Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : February - 2017,

Showing Page Number : 39 of 45

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1112
(OG)
150218-Improvement / Rehabilitation and BT of Rajjar roads to Saleem Khan Road, Gegey road, District Charsadda & Mardan.
Mardan
HW
- - - 28-08-15 - 45 0 10 10 10 10 10 35 22% 22%
February - 2017
RW 2000 mtr completed.
1112
(OG)
150218-Improvement / Rehabilitation and BT of Rajjar roads to Saleem Khan Road, Gegey road, District Charsadda & Mardan.
Provincial
- - - 28-08-15 - 45 0 10 10 10 9.447 9.447 0 - -
February - 2017
Work in progress.
1113
(OG)
140972-F/S and BT of 10 Km road from Mera Mada Khel to Godar, Tor Ghar.
Tor Ghar
22-07-15 - - 19-02-15 - 234.56 98.231 25 41.386 35.136 28.886 127.117 111.329 53% 54%
February - 2017
Length 8 Km - earth work, structure work in progress.
1114
(OG)
150872-Construction of Machai Peek Coor Kalam (Oagi road) District Tor Ghar.
Tor Ghar
- - - 10-09-15 - 99.785 0.484 5 5 3.75 2.5 2.984 94.301 5% 3%
February - 2017
Earth work 40% completed.
1115
(New)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 0 25 66.646 58.396 0 0 181.95 12% -
February - 2017
Pre-qualification called on 06/02/2017. Technical propsal approved. Finanacial bid approval under process.
1116
(New)
160641-Improvement of road village Tordher, Swabi.
Swabi
- - - 26-10-16 - 40 0 5 5 0 0 0 35 13% -
February - 2017
Work order issued.
1117
(New)
160623-F/S, Design & Construction of overhead / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan.
Mardan
HW
- - - 27-12-16 - 1750 0 100 70 45 0.5 0.5 1650 6% 0%
February - 2017
Scheme approved on 27/12/2016 for Rs.1750 m. AA awaited. Summary submitted to CA for enhancement of cost.
1118
(New)
160643-Construction of Gajee, Karshat Shingle Road (4 Km), District Shangla.
Shangla
- - - 24-11-16 - 40 0 10 10 0 0 0 30 25% -
February - 2017
Tender invited on 05/04/2017.
1119
(New)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
- - - 03-11-16 - 464.813 0 5 5 0 0 0 459.813 1% -
February - 2017
Evaluation of pre-qualification of contractors approved, tender invited on 28/02/2017. Tender approval under process.
1120
(New)
160624-F/S, Design and Supervision of Mansehra Bypass District Mansehra.
Mansehra
- - - - - 20 0 20 8 3 0 0 0 100% -
February - 2017
LOA issued on 10/01/2017. Survey work started.
1121
(New)
160625-F/S and Design of Qalandarabad Bypass road (4 Km), District Abbottabad.
Abbottabad
- 30-06-17 - - - 4 0 10 10 5 0 0 0 100% -
February - 2017
LOA issued on 10/01/2017. Survey work completed.
1122
(New)
160628-F/S, Design & Construction & Supervision of Bypass road from Ayub Bridge Havellian (N-35) to Dhmatour at Abbottabad (18.325 Km).
Abbottabad
- - - 03-11-16 - 1470.041 0 40 40 0 0 0 1430.041 3% -
February - 2017
NIT floated for pre-qualification on 23/12/2016. Tech evaluation in progress.
1123
(New)
160627-F/S, Design and Construction of (a) Akunbandi bridge (b) from Rehana to Chapra (c) Rehana to Tachar (d) Noordi to Pind Jamal Khan (e) Talkar road, District Haripur.
Haripur
- - - 03-11-16 - 236.504 0 30 40.924 10.924 0 0 206.504 13% -
February - 2017
4 units - tender approval under process (1 unit), work started (3 units).
1124
(New)
160626-F/S, Design and Construction of Makhnial road from Changla to Islamabad.
Abbottabad
- - - - Line Deptt 1988 0 67 67 0 0 0 1921 3% -
February - 2017
PC-II approved. RFP called on 18/08/2016. LOA issued to consultant on 26/10/2016. Survey completed. PCI/DCE prepared for Rs.2.23 billion rationalization required. Pre-PDWP will be held on 14/03/2017.
1125
(OG)
140626-Construction of road from Amberi Killa to Daratang Phase-II SH: Km 17 to Km 35 District Karak (19 Km).
Karak
PKHA
02-11-15 - - 06-03-15 - 798.06 100 20 20 15 15 115 678.06 15% 14%
February - 2017
Pack-1 (7 Km) - earth work, sub-base, base course in progress. Pack-2 (7 Km) - earth work, culverts in progress. Pack-3 (5.825 Km) - earth work in progress.
1) Package-1 (7 Km)
2) Package-2 (7 Km)
3) Package-3 (5.825 Km)
1126
(OG)
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km).
Kohat
PKHA
02-11-15 - - 04-06-15 - 294.598 160 60 60 45 45 205 74.598 75% 70%
February - 2017
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress.
1127
(OG)
140879-Dualization / Rehabilitation of road from Gulshan Abad Chowk to Jerma Bridge via Hangu Pattak (11.5 Km) District Kohat.
Kohat
PKHA
12-11-15 - - 04-06-15 - 1329.516 360 80 80 60 60 420 889.516 33% 32%
February - 2017
Pack-1 - sub base, sub grade, NGC, embankment completed (Km-2 to 3). Pack-2 - embankment, sub grade in progress. Pack-3 - embankment, sub grade, sub base (shoulder portion) in progress. Pack-4 - pile load test at Jerma bridge completed, NGC, embankment in progress.
1) Package-1
2) Package-2
3) Package-3
4) Package-4
5) Package-5
1128
(OG)
120282-Improvement and Widening of Road from Mufti Mehmood Flyover to old Budni Bridge upto Wahid Garhi 9 Km on PH S-I i/c reconstruction of old Budhni Bridge District Peshawar.
Peshawar
PKHA
15-01-14 - - 12-04-16 - 1119.959 361.533 50 50 37.5 37.5 399.033 708.426 37% 36%
February - 2017
Bridge completed and opened for traffic. Section-1 (1550 mtr) - asphalt overlay both side completed, drain in progress. Section-2 (1000 mtr)- sub base, aggregate base, RCC pipe culvert completed, asphalt base course, asphalt WC in progress. Financial evauation proposals of bidder opened for balance approach road.
1) 2.5 Kms
1129
(OG)
140628-Construction of Dual Carriageway from Chamkani to Badaber via Surezai with a link to Peshawar Ring Road. SH: Peshawar Ring Road to Badaber via Surezai (16 Km) (Phase-I), Distt. Peshawar.
Peshawar
PKHA
- - - - Line Deptt 7500 0 50 50 37.5 37.5 37.5 0 - -
February - 2017
The CA has decided to execute the scheme through PPP mode. Node meeting has been held Dec 2016 case has been forwarded to Unit Committee in P&D Deptt.
1130
(OG)
120284-Dualization of Mardan Charsadda Road i/c Dargai Bypass and Rehabilitation of existing dual carriageway to Charsadda City Phase-II (14.5 Km), District Charsadda.
Charsadda
PKHA
14-05-13 - - 14-12-12 - 1394 1225 70 70 52.5 52.5 1277.5 99 93% 92%
February - 2017
10/14 Km completed, Dargai bypass (3 Km) in progress.
1131
(OG)
120295-Dualization of Charsadda - Tangi Road i/c Utmanzai Road Bypass District Charsadda (23 Kms).
Charsadda
PKHA
30-05-13 - - 14-12-12 - 1979.638 1646.151 40 40 30 30 1676.151 293.487 85% 85%
February - 2017
Length 23 Km - 18 Km sub base, 12 Km WBM, 13 Km asphaltic base completed. 3 bridges completed, 1 in progress.
1132
(OG)
140621-Dualization of Naguman Shabqadar Section of Provincial Highway S-A, District Charsadda (13 Km).
Charsadda
PKHA
19-02-16 - - 25-03-15 - 1609.96 280 100 100 75 75 355 1229.96 24% 22%
February - 2017
Land acquisition in progress. 6 Nos culverts, clearing and grubbing in progress.
1133
(OG)
150287-Improvement of Takht-e-Bhai Rajjar Road from Ghani Khan road to Saro Shah (14 Km), District Charsadda.
Charsadda
PKHA
- - - 21-01-16 - 1498.019 0 50 50 37.5 37.5 37.5 1448.019 3% 3%
February - 2017
Work in progress on 2 Nos culverts. Trees and stumps removed. 5 Nos culverts in progress.
1134
(OG)
130680-Improvement and widening of Malang Baba - Nizampur Road, Nowshera.
Nowshera
PKHA
15-09-14 - - 02-11-15 - 1726.703 995.999 150 150 112.5 112.5 1108.499 580.704 66% 64%
February - 2017
Length 21 Km - earth work 60%, sub base, base course, structure work in progress. Bridge and culverts in progress.
1135
(OG)
150764-F/S, Design and Construction of Swabi By-pass Road (12 Km).
Swabi
PKHA
- - - - Line Deptt 2266.44 0 15 15 0 0 0 0 - -
February - 2017
Feasibility study and detailed engineering design in porgress. PC-I/DCE submitted to competent forum for approval. Pre-PDWP held. Summary Submiited to CA for funding of scheme from ADP instead of ADB protfolio.
1136
(OG)
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner.
Buner
PKHA
21-10-15 - - 02-12-16 - 776.39 30 53.39 53.39 35.791 35.791 65.791 0
February - 2017
Length 25 mtr - diversion, load test pile, pile 16/16, pile cape 3/3, pier shaft 5/5, transum 3/3, abutment A&B, RCC beam 12/12, deck slab 2/2, diaphragm 24/24, RW 44/240 completed.
1137
(OG)
140629-Construcction of Swat Motorway (Land Acquisition).
Swat
PKHA
10-06-14 - - 29-07-16 - 5850 4668.987 10 10 10 10 4678.987 1171.013 80% 80%
February - 2017
Land payment of all the mozas of all districts made to the concerend revenue officers. 56 Km land acquired and handed over to FWO.
1138
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
04-09-15 - - 07-01-15 - 318.69 145 50 50 37.5 37.5 182.5 123.69 61% 57%
February - 2017
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress.
1139
(OG)
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper.
Dir Upper
PKHA
31-01-11 - - 07-01-15 - 1798.521 1251.587 50 50 37.5 37.5 1289.087 496.934 72% 72%
February - 2017
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed.
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges
1140
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
PKHA
08-10-15 - - 19-02-15 - 988.52 200 50 50 37.5 37.5 237.5 738.52 25% 24%
February - 2017
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
1141
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
- - - - - 344.978 0 50 50 37.5 37.5 37.5 294.978 14% 11%
February - 2017
Work started on side drain.
1142
(OG)
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad.
Abbottabad
PKHA
29-12-15 - - 07-01-15 - 983.904 357 50 50 37.5 37.5 394.5 576.904 41% 40%
February - 2017
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress.
1143
(OG)
140877-Construction of Haripur Bypass Road (23 Km).
Haripur
PKHA
30-09-15 - - 28-01-15 - 3712.05 980 500 500 375 375 1355 2232.05 40% 37%
February - 2017
Length 23 Km - Pack-1 to 6 work started. Land acquisition payment completed.
1144
(OG)
20665-Construction / Supervision of new Road Works.
Provincial
PKHA
20-06-06 - - 20-03-06 - 1104.58 870.354 40 40 32.5 32.5 902.854 194.226 82% 82%
February - 2017
Construction supervision of new road works.
1145
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
PKHA
15-10-10 - - 23-08-11 - 253.57 153.496 25 25 18.75 18.75 172.246 75.074 70% 68%
February - 2017
Conusltancy services for feasilbility study and design and framing PC-I.
1146
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
PKHA
21-11-15 - - 17-04-14 - 498.16 131.25 10 10 7.5 7.5 138.75 356.91 28% 28%
February - 2017
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
1147
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
PKHA
21-10-15 - - 25-03-15 - 2759.858 220 40 121.933 111.933 111.93 331.93 2499.858 9% 12%
February - 2017
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
1148
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Nowshera
PKHA
04-09-15 - - 28-01-15 - 2796.766 427.25 50 131.93 119.43 119.43 546.68 2319.516 17% 20%
February - 2017
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress.. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
1149
(OG)
160193-Project Directorate for Swat Expressway.
Swat
PKHA
01-08-16 - - 05-08-16 - 67.401 0 16.67 16.67 12.501 12.501 12.501 50.731 25% 19%
February - 2017
Project directorate setup.
1150
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
PKHA
- - - 02-12-16 - 59.318 0 15 15 11.25 11.25 11.25 44.318 25% 19%
February - 2017
PIU setup, staff deputed. Revised AA approved.
1151
(OG)
160251-Construction of Swat Motorway Phase-I VGF Component for 2016-17.
Swat
PKHA
- - - 29-07-16 - 6000 0 3000 6000 6000 6000 6000 3000 50% 100%
February - 2017
56 Km land handed over for physical work. Topographic survey for design completed in 56 Km. Concrete batch plant created in 2 Km.
1152
(New)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
PKHA
- - - - Line Deptt 30 0 20 20 0 0 0 10 67% -
February - 2017
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress.
1153
(New)
160631-F/S and Design of Expressway from Chakdara to Mingora City, District Swat.
Swat
PKHA
- - - - - 50 0 20 20 0 0 0 30 40% -
February - 2017
PC-II for Rs.50 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Alignment finalized. Detail survey in progress.
1154
(New)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir (SDG).
Dir Lower
PKHA
- - - - Line Deptt 3.75 0 30 30 0 0 0 0 100% -
February - 2017
PC-II for Rs.3.750 m approved in DDWP-I on 19/07/2016. Consultant selected. Survey completed. PC-I/DCE under preparation.
1155
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
- - - - Line Deptt 2250 0 20 20 0 0 0 0 - -
February - 2017
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1155
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
PKHA
- - - - Line Deptt 15351 0 200 200 0 0 0 0 - -
February - 2017
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1156
(New)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
- 30-06-17 - - Line Deptt 0.01 0 0.01 0.01 0 0 0 0 - -
February - 2017
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1156
(New)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
PKHA
- 30-06-17 - - Line Deptt 1000 0 1000 1000 0 0 0 0 - -
February - 2017
PPTA consultancy TOR will be submitted by ADB. PC-II for 1 million USD submitted to Chief Infra on 19/01/2017.
1157
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
15-03-11 - - 22-04-04 - 14594.25 12652.99 2553.84 2553.84 1703.55 782.52 13435.51 0 100% 92%
February - 2017
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km, Distt road 425.55 Km, 405.89 Km, Bridges length 699.55 mtrs (10 Nos), 482.25 mtr (9 Nos) completed.
18 districts of Khyber Pakhtunkhwa
Upto till Release Jan-2016 Rs.1304.09 m
1157
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
PMU
15-03-11 - - 22-04-04 - 100 10.81 5 5 3.75 0 10.81 84.19 16% 11%
February - 2017