Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2017,

Showing Page Number : 39 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1273
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
04-09-15 - - 07-01-15 - 318.69 192.5 30 30 10.65 0 192.5 96.19 70% 60%
July - 2017
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress.
1274
(OG)
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper.
Dir Upper
PKHA
31-01-11 - - 07-01-15 - 1798.521 1659.087 40 40 14.2 0 1659.087 99.434 94% 92%
July - 2017
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed.
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges
1275
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 247.5 70 70 24.85 0 247.5 671.02 32% 25%
July - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
1276
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
- - - - - 344.978 167.5 40 40 14.2 0 167.5 137.478 60% 49%
July - 2017
Structure/road work in progress.
1277
(OG)
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad.
Abbottabad
PKHA
29-12-15 - - 07-01-15 - 983.904 454.5 55 55 19.525 0 454.5 474.404 52% 46%
July - 2017
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress.
1278
(OG)
140877-Construction of Haripur Bypass Road (23 Km).
Haripur
PKHA
30-09-15 - - 28-01-15 - 3712.05 1655 120 120 42.6 0 1655 1937.05 48% 45%
July - 2017
Length 23 Km - Pack-1 to 6 work started. Land acquisition payment completed. P&D directed DG M&E to examine revised PC-I and submit recommendations.
1279
(OG)
20665-Construction / Supervision of new Road Works.
Provincial
PKHA
20-06-06 - - 20-03-06 - 1104.58 908.354 100 100 35.5 0 908.354 96.226 91% 82%
July - 2017
Construction supervision of new road works.
1280
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
15-10-10 - - 23-08-11 - 253.57 177.246 20 20 7.1 0 177.246 56.324 78% 70%
July - 2017
Conusltancy services for feasilbility study and design and framing PC-I.
1281
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 140.75 20 20 7.1 0 140.75 337.41 32% 28%
July - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
1282
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
21-10-15 - - 25-03-15 - 2759.858 509.99 100 100 35.5 0 509.99 2149.868 22% 18%
July - 2017
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
1283
(OG)
140629-Construcction of Swat Motorway (Land Acquisition).
Swat
PKHA
10-06-14 - - 29-07-16 - 5850 4668.987 50 50 17.75 0 4668.987 1131.013 81% 80%
July - 2017
Land payment of all the mozas of all districts made to the concerend revenue officers. 56 Km land acquired and handed over to FWO.
1284
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Provincial
PKHA
04-09-15 - - 28-01-15 - 2796.766 427.25 240 240 85.2 0 427.25 2129.516 24% 15%
July - 2017
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
1285
(OG)
160193-Project Directorate for Swat Expressway.
Swat
PKHA
01-08-16 30-06-18 - 05-08-16 - 67.401 32.596 34.061 34.061 12.092 0 32.596 0.744 99% 48%
July - 2017
Project directorate setup.
1286
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PKHA
- - - 02-12-16 - 59.318 14.25 5 5 1.775 0 14.25 40.068 32% 24%
July - 2017
PIU setup, staff deputed. Revised AA approved.
1287
(OG)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
- - - 02-03-17 - 0.01 0 0.001 0.001 0 0 0 0 - -
July - 2017
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1287
(OG)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
- 30-06-18 - 02-03-17 - 104.815 0 82.995 82.995 0 0 0 0 - -
July - 2017
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1288
(New)
170523-F/S & Construction of Southern Link Road (Circular Road), Bannu.
Bannu
PKHA
- - - - Line Deptt 3000 0 30 30 0 0 0 0 - -
July - 2017
PC-II for Rs.20 m approved in DDWP on 19/06/2017.
1289
(New)
150764-F/S, Design and Construction of Swabi By-pass Road (12 Km).
Swabi
PKHA
- - - - Line Deptt 2266.44 0 50 50 0 0 0 0 - -
July - 2017
Feasibility study and detailed engineering design in porgress. PC-I/DCE submitted to competent forum for approval. Pre-PDWP held. Summary Submiited to CA for funding of scheme from ADP instead of ADB portfolio.
1290
(New)
170566-Widening, Improvement and BT of Swari, Dewana Baba road (11 Km) including RCC Bridge at Tangu, District Buner.
Buner
PKHA
- - - - Line Deptt 600 0 5 5 0 0 0 0 - -
July - 2017
PC-II for Rs.6 m approved in DDWP on 19/06/2017.
1291
(New)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
PKHA
- - - - Line Deptt 30 0 10 10 0 0 0 20 33% -
July - 2017
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress.
1292
(New)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir (SDG).
Dir Lower
PKHA
- - - 26-07-17 - 410.621 0 40 40 0 0 0 370.621 10% -
July - 2017
Procurement under process.
1293
(New)
170629-Widening & Improvement of Tarnawa Kohala Bala Road (35 Km) District Haripur.
Haripur
PKHA
- - - - Line Deptt 3100 0 20 20 0 0 0 0 - -
July - 2017
PC-II for Rs.15.500 m approved in DDWP on 19/06/2017 for conducting feasibility study and detailed engineering design.
1294
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
- - - - - 3354.081 0 72 72 0 0 0 0 - -
July - 2017
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1294
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
- - - - - 20963 0 5240.75 5240.75 0 0 0 0 - -
July - 2017
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1295
(New)
170174-Construction of Swat Motorway SH: Provincial Equity (VGF) Phase-II.
Provincial
PKHA
- - - - Line Deptt 6000 0 0.001 0.001 0 0 0 0 - -
July - 2017
PC-I submitted to PDWP for approval. Summary for SBLC submitted to CA for approval.
1296
(New)
170521-F/S & Dualization of Mardan-Swabi road.
Provincial
PKHA
- - - - Line Deptt 8000 0 195 195 0 0 0 0 - -
July - 2017
As per descision of the steering committee, the scheme will be financed under PRRP. ADB assistance.
1297
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
15-03-11 30-06-18 - 22-04-04 - 100 10.81 84.19 84.19 29.887 0 10.81 5 95% 11%
July - 2017
1297
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
15-03-11 30-06-18 - 22-04-04 - 14594.25 10.81 500 500 0 0 10.81 14083.44 4% 0%
July - 2017
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km, Distt road 425.55 Km, 405.89 Km, Bridges length 699.55 mtrs (10 Nos), 482.25 mtr (9 Nos) completed.
18 districts of Khyber Pakhtunkhwa
Upto till Release Jan-2016 Rs.1304.09 m
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Bannu
15-04-13 - - 25-10-11 - 114.982 131.482 0 0 0 0 131.482 0 - 100%
July - 2017
Completed.
1) RCC Bridge Ghundakai (PK-72)
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Battagram
01-11-12 - - 25-10-11 - 48.69 55.41 0 0 0 0 55.41 0 - 100%
July - 2017
Completed (bridge span 45 mtr).
RCC Bridge on Nandehar Khawar at Deshan Hotel PK-59
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Buner
- - - 11-03-16 - 100.651 56 0 0 0 0 56 44.651 - 56%
July - 2017
Bridge structure completed, approaches in progress.
1) RCC bridge on Barundu Khawar
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Dir Lower
06-12-12 - - 25-10-11 - 103.908 122.015 0 0 0 0 122.015 0 - 100%
July - 2017
Completed.
a) RCC Bridge at Badin Khawar Summer Bagh
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
15-09-15 - - 25-10-11 - 116.283 128.455 0 0 0 0 128.455 0 - 100%
July - 2017
Completed.
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mansehra
06-12-11 - - 25-10-11 - 59.85 68.02 0 0 0 0 68.02 0 - 100%
July - 2017
Completed.
1) Mansehra City Bridge PK-53
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mardan
HW
29-09-11 - - 25-10-11 - 349.12 298.184 0 0 0 0 298.184 50.936 - 85%
July - 2017
4/5 bridges completed, 1 in progress (Mayar Bridge) lauching in porgress.
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Nowshera
HW
01-08-12 - - 25-10-11 - 45 48.737 0 0 0 0 48.737 0 - 100%
July - 2017
Completed.
1) RCC bridge at Qasim Ali Baig (Taru)
1298
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Provincial
29-09-11 - - 22-01-15 - 918.425 908.303 85 85 0 0 908.303 0 100% 99%
July - 2017
Work in progress (Umbrella).
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
D.I.Khan
HW
28-02-12 - - 23-12-16 - 49.569 38.5 0 0 0 0 38.5 11.069 - 78%
July - 2017
Completed.
1) Diyal bridge (200 feet span)
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Dir Lower
- - - 23-12-16 - 2.515 18.78 0 0 0 0 18.78 0 - 100%
July - 2017
1) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Dir Upper and Lower
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Dir Upper
14-08-12 - - 23-12-16 - 22.285 18.78 0 0 0 0 18.78 3.505 - 84%
July - 2017
Completed.
1) Shomai bridge
2) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Dir Upper and Lower
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Provincial
02-02-12 - - 23-12-16 - 764 262.615 50 50 0 0 262.615 0 - -
July - 2017
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Swat
HW
05-01-12 - - 23-12-16 - 174.45 155.703 0 0 0 0 155.703 18.747 - 89%
July - 2017
Out of 7 bridges, 6 completed, 1 launching under process (Rahim Abad Bridge). Paymnet made to Pak Army 3 year ago.
1) Mula Baba Bridge
2) Amankot (Rahim Abad) Bridge
3) Rahim Abad Bridge
4) Barikot (Babaji Baba) Bridge
5) Faiz Abad Bridge
6) Kuz Kalay Khwaza Khela Bypass bridge
7) Chinkolai Faqira Bridge
8) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Swat
1299
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Tank
01-10-12 - - 23-12-16 - 67.825 30.852 0 0 0 0 30.852 36.973 - 45%
July - 2017
18/18 piles completed. Both abutments completed.
1) Shah Alam bridge (180 feet)
1300
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
- - - 02-05-14 - 6.05 5.268 0 0 0 0 5.268 0.782 - 87%
July - 2017
PC-II approved. Consultant selected.
1300
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Provincial
- - - 02-04-14 - 100 5.268 50 50 0 0 5.268 0 - -
July - 2017
PC-II approved.
1301
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
- - - 26-12-13 - 100 2.473 44.422 44.422 0 0 2.473 0 - -
July - 2017
PC-II approved.
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Buner
28-02-14 - - 17-04-14 - 151.056 134 0 0 0 0 134 17.056 - 89%
July - 2017
All 3 bridges completed.
1) Sura Bridge
2) Sunigrame Bridge
3) Bagra Baridara
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Chitral
- - - 17-04-14 - 0 0 0 0 0 0 0 0 - -
July - 2017
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Lower
25-10-14 - - 17-04-14 - 127.977 95.837 0 0 0 0 95.837 32.14 - 75%
July - 2017
Completed (3 bridges).
1302
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Upper
- - - 17-04-14 - 122.148 97.57 0 0 0 0 97.57 24.578 - 80%
July - 2017
Out of 4 bridges, 1 completed, 3 launched.
1) Steel bridge Sheringla Colony PK-92
2) Steel bridge Jan Bahtti PK-91
3) Steel bridge Sordam PK-92
4) Steel bridge Almas Dag Tarpatar PK-92
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43