Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : September - 2017,

Showing Page Number : 35 of 44

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1030
(OG)
150954-Construction and BT of road (a) Peshawar road to Kodai UC Agra (b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda.
Charsadda
26-02-16 - - 10-09-15 - 125 51.755 43.867 43.867 15.573 13.753 65.508 29.378 76% 52%
September - 2017
8.5 Km - 4 Km asphalt completed. Revised PC-I/DCE for Rs.325 m submitted to P&D. Pre-PDWP held.
1031
(OG)
150980-Construction of Sarwar Abad Umarzai Road and Road from Shakh No.4 to Shakh No.5 via Zarbab Ghari Maira Umarzai, District Charsadda.
Charsadda
29-02-16 - - 10-09-15 - 80 36.598 43.152 43.152 15.319 15.319 51.917 0.25 100% 65%
September - 2017
6.5 Km - 3 Km asphalt completed. Revised PC-I/DCE for Rs.200 m submitted to P&D. Pre-DPWP held.
1032
(OG)
151069-Construction of Sro Kalay Road from Yaka Ghund Road to Subhan Khwar, District Charsadda.
Charsadda
- 30-06-18 - 18-11-15 - 20 8.5 11.25 11.25 3.994 3.994 12.494 0.25 99% 62%
September - 2017
2 Km - 1 Km asphalt completed.
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 70 24.85 0 76.996 59.954 71% 37%
September - 2017
Land paymnet made. Dispute resolved . Work re-started.
1034
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Gharai on Right Bank and Kheshki on Left Bank, District Nowshera.
Nowshera
HW
23-01-15 - - 27-10-14 - 680.592 503.644 40 40 14.2 12.045 515.689 136.948 80% 76%
September - 2017
Length 450 mtr - Bridge substantially completed, opened to Traffic.
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 02-03-17 - 1010.279 426.892 164.997 164.997 58.574 35.77 462.662 418.39 59% 46%
September - 2017
Length 27 Km - earth work 100%, sub base 15 Km, WBM 15 Km, WC 12 Km, structure work 95%, PCC road 6 Km completed.
1036
(OG)
140936-F/S, Design and BT of internal roads Pirpiai - Azakhel Bala - Payan - Dagai - Banda Nabi, Badrashi, Nowshera. SH: Const of internal road in UCs Dagai-Banda Nabi, Pirpiai, Badrashi, Azakhel Bala & Payan, District Nowshera (Phase-II).
Nowshera
HW
30-03-15 - - 05-05-17 - 1050 427.927 200 200 41 22.827 450.754 422.073 60% 43%
September - 2017
Length 25.6 Km - earth work 100%, sub base 14 Km, WBM 14 Km, WC 16 Km, structure work 95% completed.
1037
(OG)
140938-F/S, Design & Improvement / BT of Internal 16 Km road at Kheshgi Bala and Payan, Nowshera.
Nowshera
HW
23-03-15 - - 23-12-16 - 850 168.772 100 100 35.5 3.576 172.348 581.228 32% 20%
September - 2017
Completed (16 Km). Tender opeing on 01/11/2017 for additional wor .
1038
(OG)
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera.
Nowshera
HW
16-03-15 - - 19-11-14 - 400 182.999 100 100 35.5 4.185 187.184 117.001 71% 47%
September - 2017
Length 6.7 Km - earth work 100%, sub base 6.5 Km, WBM 6.5 Km, WC 6.5 Km, structure work 90% completed. Bridge (80 mtr) completed. Tender floated for additional work, opening on 01/11/2017.
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 28-01-15 - 370 33.934 37.406 37.406 13.279 0 33.934 298.66 19% 9%
September - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder in progress.
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 30 10.65 0 118.494 0 100% 95%
September - 2017
Length 8.3 Km - 8 Km completed. Revised PC-I/DCE deferred.
1041
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads (a) GT road to Said Akbar Koroona (b) Ayub Abad to Essori Bala (c) Jehangira Kati Maina (d) Pitao Payan to Dargai village (e) GT road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
25-05-15 - - 28-01-15 - 294.551 206.96 20 20 7.1 0 206.96 67.591 77% 70%
September - 2017
Completed (12 Km). Revised scope tendering in progresss, opening on 01/11/2017.
1042
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
08-06-15 - - - - 284 173.47 19.994 19.994 7.098 1.768 175.238 90.536 68% 62%
September - 2017
Length 10 Km - earth work, sub-base 7 Km, WBM 7 Km, WC 7 Km, structure work 95% completed. Revised scope tendering in progress, opening on 01/11/2017.
1043
(OG)
141024-F/S, Design & Construction / Rehabilitation of roads (a) Gajoo Khel Ameero road (b) Jabbi road (c) Piran Bala and Payan & (d) From Duran to Masamkhel via Malikhel Bala Payan, District Nowshera.
Nowshera
HW
07-03-15 30-06-18 - 03-12-14 - 200 144.501 36.326 36.326 12.896 0 144.501 19.173 90% 72%
September - 2017
Completed (11 Km). Revised scope tendering in progress, opening on 01/11/2017.
1044
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru Distt Nowshera.
Nowshera
HW
01-05-16 - - 02-03-17 - 749.808 173.693 60 60 21.3 8.031 181.724 516.115 31% 24%
September - 2017
Length 23 Km - earth work, sub base, WBM, structure work, street pavement in progress. Revised scope tendering in progress, opening on 01/11/2017.
1045
(OG)
150809-Construction / Pavement of roads / streets alongwith allied works in UCs Aman Kot, Mohib Banda, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 600 191.93 100 100 35.5 19.121 211.051 308.07 49% 35%
September - 2017
Length 17.5 Km - earth work, sub base, WBM, structure work, street pavement in progress. Revised dcope tendering in progress, opening on 01/11/2017.
1046
(OG)
150810-Construction / pavement of roads / streets in UCís Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 100 35.5 10.016 185.288 74.728 79% 53%
September - 2017
Length 15 Km - structure work, street pavement in progress.
1047
(OG)
150813-Construction / Rehabilitation of Road from Inzari to Hisartang and Shaidu Khwar to Shinwari Koroona via Eidgah District Nowshera.
Nowshera
HW
- - - 26-11-15 - 200 6.384 90 90 31.95 0 6.384 103.616 48% 3%
September - 2017
Earth work, structure work in progress. Revised scope tendering, opening on 01/11/2017.
1048
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, GT Road to Fazal Gange and Hassan Abad Risalpur GT Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 200 117.52 53.483 53.483 18.986 0 117.52 28.997 86% 59%
September - 2017
Length 8.5 Km - earth work, sub base, WBM, asphalt 7 Km completed, structure work in progress. 2nd Revised PC-I/DCE for Rs.400 m submitted P&D. Pre-PDWP held.
1049
(OG)
150955-Construction of drains, pavement of streets and internal roads of Dak Ismail Khel, Shah Kot, Dak Besud, Balu, Spin Khak and Jalozai Distt Nowshera.
Nowshera
HW
01-05-16 - - 02-03-17 - 700 199.393 100 100 35.5 14.66 214.053 400.607 43% 31%
September - 2017
Length 18.5 Km - earth work, sub base, WBM, structure work in progress. Revised scope tendering in progress, opening on 01/11/2017.
1050
(OG)
150957-Construction of road from Jalozai to Kotli Kalan Distt: Nowshera.
Nowshera
HW
01-05-16 - - 09-02-15 - 136.624 82.424 40 40 14.2 11.952 94.376 14.2 90% 69%
September - 2017
Length 9 Km - WC in progress.
1051
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
- - - 26-11-15 - 200 23.5 30 30 10.65 0 23.5 146.5 27% 12%
September - 2017
3/11 Km asphalt completed. WBM, AWC in progress. Revised scope tendering in progress, opening on 01/11/2017.
1052
(OG)
151074-Construction / Pavement of roads / streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 450 209.946 100 100 35.5 8.112 218.058 140.054 69% 48%
September - 2017
18 Km - earth work, sub base, WBM, WC, structure work in progress. Revised scope tendering in progress, opening on 01/11/2017.
Package-1 - UC Dheri Katti Khel
Package-2 - UC (Dheri Katti Khel) Armour Colony, Hakeemabad
Package-3 - UC Kurvi
Package-4 - UC (Kurvi) Zakhijat, Banda Mulahan, Bajurabad
1053
(OG)
170588-Upgradation of Six (6) Numbers of Level Crossings (Phattak) in Nowshera Khyber Pakhtunkhwa (1st Phase).
Nowshera
HW
- - - 28-03-17 - 87.38 0 20 20 7.1 0 0 0 - -
September - 2017
Deposit work - Rs.7.1 m will be paid as processing fee.
1054
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park-Alla Dher Road, District Swabi.
Swabi
- - - 22-01-15 - 180 66.536 50 50 17.75 17.401 83.937 63.464 65% 47%
September - 2017
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress. Liability of the contractor Rs.60 m.
1055
(OG)
140961-F/S, Design and Construction of road from Shewa Chowk to Shewa Village (6 Km), District Swabi.
Swabi
- 30-06-18 - 23-12-16 - 200 120.215 34.59 34.59 17.295 12.27 132.485 45.195 77% 66%
September - 2017
Length 6 Km - 5 Km asphalt complted- 1 Km (shewa dagai) work started on trenches, sub base completed.
1056
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km), District Swabi.
Swabi
- - - 27-01-17 - 250 100.832 60 60 30 20.228 121.06 89.168 64% 48%
September - 2017
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
1) Dobian to Nazar and Tarkha (8 Km)
2) Tarkha road to Shaheedan (2.60 Km) PK-33
3) Nazar Chowk to Ismaila (7 Km) PK-33
4) Mardan-Swabi main road to Ismaila (4 Km) PK-33
1057
(OG)
141002-F/S, Design and Construction / Rehabilitation of Roads and street pavements (a) Kunda Topi (b) Gar Mergoz (c) Zarobi Topi (d) Zaida Kaddi (e) Marghuz Yousafi Swabi (21 Kms).
Swabi
- - - 22-01-15 - 210 158.257 70 70 35 27.052 185.309 0 100% 88%
September - 2017
Length 12 Km - 12 Km asphalt completed, structure work in progress. Liability of the contractor is Rs.119 m (punching issue of Rs.35 m).
1058
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
- 30-06-18 - - - 97.804 118.507 0.001 0.001 0 0 118.507 0 100% 100%
September - 2017
RW in progress. PC-I/DCE for Rs.137.782 m submitted to Chief Infra P&D on 25/09/2017. Summary for cahnge of nomenclature is under process.
1059
(OG)
150849-Const / Reh / widening of road from (a) Shahmansoor Town to Sikandari (b) Govt Girls High School Manari Bala to Saleem Khan Chowk (c) Panjpir main road to Shaga Bridge (d) Qazi Abad to Aboo Banda, Swabi.
Swabi
- - - 10-09-15 - 100 51.675 20 20 7.1 7.1 58.775 28.325 72% 59%
September - 2017
Length 8 Km - embankment, WBM completed.
1060
(OG)
150850-Construction / BT of roads (a) Shaheed Garnay Qadamay Dheri (b) Turlandi Shehram Tarskai (c) Turlandi Khawaja (d) Turlandi Kalu Dheri Lahor Lar (e) Tarakai Lar Managai (f) Sheikh Jana Pio Dher (g) Sheikh Jana Mansabdar (h) Sheikh Jana Ahmad Khel District Swabi.
Swabi
- - - 23-12-16 - 300 85.31 75 75 37.5 25.562 110.872 139.69 53% 37%
September - 2017
Length 9 Km (b, c, g, h)- asphalt completed, sub base 4 Km completed, WBM in progress.
1061
(OG)
150851-Construction / BT of roads (a) Karizoo to Urmar Sadri road, (b) Palosai Khairabad, (c) Rohani Bazargay road, District Swabi.
Swabi
- - - 23-12-16 - 300 53.25 75 75 37.5 26.255 79.505 171.75 43% 27%
September - 2017
Length 8 Km - sub base, embankment, drain in progress.
1062
(OG)
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sherafzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi.
Swabi
- - - 10-09-15 - 280 57.859 50 50 17.75 17.732 75.591 172.141 39% 27%
September - 2017
Length 13 Km - sub base, WBM, structure work in progress. Revised PC-I/DCE for Rs.330 m re-submitted to Chief Infra. Liability of the contractor is Rs.220 m.
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
- - - 10-09-15 - 250 97.223 50 50 25 17.085 114.308 102.777 59% 46%
September - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE. Liability of the contractor is Rs.200 m.
1064
(OG)
150854-Construction of Road (a) Gabaie Panawal road (b) Leron Amarai Bala road (c) Chanai road, District Swabi.
Swabi
- - - 10-09-15 - 80 39.5 30 30 15 14.162 53.662 10.5 87% 67%
September - 2017
Length 6 Km - sub base, WBM, structure work in progress. Liability of the contractor is Rs.120 m.
1065
(OG)
150888-Construction / Rehabilitation / Restoration of Access road from Swabi Interchange to Tourism related project at Hund, Swabi.
Swabi
- - - 10-09-15 - 99.696 49.25 30 30 15 0 49.25 20.446 79% 49%
September - 2017
Length 5 Km - widening/structural, embankment work in progress. Revised DCE for Rs.180 m submitted to SOR. Liability of the contractor is Rs.40 m.
1066
(OG)
150959-Construction / BT of roads (a) Parmoli Bypass road (b) Permoli Sabar Wand Lar (c) Sher Dara road (d) Speen Kany Bandi Oba (e) Speen Kany Bande Oba Dojangi road (f) Speen Kany Aman Kot Lar PCC road, District Swabi.
Swabi
- - - 23-12-16 - 300 99.918 80 80 40 29.398 129.316 120.082 60% 43%
September - 2017
Length 8 Km - PCC, base course, structure work, sub base in progress.
1067
(OG)
150960-Construction / BT of roads (a) Yar Hussain Shaheen Abad road, (b) Kas Koroona to Adena road, (c) Main road Shergaharri Asmela road, District Swabi.
Swabi
- - - 23-12-16 - 300 101.532 50 50 25 16.928 118.46 148.468 51% 39%
September - 2017
Length 8 Km - 0.6 KM asphalt completed, WBM in progress. Sub base, embankment completed.
1068
(OG)
150961-F/S, Design and Const of roads, Gara Jehangira 1 Km, Jalsai Jaganat (2 Km), Jalsai Dhok (1 Km), Doba Lar (1 Km), Zakriya Khel (1 Km), Batlasai Naray Lar Ambar (1 Km), Hayatabad Azim Garhi (1 Km), Jehangira Mera Dhab (1 Km) Swabi.
Swabi
- - - 02-11-15 - 149.63 30.875 30 30 10.65 10.507 41.382 88.755 41% 28%
September - 2017
Length 8 Km - embankment completed, sub base in progress. Liability of the contractor is Rs.200 m.
1069
(OG)
160497-(a) Construction and BT of Mian Essa Chowk to Jehangira Road 1 Km (b) Constn of PCC road of Mian Essa to Police Chowk and Mohalla Awan Jehangira Road (0.8 Km), District Swabi.
Swabi
- 30-06-18 - 14-10-16 - 27.838 0 22.838 22.838 11.419 11.419 11.419 5 82% 41%
September - 2017
Length 1.8 Km - in progress.
1070
(OG)
160641-Improvement of road village Tordher, Swabi.
Swabi
- 30-06-18 - 26-10-16 - 40 0 35 35 17.5 12.425 12.425 5 88% 31%
September - 2017
Work in progress.
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 13.68 6.5 62.154 2.6 97% 73%
September - 2017
5 Km/Bridge - deck slab 3/4, work on road work started.
5 Kms including bridge PK-26
1072
(OG)
140925-F/S, Design, Construction & BT of (a) Chiragh din Killy to Fazle Abad UC Maday Baba & (b) Safi Abad to Dheri Killy Hathian, Mardan.
Mardan
HW
- - - 23-12-16 - 130.656 58.927 10 10 3.55 3.55 62.477 61.729 53% 48%
September - 2017
Length 7.5 Km - BT 2.9 Km completed.
1) Chiragh Din Killi to Fazle Abad UC Maday Baba PK-27
2) Safi Abad to Dheri Killi Hatthian PK-27
1073
(OG)
140929-F/S, Design & Construction of roads (a) Katlang to Qadar Village (b) Kot Ismailzai (c) Shahand Maqbara to Kareem Abad (d) Toot Killy Nehar to Babanay & (e) Toot Killy Nehar to Chaghzau village, Mardan.
Mardan
HW
01-08-15 30-06-18 - 11-02-15 - 155.359 134.183 28.049 28.049 14.024 0 134.183 0 100% 86%
September - 2017
Completed (12 Km).
1) Main Katlang road to Gadar village (1.950 Kms) PK-30
2) Kot Ismailzai (1.700 Kms) PK-30
3) Shaheedano Muqbara to Kareem Abad (1.100 Kms) PK-30
4) Toot Killi road to Babaney village (1.200 Kms) PK-30
5) Toot Killi Nehar road to Chaghrzau road (0.800 Kms) PK-30
6) Construction and Black topping of Dobai Adda to Gul Abad 1.5 km.
1074
(OG)
140931-F/S, Design & Construction (a) Battagram Nehar to Zai (b) Katlang to Kudi Noor (c) Dubi Ada to Srekh (d) Katlang to Qaziabad (e) Bakhshali Dheri to Jangirh (f) Gazi Shek Babuzi (g) Charsada to Dheray Baba (h) Pir Gari (i) Fatima to GGPS (j) Main to Bala Gari (k) Muhib to Husain Madrasa, Mardan.
Mardan
HW
13-06-15 - - 11-02-15 - 110.647 83.485 26.662 26.662 9.465 5.748 89.233 0.5 100% 81%
September - 2017
Original scope completed (9 Km). Revised PC-I/DCE submitted to CE.
1) Battagram Nehar to Daulatzai road (1.700 Kms) PK-30
2) Katlang road to Khudai Noor village (1.500 Kms) PK-30
3) Dubai Adda to Sreekh village road (1.200 Kms) PK-30
1075
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
- 30-06-18 - 03-03-17 - 32.53 0.973 31.558 31.558 15.779 2.714 3.687 0 100% 11%
September - 2017
Work piles in progress.
PK-25
1076
(OG)
140991-F/S, Design and Construction of Roads (a) Shatoo (b) Murad Koroona to Khana Dher and (c) Jalakai road to Shurkh Dheri, Mardan.
Mardan
HW
- 30-06-18 - 22-01-15 - 94.9 68.869 12.918 12.918 6.459 6.459 75.328 13.113 86% 79%
September - 2017
Length 6.5 Km - 3.26 Km completed.
PK-29
1077
(OG)
150230-Construction of Mardan Bypass Road from Rashakai Interchange to Jalala (Missing links 8 Kms), Mardan (including land).
Mardan
HW
01-01-16 - - 21-01-16 - 1078.85 618.977 50 50 17.75 17.75 636.727 409.873 62% 59%
September - 2017
Length 12 Km - Pack-I (1.5 Km BT). Service road 4 K BT Bridge No. 1 & 2 completed. Pack-2 (8 Km) - work in progress.
1078
(OG)
150826-Construction / rehabilitation of internal roads of UC Toru Maira and UC Maho Dheri road, District Mardan.
Mardan
HW
01-04-16 - - 02-11-15 - 129.829 41.272 60 60 21.3 21.3 62.572 28.557 78% 48%
September - 2017
Length 7.3 Km - 4.75 Km BT completed.
1079
(OG)
150828-Construction / Rehabilitation of road (a) Kandary to Chatlay, Kombat to Qasam Kalay (b) Haspital road Qumbat from Dheki to Chunkay Bara Qadar Naseer road, Mardan.
Mardan
HW
11-07-16 - - 10-09-15 - 100 9.5 30 30 10.65 10.65 20.15 60.5 40% 20%
September - 2017
Length 6.5 Km - RW, drain completed.
a) Gumbat Chungay to Dhaki Killi (5.500 Kms)
b) Bara Qadar Naseer Killi road (1 Km)