Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : December - 2016,

Showing Page Number : 43 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
88518
(OG)
GPS Remin Kass (Flood Affected)
Dir Upper
28-10-16 - - - Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
December - 2016
T3 - lean concrete completed and materials delivered for footings. LB, Dev work - not yet started.
88519
(OG)
GPS Kass Barikot (Flood Affected)
Dir Upper
28-10-16 - - - Line Deptt 21.119 0 0 0 0 0 0 21.119 - -
December - 2016
T3 - lean concrete completed and materials delivered for footings. LB, Dev work - not yet started.
88611
(OG)
GPS Hisar Baba (Flood Affected)
Malakand
15-08-16 - - - Line Deptt 21.864 0 0 0 0 0 0 21.864 - -
December - 2016
Neck columns, RW and dug well in progress.
88612
(OG)
GHS Inzergai (Flood Affected)
Malakand
24-11-16 - - - Line Deptt 33.537 0 0 0 0 0 0 33.537 - -
December - 2016
Excavation for M4 in progress.
88613
(OG)
GPS Jalal Kot (Flood Affected)
Malakand
15-08-16 - - - Line Deptt 15.083 0 0 0 0 0 0 15.083 - -
December - 2016
GF slab concrete of T7 poured.
88711
(OG)
GPS No.1 Mishak (Flood Affected)
Nowshera
23-08-16 - - - Line Deptt 21.882 0 0 0 0 0 0 21.882 - -
December - 2016
Plinth beam done.
88712
(OG)
GGPS Maroba Nizampur (Flood Affected)
Nowshera
20-08-16 - - - Line Deptt 21.882 0 0 0 0 0 0 21.882 - -
December - 2016
Lean done, foundation in progress.
88713
(OG)
GGPS Pashtoon Garhi (Flood Affected)
Nowshera
01-09-16 - - - Line Deptt 15.938 0 0 0 0 0 0 15.938 - -
December - 2016
GF slab completed.
88714
(OG)
GPS Kandi Tazaden (Flood Affected)
Nowshera
28-08-16 - - - Line Deptt 21.882 0 0 0 0 0 0 21.882 - -
December - 2016
GF slab completed.
88715
(OG)
GPS Bab-e-Jadeed (Flood Affected)
Nowshera
02-10-16 - - - Line Deptt 8.725 0 0 0 0 0 0 8.725 - -
December - 2016
Plinth beam done.
88716
(OG)
GPS No.1 Kotarpan (Flood Affected)
Nowshera
16-10-16 - - - Line Deptt 19.172 0 0 0 0 0 0 19.172 - -
December - 2016
Plinth beam done.
88717
(OG)
GPS Tor Dherai (Flood Affected)
Nowshera
03-09-16 - - - Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
December - 2016
Plinth beam done.
88718
(OG)
GPS Sherin Kotai (Flood Affected)
Nowshera
18-08-16 - - - Line Deptt 33.309 0 0 0 0 0 0 33.309 - -
December - 2016
FF columns completed. SF BBM in progress in both module.
88719
(OG)
GPS Shahab Khel Kaka Sahib (Flood Affected)
Nowshera
29-08-16 - - - Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
December - 2016
Slab in progress.
88811
(OG)
GHS Amnavi (Flood Affected)
Shangla
28-11-16 - - - Line Deptt 51.392 0 0 0 0 0 0 51.392 - -
December - 2016
Layout for T3 and T6 has been given, excavation in progress.
88812
(OG)
GGPS Begumar Lahore (Flood Affected)
Shangla
28-07-16 - - - Line Deptt 18.78 0 0 0 0 0 0 18.78 - -
December - 2016
Footing concrete completed, neck columns in progress.
88813
(OG)
GMS Bilkanai (Flood Affected)
Shangla
20-07-16 - - - Line Deptt 26.97 0 0 0 0 0 0 26.97 - -
December - 2016
Steel fixing for T7 plinth beam in progress.
88814
(OG)
GGPS Shalmano Chakasar (Flood Affected)
Shangla
25-07-16 - - - Line Deptt 18.78 0 0 0 0 0 0 18.78 - -
December - 2016
T4 - excavation, RW in progress.
88815
(OG)
GHS Shang (Flood Affected)
Shangla
28-11-16 - - - Line Deptt 62.528 0 0 0 0 0 0 62.528 - -
December - 2016
Lean concrete of T6 poured, preparation for footing in progress.
88816
(OG)
GGPS Shalmano Kotkai (Flood Affected)
Shangla
20-09-16 - - - Line Deptt 22.56 0 0 0 0 0 0 22.56 - -
December - 2016
Footing formwork for T3, RW in progress,
88817
(OG)
GGPS Qambari (Flood Affected)
Shangla
24-10-16 - - - Line Deptt 16.085 0 0 0 0 0 0 16.085 - -
December - 2016
Levelling and dressing for T7 in progress.
88911
(OG)
GGPS Bara Bandai (Flood Affected)
Swat
06-09-16 - - - Line Deptt 15.263 0 0 0 0 0 0 15.263 - -
December - 2016
Work has been stopped since November, notice issued.
88912
(OG)
GPS Muraday (Flood Affected)
Swat
17-09-16 - - - Line Deptt 20.735 0 0 0 0 0 0 20.735 - -
December - 2016
Footing concrete for T3 completed
88913
(OG)
GGPS Serai Gut (Flood Affected)
Swat
03-10-16 - - - Line Deptt 20.735 0 0 0 0 0 0 20.735 - -
December - 2016
Footing concreted done., BB under floor completed. Slow pace of work.
88914
(OG)
GGMS Laikho Qayum Abad (Flood Affected)
Swat
29-07-16 - - - Line Deptt 14.377 0 0 0 0 0 0 14.377 - -
December - 2016
GF slab concrete poured.
88915
(OG)
GPS Biha (Flood Affected)
Swat
26-09-16 - - - Line Deptt 25.064 0 0 0 0 0 0 25.064 - -
December - 2016
RW around T4 and T7 are in progress, plinth beam will be poured after RW completed.
88916
(OG)
GGPS Godha (Flood Affected)
Swat
- - - - Line Deptt 17.023 0 0 0 0 0 0 17.023 - -
December - 2016
Layout given, excavation started. There was land dispute.
88917
(OG)
GPS Godha (Flood Affected)
Swat
22-09-16 - - - Line Deptt 17.023 0 0 0 0 0 0 17.023 - -
December - 2016
Footing concrete completed, neck columns in progress.
88918
(OG)
GPS Pacha Kalay (Dardyal Kabal) (Flood Affected)
Swat
27-07-16 - - - Line Deptt 20.735 0 0 0 0 0 0 20.735 - -
December - 2016
GF long columns completed.
88919
(OG)
GGPS Kas (Flood Affected)
Swat
22-10-16 - - - Line Deptt 14.377 0 0 0 0 0 0 14.377 - -
December - 2016
Plinth beam concrete poured in T7.
89110
(OG)
GPS Chinda Khora (Flood Affected)
Swat
23-08-16 - - - Line Deptt 30.097 0 0 0 0 0 0 30.097 - -
December - 2016
Work stopped since last month because of unavailability of fund has been resumed now, preparing for plinth beam.
89111
(OG)
GPS No.2 Maloach (Flood Affected)
Swat
26-07-16 - - - Line Deptt 21.351 0 0 0 0 0 0 21.351 - -
December - 2016
GF floor slab concrete poured, long columns for FF in progress.
99991
(OG)
Construction Re-Hydration and Maternity Center at Kohati Gate Peshawar (Prime Minister's Directive).
Peshawar
PBC-2
- - - - Line Deptt 95.57 92.688 0 0 0 0 92.688 2.882 - 97%
December - 2016
External sewerage in progress.
99992
(OG)
Construction of Medical City in Dabgari Gardens Peshawar.
Peshawar
PBC-2
- - - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2016
Consultants hiring under process.
889111
(OG)
GGP Manglawar (Militancy Affected)
Swat
- - - - Line Deptt 21.81 0 0 0 0 0 0 21.81 - -
December - 2016
Finishing works and snag list rectification.
889112
(OG)
GHS Gul Bandai (Militancy Affected)
Buner
- - - - Line Deptt 21.592 0 0 0 0 0 0 21.592 - -
December - 2016
In progress.
889113
(OG)
GGPS Chuprial (Militancy Affected)
Swat
- - - - Line Deptt 13.88 0 0 0 0 0 0 13.88 - -
December - 2016
Re-tendered and work started.
889114
(OG)
GPS Inzer Maira (Militancy Affected)
Buner
15-11-16 - - - Line Deptt 19.994 0 0 0 0 0 0 19.994 - -
December - 2016
Excavation in progress.
889114
(OG)
GMS Gul Bandai (Militancy Affected)
Buner
- - - - Line Deptt 14.79 0 0 0 0 0 0 14.79 - -
December - 2016
Re-tendered, work order issued.
889115
(OG)
BHU Kotanai (PD) (Militancy Affected)
Swat
- - - - Line Deptt 18.4 0 0 0 0 0 0 18.4 - -
December - 2016
Repair work in residential quarters.
889116
(OG)
BHU Bishbanr (PD) (Militancy Affected)
Swat
- - - - Line Deptt 12.91 0 0 0 0 0 0 12.91 - -
December - 2016
Repair work in MO residence.
889117
(OG)
GPS Raidgai (Militancy Affected)
Dir Lower
- - - - Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
December - 2016
NIT floated.
889117
(OG)
GGPS Gumbatai (Militancy Affected)
Dir Lower
- - - - Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
December - 2016
NIT floated.
889117
(OG)
GPS Meramai (Militancy Affected)
Dir Lower
- - - - Line Deptt 17.996 0 0 0 0 0 0 17.996 - -
December - 2016
NIT floated.
889117
(OG)
GPS Maidan Bandai (Militancy Affected)
Dir Lower
09-07-16 - - - Line Deptt 29.994 0 0 0 0 0 0 29.994 - -
December - 2016
M3 - GF columns casting in progress. M4 - excavation completed, only dressing in progress. LB - not yet started.
889117
(OG)
GHS Maidan Bandai (Militancy Affected)
Dir Lower
08-11-16 - - - Line Deptt 48.75 0 0 0 0 0 0 48.75 - -
December - 2016
Ushap - lean concrete completed, steel cutting for footing in progres. M3, LB, Dev works - not yet started.
889117
(OG)
GPS Charbagh (Militancy Affected)
Swat
- - - - Line Deptt 43.46 0 0 0 0 0 0 43.46 - -
December - 2016
Work order issued.
889117
(OG)
GPS Torakay (Militancy Affected)
Swat
- - - - Line Deptt 0 0 0 0 0 0 0 0 - -
December - 2016
Drooped.
889117
(OG)
BHU Mashkomai (PD) (Militancy Affected)
Swat
- - - - Line Deptt 12.156 0 0 0 0 0 0 12.156 - -
December - 2016
Re-tendered and work started.
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43