Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : November - 2016,

Showing Page Number : 35 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1010
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 0 5 5 0 0 0 226.52 2% -
November - 2016
Pre-qualification of contractors invited.
1011
(OG)
150947-Construction of Mingora Kokray Marghuzar road District Swat.
Swat
HW
10-02-16 - - 20-08-15 - 45 10 20 20 10 10 20 15 67% 44%
November - 2016
Length 2.6 Km - structure work, WBM in progress.
1012
(OG)
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II).
Dir Lower
24-10-14 - - 10-10-13 - 126.085 74.194 5 3.75 1.25 1.25 75.444 46.891 63% 60%
November - 2016
Length 7.8 Km - 2.8 Km completed. 2 Km sub base, WBM completed.
1013
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 117.735 30 50 50 50 167.735 1062.835 12% 14%
November - 2016
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km.
1014
(OG)
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower.
Dir Lower
19-08-15 - - 28-01-15 - 162.54 20 10 10 5 5 25 132.54 18% 15%
November - 2016
Length 15 Km - out of 4 packages, all in progress.
1015
(OG)
140901-F/S, Design & Construction of Talash Kalpanai Bypass road (10 Km), Dir Lower.
Dir Lower
- - - 11-02-15 - 350 7.5 10 5 0 0 7.5 332.5 5% 2%
November - 2016
Work started.
1016
(OG)
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower.
Dir Lower
06-08-15 - - 28-01-15 - 174.826 65.25 15 25 17.5 17.5 82.75 94.576 46% 47%
November - 2016
Out of 4 bridges, Agharily Bridge- piling in progress. Arif Killi - grider launching completed. Garangal - piling under progress. Markhani - girder launched.
1017
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
- - - 03-11-16 - 99.296 0 5 5 0 0 0 94.296 5% -
November - 2016
Pre-qualification invited on 28/12/2016.
RCC Bridges in Dir Lower (4 Nos) (a) RCC Bridge at Munjai
1018
(OG)
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower.
Dir Lower
- - - 02-11-15 - 199.796 10 5 16.25 16.25 16.25 26.25 184.796 8% 13%
November - 2016
Length 12 Km - work in progress on all 6 units.
1019
(OG)
150838-Construction of RCC bridges Raidgay (Kotkay) & Gul Khawarr Maidan Dir Lower.
Dir Lower
- - - 03-11-16 - 190.549 0 5 5 0 0 0 185.549 3% -
November - 2016
Pre-qualifcation called on 28/12/2016.
RCC Bridges in Dir Lower (a) RCC Bridge at Raidgay (Kotkay) (b) RCC Bridge at Gul Khawar Maidan
1020
(OG)
150839-Const of (a) Asband Swat (3 Km) (b) Shursheen (c) Joro Kashmir (2 Km) (d) Ghazo Chat Pat (e) Deghan (1 Km) (f) Dheri Tesko (3 Km) (g) Oskai (1.5 Km) (i) Laiko (1 Km) (j) Naw Kalay Bochake (2 Km) (k) Mayar Dogha (2 Km) Dir Lower.
Dir Lower
- - - - - 139.251 8.75 250 210 23.75 23.75 32.5 0 100% 23%
November - 2016
Out of 4 roads, all in progress. Rev DCE approved on 02/12/2016. AA awaited.
1021
(OG)
150963-Construction / Rehabiliation of roads Pato Atak & Barikot, Rabat Assigay Laram Danda, Sarbanda, Dod Khana, Shati, Mali, Watangay, Malakand Kohrey, Gadla, Banda, Karam Khel, Sparay, Danwa, Rani & Ghwaago Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 369.278 15 20 43.75 43.75 43.75 58.75 334.278 9% 16%
November - 2016
Out of 17 units, work in progress in all 17 units.
1022
(OG)
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 367.574 15 20 43.75 43.75 43.75 58.75 332.574 10% 16%
November - 2016
Out of 20 units, all in progress.
1023
(OG)
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower.
Dir Lower
- - - 02-11-15 - 275.308 5 5 5 2.5 2.5 7.5 265.308 4% 3%
November - 2016
Out of 18 units, all in progress.
1024
(OG)
150966-Construciton of RCC Bridge at Matako Rahim Abad District Dir Lower.
Dir Lower
- - - 08-08-16 - 49.733 0 15 15 3.75 0 0 34.733 30% -
November - 2016
Pre-qualification approved on 03/11/2016. Ternder opened on 04/12/2016, approval under process.
1025
(OG)
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower.
Dir Lower
- - - 02-11-15 - 278.061 12.5 5 5 5 5 17.5 260.561 6% 6%
November - 2016
Out of 6 units, work in progress on all units.
1026
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper.
Dir Upper
11-10-12 - - 11-02-15 - 255.368 157.004 5 5 2.5 0 157.004 93.364 63% 61%
November - 2016
10 Km - earth, structure, road work completed. 5 Km road surfacing PCC completed.
PK-92 (Km-1 to 10)
1027
(OG)
130577-Construction of 3 Nos RCC Bridges i.e. Surbat, Dogai and Garonai District Dir Upper.
Dir Upper
- 30-06-17 - 03-12-14 - 81.095 57.176 23.919 23.919 11.958 10.85 68.026 0 100% 84%
November - 2016
All 3 bridges in progress. Abutmnet completed. Launching in progress.
1028
(OG)
140648-Construction of RCC Bridge at Khal Barkalay Bazaar PK-93 District Dir Upper.
Dir Upper
- 30-06-17 - 16-12-14 - 53.699 43.158 10.541 10.541 5.27 5.27 48.428 0 100% 90%
November - 2016
36/36 pile, 8/20 girders launched 15 girders casted, 1/5 slabs completed. Right side abutment completed.
1029
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 - - 22-01-15 - 120 20 10 10 5 2.5 22.5 90 25% 19%
November - 2016
Length 8 Km - earth work 30%, structure work 30% in progress.
1030
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 - - 22-01-15 - 100 20 15 15 7.5 3.627 23.627 65 35% 24%
November - 2016
Length 5 Km - structure work on both side in progress.
1031
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 166.565 20 5 5 2.5 1.25 21.25 141.565 15% 13%
November - 2016
Length 10 Km - structure work in progress.
1032
(OG)
140905-Construction of PCC Roads at Usherai Dara (10 Km), Dir Upper.
Dir Upper
01-07-15 - - - - 166.99 20 50 50 25 18.5 38.5 96.99 42% 23%
November - 2016
Length 10 Km - structure work on both side in progress. 20% PCC road completed.
1033
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
- - - 11-02-15 - 380.856 66.7 10 10 5 4.067 70.767 304.156 20% 19%
November - 2016
Length 27 Km - earth work in progress, structure work 30%, 5 Km base course completed.
1034
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
- - - 25-03-15 - 597.77 65.359 10 10 5 2.5 67.859 522.411 13% 11%
November - 2016
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed (Kotkay bridge).
1035
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
- - - 02-11-15 - 279 3.75 5 5 2.5 1.25 5 270.25 3% 2%
November - 2016
5 units - work in progress.
PK-91
1036
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
- - - 02-11-15 - 325.5 15 5 5 2.5 1.25 16.25 305.5 6% 5%
November - 2016
6 units - work started (5 units), 1 work order issued.
PK-92
1037
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
- - - 21-01-16 - 300 10 10 10 7.5 4.627 14.627 280 7% 5%
November - 2016
Out of 8 units,8 in progress.
PK-93
1038
(OG)
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper.
Dir Upper
- - - - Line Deptt 100 0 5 5 0 0 0 0 - -
November - 2016
Fresh directive issued for 3 bridges on 24/11/2016, summary submitted to CA for approval for enhancement of ADP cost.
PK-91
1039
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
- - - 16-10-15 - 50 5 5 5 2.5 2.5 7.5 40 20% 15%
November - 2016
Length 25 Km - earth work, structure work in progress.
PK-91
1040
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
- - - 09-02-16 - 200 0 10 10 5 5 5 190 5% 3%
November - 2016
Earth work in progress.
PK-93
1041
(OG)
151082-Construction of Bridge on Patrak-Kumrat Road.
Dir Upper
- - - - - 24.712 0 10 10 0 0 0 14.712 40% -
November - 2016
Tender approval under process.
PK-92
1042
(OG)
70210-Construction of Khan Abdul Wali Khan By-pass road District Chitral.
Chitral
16-01-10 - - 18-05-11 - 788.857 686.114 40 40 20 20 706.114 62.743 92% 90%
November - 2016
Length 3.27 Km - road work completed, 2 RCC bridges completed, streets lights in progress.
1043
(OG)
70216-Improvement / Black Topping of Booni, Mastuj Shandoor Road (70 Km) at Chitral (PSDP Funded).
Chitral
02-05-08 - - 09-03-15 - 2323.914 204.101 10 0 0 0 204.101 2109.813 9% 9%
November - 2016
Federalization of road in progress.
1044
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
01-06-10 - - 09-03-15 - 1108.42 199.774 10 15 10 10 209.774 898.646 19% 19%
November - 2016
Length 28 Km - earth work, structure work, road work in progress.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
- - - 11-02-15 - 130 5.142 5 5 5 5 10.142 119.858 8% 8%
November - 2016
RCC bridge in progress, 2 Km road work restarted.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
28-10-15 - - 11-02-15 - 199.75 20.183 10 10 2.5 0 20.183 0 - -
November - 2016
Work in progress.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
28-10-15 - - 11-02-15 - 69.75 12.183 2.5 2.5 2.5 2.5 14.683 55.067 21% 21%
November - 2016
Length 4.5 Km - earth work completed, sub-base and structure work in progress.
1046
(OG)
140984-F/S, Design and Construction of RCC Bridge at Ayun, Chitral.
Chitral
- - - - - 90 0 5 5 0 0 0 0 - -
November - 2016
PC-I approved on 02/12/2016, AA awaited.
1047
(OG)
150822-Realignment and Black Topping of Garam Chashma road from Shaghore to Mough including bridges District Chitral.
Chitral
- - - - Line Deptt 1293 0 5 5 0 0 0 0 - -
November - 2016
Scheme federalized. NHA started survey and DCE.
1048
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
- - - 02-11-15 - 83.43 7.5 5 5 1.25 1.25 8.75 70.93 15% 10%
November - 2016
Out of 3 units, 2 started.
1049
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
- - - 02-11-15 - 75.851 7.5 10 10 5 5 12.5 58.351 23% 16%
November - 2016
Out of 3 units, 3 work started.
1050
(OG)
160636-Reconstruction of washedway Mozh Gole Suspension bridge and approach Mulkhow due to flood in July August 2015 District Chitral.
Chitral
- - - 12-05-16 - 19.8 0 5 5 2.5 2.5 2.5 14.8 25% 13%
November - 2016
Completed.
1051
(OG)
160638-Restroation of flood affected roads and bridge etc. due to torrential and thunderstorm rain during mid August September 2015, District Chitral.
Chitral
- - - 12-05-16 - 15.01 0 10 10 5 3.75 3.75 5.01 67% 25%
November - 2016
Completed.
1052
(OG)
160639-Restoration of Rehun Power House road damaged due to torrential rain / glacial lake outburst flood (GLOF) in July & August 2015, District Chitral.
Chitral
- - - 12-05-16 - 12.627 0 5 5 2.5 2.5 2.5 7.627 40% 20%
November - 2016
Completed.
1053
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
05-09-07 - - 25-03-15 - 406.458 137.892 10 10 5 5 142.892 258.566 36% 35%
November - 2016
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
1) Bataira to Mirbat Road PK-62 (B/W 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (B/W 7 KM)
1054
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 - - 29-05-14 - 322.534 169.881 40 40 20 0.3 170.181 112.653 65% 53%
November - 2016
20/48 piles, 6 girder, left abutment completed. Right side abutment in progress.
1055
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
- - - 17-11-15 - 100 0 10 10 5 0 0 90 10% -
November - 2016
Work in progress.
1056
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan.
Kohistan
- - - 17-11-15 - 200 0 10 10 5 5 5 190 5% 3%
November - 2016
4 units - 1 land acquisition under process, 2 in progress, 1 work started.
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
1057
(OG)
150875-Construction of road from Shaha to Sput Valley, Gabar Naala Road and Dong Naala Road District Kohistan.
Kohistan
- - - 10-09-15 - 80 3.75 5 3.75 2.5 0 3.75 71.25 11% 5%
November - 2016
3 units - 1 earth work 100% completed, 2 work order issued.
1) Construction of road from Soha to Sput 3 Km
2) Construction of Gabber Nullah road 2 Km
3) Construction of Dong Nullah road 2 Km
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43