
1040
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
- - - 09-02-16 - 200 0 10 10 5 5 5 190 5% 3%
December - 2016
Earth work in progress.
PK-93
1041
(OG)
151082-Construction of Bridge on Patrak-Kumrat Road.
Dir Upper
- - - - - 24.712 0 10 10 0 0 0 14.712 40% -
December - 2016
Tender approval under process. Will be approved by 12/01/2017.
PK-92
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43