Progressive Review for the month(s) of : September - 2017,

Showing Page Number : 33 of 44

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
930
(OG)
150134-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Nowshehra.
Nowshera
- - - 24-06-16 - 72.154 0 10 10 0 0 0 62.154 14% -
September - 2017
Work order issued. Site not yet H/O.
1) Rescue 1122 Pabbi
2) Rescue 1122 Nowshera
3) Rescue 1122 Jehangira
931
(OG)
150135-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Swabi.
Swabi
- - - 26-11-15 - 350 0 10 10 0 0 0 0 - -
September - 2017
Site/scope of work not identified.
932
(OG)
150648-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in Tehsil Rustam & Katlang District Mardan.
Mardan
- - - 04-06-15 - 185.21 0 10 10 0 0 0 0 - -
September - 2017
Site not yet H/O.
933
(OG)
130372-Establishment of Emergency Rescue Services (Rescue 1122) in District Swat.
Swat
22-04-15 - - 09-12-16 - 55.31 30.886 55 55 32.712 2.799 33.685 0 100% 61%
September - 2017
Out of 2 units, 1 in progress, 1 site not H/O (Matta).
1) Saidu Sharif
2) Matta
934
(OG)
150658-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Dir Lower.
Dir Lower
- 30-06-18 - 26-11-15 - 137.445 0 10 10 0 0 0 0 - -
September - 2017
Site not yet identified by client deptt.
935
(OG)
160545-Establishment of Emergency Rescue Services (Rescue 1122) in District Dir Upper.
Dir Upper
- - - 23-12-16 - 241.089 0 10 10 0 0 0 0 - -
September - 2017
936
(OG)
160217-Establishment of Emergency Rescue Services (Rescue 1122) in District Chitral.
Chitral
- - - 21-01-16 - 411.88 0 10 10 0 0 0 0 - -
September - 2017
937
(OG)
150137-Establishment of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122) in District Mansehra.
Mansehra
- - - 26-11-15 - 137.445 0 10 10 0 0 0 0 - -
September - 2017
Site/scope of work not identified.
938
(OG)
140316-Establishment of Emergency Rescue Services (Rescue 1122) in District Abbottabad.
Abbottabad
- - - 19-11-14 - 3 0 10 10 0 0 0 0 100% -
September - 2017
LOA issued to consultant on 03/03/2015. PC-I/DCE for Rs.57.999 m re-submitted to Secretary R&R on 28/01/2016. Land not available.
939
(OG)
160543-Establishment of Emergency Rescue Services (Rescue 1122) in District Haripur.
Haripur
- - - 23-12-16 - 242.629 0 10 10 0 0 0 0 - -
September - 2017
Site/scope of work not identified.
940
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Mardan
21-11-04 30-06-18 - 08-10-12 - 140.049 116.916 129.388 129.388 129.388 1.826 118.742 0 100% 85%
September - 2017
Out of 5 unit, 4 in progress, 1 court case.
940
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Peshawar
BD-2
05-05-11 30-06-18 - 08-10-12 - 268.214 192.916 0 0 0 0 192.916 75.298 - 72%
September - 2017
Out of 7 units, 3 completed & H/O, 4 site not available for last 4 years. Client deptt has requested to cap the project on 04/01/2017.
940
(OG)
100385-Development of Emergency Rescue Services (Rescue 1122) in Khyber Pakhtunkhwa (Phase-II).
Provincial
- 30-06-18 - 25-02-14 - 1208.258 309.832 83.998 83.998 0 0 309.832 0 - -
September - 2017
941
(OG)
110537-Reconstruction and Rehabilitation of Disaster Affected Infrastructure in Khyber Pakhtunkhwa.
Abbottabad
01-07-14 30-06-18 - - Line Deptt 40 40 0 0 0 0 40 0 - 100%
September - 2017
Completed.
941
(OG)
110537-Reconstruction and Rehabilitation of Disaster Affected Infrastructure in Khyber Pakhtunkhwa.
Chitral
- 30-06-18 - - Line Deptt 148.003 169.793 0 0 0 0 169.793 0 - 100%
September - 2017
Completed.
1) Chitral Booni road near District Jail Chitral
2) Bomborate road (Ayun to Dobash)
3) Rombor road from Dobash to Rombor
4) From Dobash to Bomborate
5) Joghore Suspension Bridge
6) Birir road and bridge
7) Begusht Valley road
8) Damshoghour Orghuch road
9) Arkari Valley road with bridge
10) Chitral Booni road (Km-48 to 75)
11) Rech road
12) Domel link road
13) Terich road
14) Garam Chashma Kandojal road
15) Hassan Abad Karim Abad bridge
16) Garam Chashma road
17) Garam Chashma Parabag road
18) Biori road
19) Shishi Koh Madaklasht road
20) Patrangaz Dieveseer bridges
941
(OG)
110537-Reconstruction and Rehabilitation of Disaster Affected Infrastructure in Khyber Pakhtunkhwa.
Mardan
15-01-13 30-06-18 - - Line Deptt 79.182 77.592 17.71 17.71 17.71 0 77.592 0 100% 98%
September - 2017
Completed & H/O.
941
(OG)
110537-Reconstruction and Rehabilitation of Disaster Affected Infrastructure in Khyber Pakhtunkhwa.
Provincial
- 30-06-18 - 05-05-17 - 384 247.385 76 76 0 0 247.385 0 - -
September - 2017
944
(OG)
150749-Enhancement Capacity of Khyber Pakhtunkhwa Emergency Rescue Service (Rescue 1122).
Provincial
- - - 04-06-15 - 557.8 0 5 5 0 0 0 0 - -
September - 2017
947
(New)
170288-Establishment of Emergency Rescue Service (Rescue - 1122) in District Karak.
Karak
- - - - Line Deptt 250 0 5 5 0 0 0 0 - -
September - 2017
948
(New)
170287-Establishment of Emergency Rescue Service ( Rescue - 1122) in District Hangu.
Hangu
- - - - Line Deptt 250 0 5 5 0 0 0 0 - -
September - 2017
949
(New)
170283-Purchase of Land for Establishment of Khyber Pakhtunkhwa Emergency Services Academy and Construction of Boundary Wall.
Provincial
- - - - Line Deptt 700 0 5 5 0 0 0 0 - -
September - 2017
952
(New)
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper.
Kohistan
- 30-06-18 - - Line Deptt 0 0 0 0 0 0 0 0 - -
September - 2017
PC-I/DCE for Rs.44.086 m submitted to AD Ware House PDMA on 21/08/2017.
952
(New)
170337-Construction of Warehouses in District Kohistan, Chitral and Dir Upper.
Provincial
- 30-06-18 - - Line Deptt 100 0 70 70 0 0 0 0 - -
September - 2017
955
(OG)
140998-F/S, Design and Construction / Rehabilitation of Roads (a) Chesan Katch (b) Bazai (c) Kot Gulan to Manzai Tank (6 Kms).
Tank
- 30-06-18 - - - 60 43.6 23.15 23.15 11.575 11.258 54.858 0 100% 91%
September - 2017
Length 6 Km - earth work, strucutre in progress, sub base, WBM, TST completed.
PK-69
956
(OG)
150788-Construction / BT of Road from Bazaya to Gulan Kot via Babakhel to Umer Khan Kalay UC Tatha and Tatoor to Latti Kalay UC Tatha District Tank.
Tank
01-06-15 - - 10-09-15 - 100 11.3 10 10 3.55 3.55 14.85 78.7 21% 15%
September - 2017
Length 7.5 Km - 3 Km earth work, sub base in progress.
957
(OG)
130397-F/S for Flood Protection Works and Restoration of Damages to DI.Khan - Darya Khan Bridge District DI.Khan.
D.I.Khan
HW
12-05-15 30-06-18 - 24-01-14 - 59 42.25 2.88 2.88 1.44 1.44 43.69 13.87 76% 74%
September - 2017
3 units - 2 completed (U/S Main Right Spur, U/S Additional Right Spur), 1 90% completed (U/S Right Guide Bund).
1) Main Righ Spur
2) Additional Spur
3) Right Guide Bund Upstream
4) Left Guide Bund Upstream
958
(OG)
130604-Improvement, Rehabilitation and Construction of Roads in Kulachi Area, DI.Khan.
D.I.Khan
HW
10-09-14 30-06-18 - 03-04-14 - 328.679 320.42 4.959 4.959 0 0 320.42 3.3 99% 97%
September - 2017
Completed (34.95 Km).
1) Daraban to Kaur via Zarkani (7.5 Kms)
2) Kulachi to Tank via Rori Deewan Shah Km-19 to 25 (7 Kms)
3) New Gara Khan to Kot Walidad (5 Kms)
4) Saggu to Kot Zaffar (3 Kms)
5) Kulachi to Jahan Khani (3.30 Kms)
6) Saggu to Kohawar (3.30 Kms)
7) Maddi road to Gara Jana (2.16 Kms)
8) Kot Attal Sharif (balance work 1.77 Kms)
9) Tank road toGara Mohabat (balance work 1.52 Kms)
10) Maddi road to Gara Ibrahim (0.90 Kms)
959
(OG)
140894-F/S and Construction of 9 Km Circular Road, PK-64, DI.Khan.
D.I.Khan
HW
28-05-15 30-06-18 - 02-03-17 - 197.162 127.003 50.495 50.495 25.248 17.812 144.815 19.664 90% 73%
September - 2017
Phase-1 (9 Km) - 9 Km completed. Road marking, center media in progress.
1) Circular road 5.73 Kms
2) Bannu road 1.60 Kms
3) Diyal road 2.05 Kms
4) Zaffar Abad raod 2.50 Kms
5) Multan road 2.25 Kms
6) Sheikh Yousaf road 2.70 Kms
7) Dinpur road 2 Kms
8) Circular raod to old Parova Chungi in front of Bahu Petroleum 0.17 Kms
960
(OG)
140985-F/S, Design and Construction / Rehabilitation of Roads (a) Awan Road (b) Loke Road (c) Jabal Wala Road (d) Nadeem Shah Road (e) Kurar Shedi (8 Kms), DI.Khan.
D.I.Khan
HW
08-06-15 30-06-18 - 28-01-15 - 79.96 33.25 9.191 9.191 4.596 4.5 37.75 37.519 53% 47%
September - 2017
Length 8 Km - 7 Km completed. Remaining 1-Km WBM in progress.
Namenclature changed.
1) Awan road 2 Kms
2) Loak road 2 Kms
3) Bali Shumali road 1 Km
4) Nadeem Shah road 1 Km
5) Kurrar Shiddi road PK-65 2 Kms
961
(OG)
140986-F/S, Design and Construction / Rehabilitation of Roads (a) Multan road to Basti Gazar (8 Km), (b) Balu Hazara Link rd, (c) Main DI.Khan-Multan rd to Rangpur Janubi (5 Km), (d) Katcha Babar rd to Kacha Hazara (1 Km), (e) IH to Distry#4 (1.8 Km), DI.Khan.
D.I.Khan
HW
24-07-15 30-06-18 - 11-02-15 - 130 68.55 94.75 94.75 47.375 22.136 90.686 0 100% 70%
September - 2017
Length 13 Km - 10 Km road completed. Remaining 3-Km WBM in progress.
962
(OG)
140987-F/S, Design and Construction of Main Daraband Road from Sagu to Madi via Gara Unra Attal Sharif Road (16 Km) Kulachi, DI.Khan.
D.I.Khan
HW
21-04-16 - - 28-01-15 - 210.57 54.9 60 60 21.3 21.3 76.2 95.67 55% 36%
September - 2017
Length 16 Km - earth work completed. S/Base 8-Km completed. Revised PC-I/DCE for Rs.210.223 m approved, AA awaited.
PK-67
963
(OG)
150780-(a) Construciton / Rehabilitation of road from Tank Ada to Zafar Abad Colony, Tank Ada to Darraban Chungi (b) Road from Circular Road to Muryali Morr, Shah Alam Abad Road, Eye Hospital rd, Chashma rd to Village Singar, Sheikh Yousaf Abad rd, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 10-09-15 - 199.99 18.55 50 50 17.75 17.75 36.3 131.44 34% 18%
September - 2017
Length 10.24 Km -Zafarabad portion - 2.25 Km BT completed. Remaining 6-units S/Base in progress. Revised PC-I/DCE for Rs.199.968 m approved. AA awaited.
964
(OG)
150782-Construction / Rehabilitation of Roads from UC Dhap, UC Mandran, UC Ketch, UC Hissam, UC Yarik, UC Korai, UC Zandani, UC Band Kurai, UC Chehkan, UC Laar in District DI.Khan.
D.I.Khan
HW
15-04-16 - - 02-11-15 - 199.919 39.691 25 25 8.875 8.875 48.566 135.228 32% 24%
September - 2017
Length 26.7 Km - 5 Km BT compleed. Sub base (20-Km), base course, WBM (14-Km in progress).
965
(OG)
150784-Construction / BT of Lunda Sharif to Jumma Sharif Road UC Lunda Sharif and Charri Bhohar to Jhok Ameen Road UC Mairan, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 03-11-16 - 219.804 30.748 40 40 14.2 14.2 44.948 149.056 32% 20%
September - 2017
Length 20 Km - earth work completed. S/Base (10-Km) completed. WBM 5-Km completed).
1) Lunda Sharif to Juma Sharif road UC Lunda Sharif
2) Charri Bhohar to Jhoke Ameen road UC Miran
966
(OG)
150785-Construction of Road from Chodhwaan to Gataar to Jandi Babar to Maro Main Road (UC Chodhwaan) and Musazai Sharif to Kot Shanawaz to Gara Mir Alam to Gara Essa Khan (UC Musazai Sharif), District DI.Khan.
D.I.Khan
HW
12-04-16 - - 10-09-15 - 199.624 8.9 25 25 8.875 8.875 17.775 165.724 17% 9%
September - 2017
Length 26 Km - Jandi Babar to Maroo - earth work, sub base, structure work completed. Revised PC-I/DCE for Rs.199.526 m approved, AA awaited.
967
(OG)
150786-Construction / Improvement and widening of Paniala Paharpur road, Paniala Chunda road, Pharpur Bypass Road and Construction of one number Bridge on Paniala Bypass Road, District DI.Khan.
D.I.Khan
HW
15-04-16 - - 05-05-17 - 199.822 78.357 20 20 7.1 7.1 85.457 101.465 49% 43%
September - 2017
Length 9.3 Km - 7 Km completed. Panyala Paharpur road - earth work 75%, sub-base 40%, base course 15% completed. Panyala Chuda road - earth work 80%, sub base 75% completed. Paharpur bypass road - earth work completed (80%). Bridge - boring soil investigation, confirmatory boring, test pile loading completed. Deck slabs (11/14) completed.
968
(OG)
140664-F/S, Design and Construction of Road from Village Abasa to Shahab Khel, District Lakki Marwat (15 Kms).
Lakki Marwat
02-07-15 - - 28-01-15 - 293.915 129.61 40 40 14.8 14.8 144.41 124.305 58% 49%
September - 2017
Length 21.5 Km - earth work 13 Km completed. Sub-base 13 Km completed, base course (8-Km completed), remaining in progress, TST (8-Km completed) remaining in progress.
969
(OG)
150795-Construction of road from (a) Ghazi Khel to Phar Khel Pacca (5.156 Km), (b) Zangi Khel to Mela Mandra Khel (3-Km) and (c) Gambilla Phar Khel to Wanda Pashan (2.5 Km), District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 96.787 0 20 20 7.1 1.283 1.283 76.787 21% 1%
September - 2017
Length 5.15 Km - earth work 50% completed.
To be change of nomenclature
970
(OG)
150797-Construction / Black topping of road from Chashma road to Wanda Nizami via Wanda Dalwati, Wanda Baru District Lakki Marwat.
Lakki Marwat
- - - 03-11-16 - 150 0 10 10 5 0.439 0.439 140 7% 0%
September - 2017
Length 6 Km - earth work started.
971
(OG)
150880-BT of road from Gandi Chowk to Nar Muzaffar Khan District Lakki Marwat.
Lakki Marwat
12-02-16 30-06-18 - 20-08-19 - 30 9.325 20.425 20.425 10.213 10.2 19.525 0.25 99% 65%
September - 2017
Length 3 Km - earth work, road work completed, structure work 30% completed.
972
(OG)
140636-F/S, Design and Construction of Prestressed RCC Bridge over Tochi River on Marwat Canal Road, Bannu.
Bannu
- 30-06-18 - 07-01-15 - 208.652 136.084 77.568 77.568 27.537 27.537 163.621 0 100% 78%
September - 2017
462 mtr - test pile completed, piling, pier completed, girder completed. 4/21 deck slabs completed.
973
(OG)
140885-Reconstruction / Rehabilitation of Road from Kingar Bridge to Narmi Khel (15 Kms), Bannu.
Bannu
- - - 09-02-16 - 372.849 29.674 30 37 17.75 17.75 47.424 313.175 16% 13%
September - 2017
Length 10 Km - earth work, sub base completed, structure work (slab culvert) in progress.
974
(OG)
140886-F/S, Design & Construction of 05 Km roads from Bannu City to Kakki via Mundan, Bannu.
Bannu
- - - 02-11-15 - 175.218 3.75 20 20 7.1 0.974 4.724 151.468 14% 3%
September - 2017
Structure work 600 rft completed. Removal of encroachment in progress. 2nd Revised PC-I/DCE for Rs.220 m approved, AA awaited.
975
(OG)
140887-Construction of 8 Km Road from Bannu Link Road to Village Sada Khel, Bannu.
Bannu
- 30-06-18 - 28-01-15 - 76.516 28.193 49.073 49.073 17.421 0 28.193 0 100% 37%
September - 2017
Length 8 Km - road work 5 Km ready for asphalt. 1.5 Km disputed (court stay). Remaining (1.5-Km) earth work completed.
976
(OG)
140983-Constn / Ext: and BT of road (a) Narmi Khel to Gul Andar Korma (2 Km) (b) Marwat Canal to Lake-Shuviey (2 Km) & (c) Spin Filling Station to Gul Badin Sardi Khel (2 Km), District Bannu.
Bannu
08-09-15 30-06-18 - 13-02-15 - 59.965 14.048 43.417 43.417 15.413 6.325 20.373 2.5 96% 34%
September - 2017
Length 6 Km (3 units) - 2 units (4 Km) WBM in progress. 1 unit at serial no. (a) shifting involved, summary under process.
977
(OG)
141018-F/S, Design & Construction of Road from Kashu Khel Chowk via Sarki Khel Barmi Khel to Highway Bannu (8 Km).
Bannu
23-07-15 - - 23-12-16 - 90.612 18.837 10 10 3.55 3.55 22.387 61.775 32% 25%
September - 2017
Length 5 Km - TST 1.5-Km completed. Remaining 3.5 Km ready for TST.
978
(OG)
150790-Construction / BT of 10 Km Roads in PK-70, District Bannu.
Bannu
- - - 02-11-15 - 100.1 10.75 20 20 7.1 7.1 17.85 69.35 31% 18%
September - 2017
Length 10 Km (15 units) - structure work, sub base in progress.
979
(OG)
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu.
Bannu
- - - 23-12-16 - 200 0 20 20 7.1 2.687 2.687 180 10% 1%
September - 2017
Work started (approved 10 Km). Revised PC-I/DCE for Rs.436.034 m submitted, Pre-PDWP held.
980
(OG)
150878-Repair and Rehabilitation of Jandu Khel Road and Bannu DI.Khan road to Nar Dilasa Shah road, District Bannu.
Bannu
11-08-16 30-06-18 - 18-07-17 - 45.933 17 30 30 10.65 10.65 27.65 0 100% 60%
September - 2017
Length 10 Km - 1 - 3 completed. Tendering in progress for Bannu DI.Khan road to Mulagan.
1) Jandu Khel (Km-4)
2) Jandu Khel road to Tatar Khel link (Km-1)
3) Dilasa Shah (Km-1)
4) Bannu DI.Khan road to Mulagan
981
(OG)
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu.
Bannu
- - - 02-11-15 - 150.1 0.073 10 10 0 0 0.073 140.027 7% 0%
September - 2017
Financial bid called. Delay due to P&D direction for conversion from TST to Pre-mix - PC-I submitted but deffered. With the direction to execute TST.