Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : June - 2017,

Showing Page Number : 39 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1082
(OG)
140981-Construction / Improvement / Rehabilitation/ Widening of 16 different roads (20 Km) in PK-44, Abbottabad.
Abbottabad
23-05-16 - - 29-12-15 - 220 24.5 5 55.75 55.75 55.75 80.25 190.5 13% 36%
June - 2017
Length 20 Km - out of 16 units, all in progress. Revised PC-I/DCE for Rs.220 m submitted to SOR on 06/06/2017.
Balolia Deena Rio Guldhok road and Hata Zia Mansoor road (20 Km) PK-44
1083
(OG)
140982-F/S, Design and Construction / Rehabilitation of Bandi Attai Khan Road to Havellian (6 Km), Abbottabad.
Abbottabad
14-04-15 - - 07-01-15 - 66 50.95 5 11.875 11.875 11.875 62.825 10.05 85% 95%
June - 2017
Completed.
1084
(OG)
150861-Construciton of RCC Bridge at (a) Guldok Dhamtor District Abbottabad (b) Beer Banda Nabi Road, Mera Muzaffar road, Lower Islamkot road, Booji road, Mirpura road, Blolia / Dana road, Dna Mara Mandroch, Mandroch Kalan Faqeer Bandi road District Abbottabad.
Abbottabad
04-04-16 - - 10-09-15 - 200 24.5 10 30.12 30.12 30.12 54.62 165.5 17% 27%
June - 2017
Out of 9 units, 8 in progress, 1 (bridge) pre- qualification completed, financial bid opened 11/12/2016. Revised PC-I/DCE for Rs.200 m submitted to SOR on 12/06/2017.
1085
(OG)
150862-Reh / Imp / BT / PCC of Boi Talkandi via Pall Mohri Sahran Sambli (R/W), Bangra Chowk to Kaner Kass Malkot U/C Plack Vill with drain, Banni Jandala to Ander Kot Drwaza via Cham U/C Plack Distt. Abbottabad.
Abbottabad
13-06-16 - - 10-09-15 - 70 0 5 7.75 7.75 7.75 7.75 65 7% 11%
June - 2017
3 units - 2 earth work in progress, 1 structure work in progress.
1086
(OG)
150863-Imp & Reconstn of road from Pind Kargoo to Jarral Kotnali with link to Gul Band U/C Jarral, Totani to Pawa, Gujar Mor via Pullah di Bandi U/C Pawa, Sherwan Bazar to Shaheed Abad with link to Athora & Bambochi Distt Abbottabad.
Abbottabad
26-05-16 - - 10-09-15 - 100 10 10 19.5 19.5 19.5 29.5 80 20% 30%
June - 2017
Out of 3 units, all in progress.
1087
(OG)
150864-Construction of road from Haji Gali to Naguara Gali, Guda Takia, Beesian Riala, Sajikot Ghora Road District Abbottabad.
Abbottabad
- - - 10-09-15 - 200 0 10 31.4 31.4 31.4 31.4 190 5% 16%
June - 2017
Length 13 Km - Out of 5 units, all earth work in progress.
1088
(OG)
150865-Construction / Rehabilitation of road from BHU Tajwal to Nawansher, Machana to Batangi, Serrian to Keri Raiki, Taror, Shakra to Choprra Nawansher Pirkot to Tupla road Kala Ban, Shukka Kas road, Abbottabad.
Abbottabad
03-03-16 - - - - 200 15.584 20 63.31 63.31 63.31 78.894 164.416 18% 39%
June - 2017
10/10 units in progress. Revised PC-I/DCE for Rs.700 m submitted to P&D.
1089
(OG)
150887-F/S and Design of road i/c 3 Bridges alongwith Right Bank of River Jehlum from Phalair to Kohala (35 Km), District Abbottabad.
Abbottabad
- - - - - 48.25 0 10 0 0 0 0 38.25 21% -
June - 2017
Completed.
1090
(OG)
150951-Imp / Reh / PCC from main road to Sari Darwaza via Loongal vill U/C Plack, Moolia to Kala Ban Aliabad Pakhoo Nakar U/C Bakote, Maina road Numbal U/C Pattan Main road Numbal Rata Thapala to Majoot U/C Numbal Distt Abbottabad.
Abbottabad
15-04-16 - - 10-09-15 - 70 0 5 14 14 14 14 65 7% 20%
June - 2017
Earth work in progress (3 units).
1091
(OG)
150953-Imp & Reconstn of road from Sherwan to Thathi UC Sherwan & road from Civil Hospital to Ratian via Thandara with link to Sari Sher Shah and Bandi Nikian U/C Pind Kargoo Distt Abbottabad.
Abbottabad
01-05-16 - - 10-09-15 - 100 10 5 13.15 13.15 13.15 23.15 85 15% 23%
June - 2017
Earth work in progress (2 units).
1092
(OG)
151070-Rehabilitation of Link Road Sarban Chowk to Dhobi Ghat Chowk Murree Road, Abbottabad.
Abbottabad
05-09-16 - - 20-08-15 - 42.36 0 20 14 14 14 14 22.36 47% 33%
June - 2017
Length 3 Km - BT 3 Km completed.
1093
(OG)
151073-Construction of Sawar Lalai to Boi Road (3 Km), Abbottabad.
Abbottabad
- - - 20-08-15 - 30 0 5 7.25 7.25 7.25 7.25 25 17% 24%
June - 2017
3 Km - work started. Directive received for Change of nomenclature. Revised PC-I under preparation.
1094
(OG)
130601-Rehabilitation / Widening of Srai Naimat Khan Road (12 Kms), District Haripur.
Haripur
25-05-14 - - 24-08-16 - 216.195 156.782 14.361 59.402 59.402 59.402 216.184 45.052 79% 100%
June - 2017
Completed (Length 14 Km).
1095
(OG)
130602-Rehabilitation / Widening of Mirpur Kahl - Kamalpur Road, District Haripur (8 Kms).
Haripur
25-05-14 30-06-17 - 03-02-14 - 142.537 134.69 7.838 7.446 7.446 7.446 142.136 0.009 100% 100%
June - 2017
Completed (13 Km BT).
1096
(OG)
140656-F/S, Design & Construction of road from (i) Sulam Khand to Sira road (6.50 Km), (ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and (iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km).
Haripur
07-05-15 - - 24-08-16 - 399.486 128.735 20 84.969 84.969 84.969 213.704 250.751 37% 53%
June - 2017
Length 20 Km - Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus.
1097
(OG)
140657-F/S, Design & Improvement / Rehabilitation of Pir Sohawa to Kohala Bazar road via Makhnial, District Haripur (10 Kms).
Haripur
15-05-15 30-06-17 - 19-02-15 - 226.038 58.294 167.743 179.556 179.556 179.556 237.85 0.001 100% 100%
June - 2017
Completed (10 Km).
1098
(OG)
140662-F/S, Design & Reconstruction / Re-carpeting of Road from Tareen Abad to Hattar Industrial Estate, District Haripur.
Haripur
13-06-15 30-06-17 - 19-02-15 - 99.95 90.973 18.676 14.008 14.008 14.008 104.981 0 100% 100%
June - 2017
Completed (5 Km).
1099
(OG)
140910-F/S, Design & Construction of road (a) Akhoon Bandi to Magri road (b) Pharrori to Bandi Mian Pid Dad via Bian Ahmed Ali Khan to Kandal (c) Sarai Nimat Khan to Jabri road, District Haripur (23 Kms).
Haripur
04-05-15 - - 25-03-15 - 411.126 190.5 25 180.458 180.458 180.458 370.958 195.626 52% 90%
June - 2017
Length 27 Km - earth work 90%, sub-base 90%, base course 40%, structure work 70% completed.
1100
(OG)
140911-F/S, Design and Construction of pre-stressed Bridge from Thanda Choa to Mohri No.1, District Haripur.
Haripur
18-06-15 - - 19-02-15 - 95.946 56.308 25 51.821 51.821 51.821 108.129 14.638 85% 100%
June - 2017
Completed (Length 180 mtr).
1101
(OG)
150222-Construction of BT road from Makhnial to Danna Ferozpur Road, District Haripur.
Haripur
18-05-16 - - 28-08-15 - 48.291 12.5 30 23.262 23.262 23.262 35.762 5.791 88% 74%
June - 2017
Length 2 Km - earth work 90% completed, structure work in progress.
1102
(OG)
150686-Construction of roads (a) Mohari to Akhun Bandi Bridge (b) Durnian to Thipra to Mirupur Kahal road (c) Talhad village road and (d) Badshaia to Rehana Maira road District Haripur.
Haripur
25-12-15 - - 10-09-15 - 150 38.46 25 93.457 93.457 93.457 131.917 86.54 42% 88%
June - 2017
Length 13.3 Km - earth work and structure work in progress.
1103
(OG)
150866-Black topping of Internal road of village Khanpur UC Khanpur District Haripur.
Haripur
06-05-16 - - 02-11-15 - 99.998 0 10 9.5 9.5 9.5 9.5 89.998 10% 10%
June - 2017
Length 10 Km - road work in progress.
1104
(OG)
150867-Construction / improvement / rehabilitation of Karwala Road District Haripur.
Haripur
01-06-16 - - 14-12-15 - 60 3 10 26.193 26.193 26.193 29.193 47 22% 49%
June - 2017
Length 6 Km - masonrey, road work in progress.
1105
(OG)
150868-Construction of Road from Kala-Khtha to Thalikot road, Khair Bara to Dhok Road, Karplia to Hassan Bai road and Soha to Koktri road District Haripur.
Haripur
15-05-16 - - 02-11-15 - 200 7.5 10 25.886 25.886 25.886 33.386 182.5 9% 17%
June - 2017
Length 7 Km - out of 4 units, all in progress.
1) Kala - Khtha to Thalikot road
2) Khair Bara to Dhoke road
3) Kariplia to Hassan Bai road
4) Soha to Kakortri road
1106
(OG)
150883-Pavement of roads / Streets in different UCs of PK-50 Haripur.
Haripur
06-04-16 - - 21-01-16 - 200 30 25 132.458 132.458 132.458 162.458 145 28% 81%
June - 2017
20% work completed.
1107
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
- - - 09-02-16 - 173.524 6.322 30 42.445 42.445 42.445 48.767 137.202 21% 28%
June - 2017
Bridge 180 mtr - 20 Nos piles completed, deck slab in progress.
1108
(OG)
150885-Rehahilitation of Sarai Saleh to Pind Jamal Khan Road, District Haripur.
Haripur
07-08-17 - - - - 149.515 1.54 25 77.278 77.278 77.278 78.818 122.975 18% 53%
June - 2017
Length 6 Km - 50% work completed.
1109
(OG)
150889-Pavement of roads and streets for UC Saray Saleh, Shah Maqsood, Rehana, Ali Khan, Darwesh, Pind Hasim Khan, UC Sourth and Pandak of District Haripur.
Haripur
18-08-14 - - 03-11-16 - 150 0 30 81.886 81.886 81.886 81.886 120 20% 55%
June - 2017
Earth work, sub base in progress.
1110
(OG)
160189-Improvement and widening of Suraj Gali Hattar road (6.50 Kms), District Haripur.
Haripur
- - - 23-12-16 - 116.536 0 5 0 0 0 0 111.536 4% -
June - 2017
Work started.
1111
(OG)
140831-F/S, Design and Construction of B/T Road from Damtal Ijara to Janbatai Barawal (6 Km) Districts Dir Lower and Dir Upper.
Dir Lower
- - - 27-01-17 - 91.62 0 15 3 3 3 3 76.62 16% 3%
June - 2017
Work on 10 Km in progress.
1) Dir Lower 4 Km (Km-1 to 4)
2) Dir Upper 6 Km (Km-5 to 10)
1112
(OG)
150218-Improvement / Rehabilitation and BT of Rajjar roads to Saleem Khan Road, Gegey road, District Charsadda & Mardan.
Charsadda
- - - 28-08-15 - 0 0 0 0 0 0 0 0 - -
June - 2017
Principally approved. AA awaited.
1112
(OG)
150218-Improvement / Rehabilitation and BT of Rajjar roads to Saleem Khan Road, Gegey road, District Charsadda & Mardan.
Mardan
HW
- - - 28-08-15 - 45 0 45.015 45.015 45.015 45.015 45.015 0 100% 100%
June - 2017
Completed.
1112
(OG)
150218-Improvement / Rehabilitation and BT of Rajjar roads to Saleem Khan Road, Gegey road, District Charsadda & Mardan.
Provincial
- - - 28-08-15 - 45 0 10 45.015 45.015 45.015 45.015 0 - -
June - 2017
Work in progress.
1113
(OG)
140972-F/S and BT of 10 Km road from Mera Mada Khel to Godar, Tor Ghar.
Tor Ghar
22-07-15 - - 19-02-15 - 234.56 98.231 25 60.136 60.136 60.136 158.367 111.329 53% 68%
June - 2017
Length 10 Km - earth work, structure work in progress.
1114
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar.
Tor Ghar
- - - 10-09-15 - 99.785 0.484 5 24.75 24.75 24.75 25.234 94.301 5% 25%
June - 2017
Length 4 Km - earth work 80% completed.
1115
(New)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 0 25 76.996 76.996 76.996 76.996 181.95 12% 37%
June - 2017
Land paymnet made. Work stopped due to land dispute.
1116
(New)
160641-Improvement of road village Tordher, Swabi.
Swabi
- - - 26-10-16 - 40 0 5 0 0 0 0 35 13% -
June - 2017
Work started.
1117
(New)
160623-F/S, Design & Construction of overhead / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan.
Mardan
HW
- - - 27-12-16 - 1750 0 100 11.254 11.254 11.254 11.254 1650 6% 1%
June - 2017
Scheme approved on 27/12/2016 for Rs.1750 m. AA awaited. Summary approved by CA for enhancement of cost. Modified PC-I/DCE for Rs.1932.165 m submitted to CE North on 19/06/2017.
1118
(New)
160643-Construction of Gajee, Karshat Shingle Road (4 Km), District Shangla.
Shangla
- - - 24-11-16 - 40 0 10 0 0 0 0 30 25% -
June - 2017
Tender invited on 05/04/2017. Tender submitted to SE on 10/04/2017.
1119
(New)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
- - - 03-11-16 - 464.813 0 5 0 0 0 0 459.813 1% -
June - 2017
Work order issued.
1120
(New)
160624-F/S, Design and Supervision of Mansehra Bypass District Mansehra.
Mansehra
- - - - - 20 0 20 1.7 1.7 1.7 1.7 0 100% 9%
June - 2017
Completed (Length 35 Km).
1121
(New)
160625-F/S and Design of Qalandarabad Bypass road (4 Km), District Abbottabad.
Abbottabad
- 30-06-17 - - - 4 0 10 0.215 0.215 0.215 0.215 0 100% 5%
June - 2017
Completed.
1122
(New)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
- - - 03-11-16 - 1470.041 0 40 0 0 0 0 1430.041 3% -
June - 2017
NIT floated for financial bid opening on Jul-2017.
1123
(New)
160627-F/S, Design and Construction of (a) Akunbandi bridge (b) from Rehana to Chapra (c) Rehana to Tachar (d) Noordi to Pind Jamal Khan (e) Talkar road, District Haripur.
Haripur
18-01-17 - - 03-11-16 - 236.504 0 30 30.924 30.924 30.924 30.924 206.504 13% 13%
June - 2017
4 units - 30 piles completed. Earth work, masonry in progress.
1124
(New)
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad.
Abbottabad
- - - 28-03-17 - 667 0 67 0 0 0 0 600 10% -
June - 2017
Pre-qualification of contractor under proces.
1125
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
02-11-15 - - 06-03-15 - 798.06 100 20 19 19 19 119 678.06 15% 15%
June - 2017
Pack-1 (7 Km) - earth work, sub-base, base course in progress. Pack-2 (7 Km) - earth work, culverts in progress. Pack-3 (5.825 Km) - earth work in progress.
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.825 Km)
1126
(OG)
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km).
Kohat
PKHA
02-11-15 - - 04-06-15 - 294.598 160 60 57 57 57 217 74.598 75% 74%
June - 2017
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress.
1127
(OG)
140879-Dualization / Rehabilitation of road from Gulshan Abad Chowk to Jerma Bridge via Hangu Pattak (11.5 Km) District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 360 80 86 86 86 446 889.516 33% 34%
June - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1128
(OG)
120282-Improvement and Widening of Road from Mufti Mehmood Flyover to old Budni Bridge upto Wahid Garhi 9 Km on PH S-I i/c reconstruction of old Budhni Bridge District Peshawar.
Peshawar
PKHA
15-01-14 - - 12-04-16 - 1119.959 361.533 50 107.5 107.5 107.5 469.033 708.426 37% 42%
June - 2017
Bridge completed and opened for traffic. Section-1 (1550 mtr) - asphalt overlay both side completed, drain in progress. Section-2 (1000 mtr)- sub base, aggregate base, RCC pipe culvert completed, asphalt base course, asphalt WC in progress. Financial evauation proposals of bidder opened for balance approach road.
1) 2.5 Kms
1129
(OG)
140628-Construction of Dual Carriageway from Chamkani to Badaber via Surezai with a link to Peshawar Ring Road. SH: Peshawar Ring Road to Badaber via Surezai (16 Km) (Phase-I), Distt. Peshawar.
Peshawar
PKHA
- - - - Line Deptt 7500 0 50 47.5 47.5 47.5 47.5 0 - -
June - 2017
The CA has decided to execute the scheme through PPP mode. Node meeting has been held Dec 2016 case has been forwarded to unit committee in P&D Deptt.