Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : July - 2017,

Showing Page Number : 34 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1026
(OG)
150823-Construction and Blacktopping of roads (a) Jandai Pul to Kakakhelo Dheri U/C Umerzai (b) Jangai to Shaberra U/C Agra, District Charsadda.
Charsadda
25-02-16 30-06-18 - 10-09-15 - 125 135.06 13.75 13.75 4.881 0 135.06 0 100% 100%
July - 2017
8.5 Km - 8 Km asphalt completed.
1027
(OG)
150825-Construction and Blacktopping of roads (a) Shabqadar Chowk to Matta including Bridge, (b) Haji Zai to Yaqhi Band via Tarkha and Masal Qila to road via Mian Essa, District Charsadda.
Charsadda
- - - 03-11-16 - 150 40 60 60 21.3 0 40 50 67% 27%
July - 2017
Length 7 Km - 2 Km asphalt completed. Revised PC-I/DCE for Rs.350 m submitted to SE Peshawar on 20/07/2017.
1028
(OG)
150881-Construction of road from Sardheri to Dosehra road, Charsadda.
Charsadda
- 30-06-18 - 20-08-15 - 40.5 12.25 28 28 9.94 0 12.25 0.25 99% 30%
July - 2017
Length 5 Km - 3 Km asphalt completed.
1029
(OG)
150948-Reconstruction & Rehabilitation of roads from Haryana to Hajizai, Nazimabad to Gujar Kali, District Charsadda.
Charsadda
- - - 20-08-15 - 50 45.076 3.478 3.478 1.235 0 45.076 1.446 97% 90%
July - 2017
4 Km - 3 Km asphalt completed. Revised PC-I/DCE for Rs.150 m submitted to SOR on 01/08/2017.
1030
(OG)
150954-Construction and BT of road (a) Peshawar road to Kodai UC Agra (b) Koachaki to Ajon Kallay via Hassanabad Kandaro Kally UC Shodag, Charsadda.
Charsadda
26-02-16 - - 10-09-15 - 125 51.755 43.867 43.867 15.573 0 51.755 29.378 76% 41%
July - 2017
8.5 Km - 4 Km asphalt completed.
1031
(OG)
150980-Construction of Sarwar Abad Umarzai Road and Road from Shakh No.4 to Shakh No.5 via Zarbab Ghari Maira Umarzai, District Charsadda.
Charsadda
29-02-16 - - 10-09-15 - 80 36.598 43.152 43.152 15.319 0 36.598 0.25 100% 46%
July - 2017
6.5 Km - 3 Km asphalt completed.
1032
(OG)
151069-Construction of Sro Kalay Road from Yaka Ghund Road to Subhan Khwar, District Charsadda.
Charsadda
- 30-06-18 - 18-11-15 - 20 8.5 11.25 11.25 3.994 0 8.5 0.25 99% 43%
July - 2017
2 Km - 1 Km asphalt completed.
1033
(OG)
160629-F/S, Design and Construction of Link road from Shabqadar Naguman (PKHA) to Shabqadar Battagram road (PKHA) via Attakai, District Charsadda.
Charsadda
- - - 23-12-16 - 206.95 76.996 70 70 0 0 76.996 59.954 71% 37%
July - 2017
Land paymnet made. Work stopped due to land dispute.
1034
(OG)
140672-F/S, Design and Construction of Bridge at Kabul River connecting Mohib Banda / Pashtun Gharai on Right Bank and Kheshki on Left Bank, District Nowshera.
Nowshera
HW
23-01-15 - - 27-10-14 - 480.592 503.644 40 40 14.2 0 503.644 0 100% 100%
July - 2017
Length 450 mtr - Bridge substantially completed opened to Traffic. Revised PC-I/DCE for Rs.680.592 m submitted to SOR on 01/08/2017.
1035
(OG)
140935-F/S, Design, Improvement & Widening of Road from Akora Khattak to Manai - Dooran - Tarkhel i/c link from Shahab Khel to Guldheri, Sawarkhel-Pitao to Kaka Sahib Eidgah, Khwar Miangan to Khawryan via Bagh Gali to Bus Adda, Kaka Sahib, Nowshera.
Nowshera
HW
13-05-15 - - 02-03-17 - 910.279 426.892 164.997 164.997 58.574 0 426.892 318.39 65% 47%
July - 2017
Length 27 Km - earth work 100%, sub base 15 Km, WBM 15 Km, WC 12 Km, structure work 95%, PCC road 6 Km completed. Revised PC-I/DCE for Rs.1010 m submitted to CE Center.
1036
(OG)
140936-F/S, Design and BT of internal roads Pirpiai - Azakhel Bala - Payan - Dagai - Banda Nabi, Badrashi, Nowshera. SH: Const of internal road in UCs Dagai-Banda Nabi, Pirpiai, Badrashi, Azakhel Bala & Payan, District Nowshera (Phase-II).
Nowshera
HW
30-03-15 - - 05-05-17 - 750 427.927 200 200 71 0 427.927 122.073 84% 57%
July - 2017
Length 25.6 Km - earth work 100%, sub base 14 Km, WBM 14 Km, WC 16 Km, structure work 95% completed. Revised PC-I/DCE for Rs.1050 m submitted to SOR.
1037
(OG)
140938-F/S, Design & Improvement / BT of Internal 16 Km road at Kheshgi Bala and Payan, Nowshera.
Nowshera
HW
23-03-15 - - 23-12-16 - 750 168.772 100 100 35.5 0 168.772 481.228 36% 23%
July - 2017
Length 16 Km - 16 Km completed. Revised PC-I/DCE for Rs.850 m submitted to SOR.
1038
(OG)
140939-F/S & Construction of (a) Bakhtai-Kottli Khurd-Kottli Kalan road i/c Bridges (b) road from Cherat road to Spinkhak Village, Nowshera.
Nowshera
HW
16-03-15 - - 19-11-14 - 199.992 182.999 100 100 35.5 0 182.999 0 100% 92%
July - 2017
Length 6.7 Km - earth work 100%, sub base 6.5 Km, WBM 6.5 Km, WC 6.5 Km, structure work 90% completed. Bridge (80 mtr) completed. Revised PC-I/DCE for Rs.400 m submitted to SOR on 01/08/2017.
1039
(OG)
140940-F/S, Design & Construction of RCC Bridge on Kabul River at Kashti Pul, Nowshera Cantt.
Nowshera
HW
- - - 28-01-15 - 166.812 33.934 37.406 37.406 13.279 0 33.934 95.472 43% 20%
July - 2017
Contract agreement sanctioned by CA. FWO mobilized. Piling/bore, girder casting in progress. Revised PC-I/DCE for Rs.370 m submitted to SOR on 18/07/2017.
1040
(OG)
140992-F/S, Design & Rehabilitation / Widening of Road from GT Road to Khushal Khan Khattak Mazar, Akora Khattak, Nowshera.
Nowshera
HW
11-03-15 - - 19-11-14 - 124.99 118.494 30 30 10.65 0 118.494 0 100% 95%
July - 2017
Length 8.3 Km - 8 Km completed.
1041
(OG)
141019-F/S, Design & Construction / Rehabilitation of Roads (a) GT road to Said Akbar Koroona (b) Ayub Abad to Essori Bala (c) Jehangira Kati Maina (d) Pitao Payan to Dargai village (e) GT road Khwar Mohallah Shen Bagh Koroona, District Nowshera.
Nowshera
HW
25-05-15 - - 28-01-15 - 194.551 206.96 20 20 7.1 0 206.96 0 100% 100%
July - 2017
Length 12 Km - completed. Revised PC-I/DCE for Rs.294.551 m submitted to SOR on 01/08/2017.
1042
(OG)
141021-F/S, Design & Construction / Rehabilitation of Roads (a) Khair abad to Mandoo Khel Village (b) Camp Koroona Yousaf Abad Akora (c) Adamzai to Momond Ghari (d) Jehangira Chowk to Railway Station, District Nowshera (10 Km).
Nowshera
HW
08-06-15 - - - - 194.914 173.47 19.994 19.994 7.098 0 173.47 1.45 99% 89%
July - 2017
Length 10 Km - earth work, sub-base 7 Km, WBM 7 Km, WC 7 Km, structure work 95% completed. Revised PC-I/DCE for Rs.284 m submitted to SOR on 01/08/2017.
1043
(OG)
141024-F/S, Design & Construction / Rehabilitation of roads (a) Gajoo Khel Ameero road (b) Jabbi road (c) Piran Bala and Payan & (d) From Duran to Masamkhel via Malikhel Bala Payan, District Nowshera.
Nowshera
HW
07-03-15 30-06-18 - 03-12-14 - 135.674 144.501 36.326 36.326 12.896 0 144.501 0 100% 100%
July - 2017
Length 11 Km - completed. Revised PC-I/DCE for Rs.200 m submitted to SOR on 01/08/2017.
1044
(OG)
150807-Construction of drain, pavement of streets and internal roads of UCs Pabbi, Khan Sher Garhi, Chowki Mumraz, Akbar Pura & Taru Distt Nowshera.
Nowshera
HW
01-05-16 - - 02-03-17 - 492.382 173.693 60 60 21.3 0 173.693 258.689 47% 35%
July - 2017
Length 23 Km - earth work, sub base, WBM, structure work, street pavement in progress. Revised PC-I/DCE for Rs.750 m submitted to SE.
1045
(OG)
150809-Construction / Pavement of roads / streets alongwith allied works in UCs Aman Kot, Mohib Banda, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 191.93 100 100 35.5 0 191.93 58.07 83% 55%
July - 2017
Length 17.5 Km - earth work, sub base, WBM, structure work, street pavement in progress. Revised PC-I/DCE for Rs.500 m submitted to SE.
1046
(OG)
150810-Construction / pavement of roads / streets in UCís Kheshgi Bala, Kheshgi Payan, Aman Garh and Gandheri, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 175.272 100 100 35.5 0 175.272 74.728 79% 50%
July - 2017
Length 15 Km - structure work, street pavement in progress. Revised PC-I/DCE submitted to SE.
1047
(OG)
150813-Construction / Rehabilitation of Road from Inzari to Hisartang and Shaidu Khwar to Shinwari Koroona via Eidgah District Nowshera.
Nowshera
HW
- - - 26-11-15 - 100 6.384 90 90 31.95 0 6.384 3.616 96% 6%
July - 2017
Earth, structure work in progress. Revised PC-I/DCE for Rs.200 m submitted to SOR on 01/08/2017.
1048
(OG)
150816-Const./Rehab. of Roads in Village Kotar Pam Village Bara Banda UC Bara Banda, GT Road to Fazal Gange and Hassan Abad Risalpur GT Road to Mohallah Hassan Abad Rashakai, Kandar, Risalpur to Ghala Dher, UC Zara Miana, UC Pir Sabak, UC Mughalky, Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 200 117.52 53.483 53.483 18.986 0 117.52 28.997 86% 59%
July - 2017
Length 8.5 Km - asphalt 7 Km completed, structure work in progress.
1049
(OG)
150955-Construction of drains, pavement of streets and internal roads of Dak Ismail Khel, Shah Kot, Dak Besud, Balu, Spin Khak and Jalozai Distt Nowshera.
Nowshera
HW
01-05-16 - - 02-03-17 - 400 199.393 100 100 35.5 0 199.393 100.607 75% 50%
July - 2017
Length 18.5 Km - earth work, sub base, WBM, structure work in progress. Revised PC-I/DCE submitted for Rs.700 m to CE.
1050
(OG)
150957-Construction of road from Jalozai to Kotli Kalan Distt: Nowshera.
Nowshera
HW
01-05-16 - - 09-02-15 - 136.789 82.424 40 40 14.2 0 82.424 14.365 89% 60%
July - 2017
Length 9 Km - WC in progress. Revised PC-I/DCE for Rs.135.186 m submitted to SOR on 04/05/2017.
1051
(OG)
150958-Construction / Rehabilitation of Jehangira Bypass and Nizampur road to Charpani village, District Nowshera.
Nowshera
HW
- - - 26-11-15 - 99.999 23.5 30 30 10.65 0 23.5 46.499 54% 24%
July - 2017
3/11 Km asphalt completed. Revised PC-I/DCE for Rs.200 m submitted to SOR on 01/08/2017.
1052
(OG)
151074-Construction / Pavement of roads / streets alongwith allied works in UCs Kurvi and Dheri Kati Khel, District Nowshera.
Nowshera
HW
01-05-16 - - 23-12-16 - 350 209.946 100 100 35.5 0 209.946 40.054 89% 60%
July - 2017
18 Km - earth work, sub base, WBM, structure work in progress. Revised PC-I/DCE for Rs.550 m submitted to SE.
1053
(OG)
170588-Upgradation of Six (6) Numbers of Level Crossings (Phattak) in Nowshera Khyber Pakhtunkhwa (1st Phase).
Nowshera
HW
- - - 28-03-17 - 87.38 0 20 20 7.1 0 0 0 - -
July - 2017
Deposit work - Rs.7.1 m will be paid as processing fee.
1054
(OG)
140695-F/S, Design and Rehabilitation of (1) Tor Dher-Alla Dher Road (2) Nawa Nehar Kund Park-Alla Dher Road, District Swabi.
Swabi
- - - 22-01-15 - 180 66.536 50 50 17.75 0 66.536 63.464 65% 37%
July - 2017
Length 18 Km - BT 3 Km sub-base 5 Km, base course 5 Km, structure in progress.
1055
(OG)
140961-F/S, Design and Construction of road from Shewa Chowk to Shewa Village (6 Km), District Swabi.
Swabi
- 30-06-18 - 23-12-16 - 200 120.215 34.59 34.59 12.279 0 120.215 45.195 77% 60%
July - 2017
Length 6 Km - 5 Km asphalt completed.
1056
(OG)
140962-F/S, Design & Construction of Road Dobian to Nazar and Tarkha (8 Km), District Swabi.
Swabi
- - - 27-01-17 - 250 100.832 60 60 21.3 0 100.832 89.168 64% 40%
July - 2017
Length 8 Km - 7 Km asphalt, 1.5 Km WBM, 1 Km embank completed.
1) Dobian to Nazar and Tarkha (8 Km)
2) Tarkha road to Shaheedan (2.60 Km) PK-33
3) Nazar Chowk to Ismaila (7 Km) PK-33
4) Mardan-Swabi main road to Ismaila (4 Km) PK-33
1057
(OG)
141002-F/S, Design and Construction / Rehabilitation of Roads and street pavements (a) Kunda Topi (b) Gar Mergoz (c) Zarobi Topi (d) Zaida Kaddi (e) Marghuz Yousafi Swabi (21 Kms).
Swabi
- - - 22-01-15 - 210 158.257 70 70 24.85 0 158.257 0 100% 75%
July - 2017
Length 12 Km - 12 Km asphalt completed, structure work in progress.
1058
(OG)
141005-F/S, Design and Construction of Bridge on Nuranji Nullah at Banr Karnal Sher Khan Kali Road, District Swabi.
Swabi
- 30-06-18 - - - 97.804 118.507 0.001 0.001 0 0 118.507 0 100% 100%
July - 2017
PC-I under preparation.
1059
(OG)
150849-Const / Reh / widening of road from (a) Shahmansoor Town to Sikandari (b) Govt Girls High School Manari Bala to Saleem Khan Chowk (c) Panjpir main road to Shaga Bridge (d) Qazi Abad to Aboo Banda, Swabi.
Swabi
- - - 10-09-15 - 100 51.675 20 20 7.1 0 51.675 28.325 72% 52%
July - 2017
Length 8 Km - embankment, WBM completed.
1060
(OG)
150850-Construction / BT of roads (a) Shaheed Garnay Qadamay Dheri (b) Turlandi Shehram Tarskai (c) Turlandi Khawaja (d) Turlandi Kalu Dheri Lahor Lar (e) Tarakai Lar Managai (f) Sheikh Jana Pio Dher (g) Sheikh Jana Mansabdar (h) Sheikh Jana Ahmad Khel District Swabi.
Swabi
- - - 23-12-16 - 300 85.31 75 75 26.625 0 85.31 139.69 53% 28%
July - 2017
Length 9 Km (b, c, g, h)- asphalt completed, sub base 4 Km completed, WBM in progress.
1061
(OG)
150851-Construction / BT of roads (a) Karizoo to Urmar Sadri road, (b) Palosai Khairabad, (c) Rohani Bazargay road, District Swabi.
Swabi
- - - 23-12-16 - 300 53.25 75 75 26.625 0 53.25 171.75 43% 18%
July - 2017
Length 8 Km - sub base, embankment, drain in progress.
1062
(OG)
150852-Const / Reh of Roads Baka Lar Tordher, Zakarya Salah, Haryan Salah, Jalbai Main Dhand, Faroq Banda Jehangira, Balo Haryan, Swabi Interchange Service to Sherafzal Shah Banda Balo, Swabi University, Jalsai Tordhe, Lahor Janazgah, Beka Shakh Nabi, Swabi.
Swabi
- - - 10-09-15 - 280 57.859 50 50 17.75 0 57.859 172.141 39% 21%
July - 2017
Length 13 Km - sub base, WBM, structure work in progress. Revised PC-I/DCE for Rs.330 m re-submitted to Chief Infra.
1063
(OG)
150853-F/S, Design & Constructioin / rehabilitation of roads (a) Boko to Tashkand road (b) Jhanda Pajaman road (c) Bada Check Post via Mangal Chai to Gabasni (d) Marguz Yousafi road (e) Pabani road (f) Zarobi road (g) Kalabat Khazana road, Swabi.
Swabi
- - - 10-09-15 - 250 97.223 50 50 17.75 0 97.223 102.777 59% 39%
July - 2017
Length 16 Km (10 units) - 8 Km asphalt completed, sub base, WBM, structure work in process. Revised PC-I/DCE for Rs.350 m submitted to SE.
1064
(OG)
150854-Construction of Road (a) Gabaie Panawal road (b) Leron Amarai Bala road (c) Chanai road, District Swabi.
Swabi
- - - 10-09-15 - 80 39.5 30 30 10.65 0 39.5 10.5 87% 49%
July - 2017
Length 6 Km - sub base, WBM, structure work in progress.
1065
(OG)
150888-Construction / Rehabilitation / Restoration of Access road from Swabi Interchange to Tourism related project at Hund, Swabi.
Swabi
- - - 10-09-15 - 99.696 49.25 30 30 10.65 0 49.25 20.446 79% 49%
July - 2017
Length 5 Km - widening/structural, embankment work in progress. Revised DCE for Rs.180 m submitted to SE.
1066
(OG)
150959-Construction / BT of roads (a) Parmoli Bypass road (b) Permoli Sabar Wand Lar (c) Sher Dara road (d) Speen Kany Bandi Oba (e) Speen Kany Bande Oba Dojangi road (f) Speen Kany Aman Kot Lar PCC road, District Swabi.
Swabi
- - - 23-12-16 - 300 99.918 80 80 28.4 0 99.918 120.082 60% 33%
July - 2017
Length 8 Km - PCC, base course, structure work, sub base in progress.
1067
(OG)
150960-Construction / BT of roads (a) Yar Hussain Shaheen Abad road, (b) Kas Koroona to Adena road, (c) Main road Shergaharri Asmela road, District Swabi.
Swabi
- - - 23-12-16 - 300 101.532 50 50 17.75 0 101.532 148.468 51% 34%
July - 2017
Length 8 Km - 0.6 KM asphalt completed, WBM in progress. Sub base, embankment completed.
1068
(OG)
150961-F/S, Design and Const of roads, Gara Jehangira 1 Km, Jalsai Jaganat (2 Km), Jalsai Dhok (1 Km), Doba Lar (1 Km), Zakriya Khel (1 Km), Batlasai Naray Lar Ambar (1 Km), Hayatabad Azim Garhi (1 Km), Jehangira Mera Dhab (1 Km) Swabi.
Swabi
- - - 02-11-15 - 149.63 30.875 30 30 10.65 0 30.875 88.755 41% 21%
July - 2017
Length 8 Km - embankment completed, sub base in progress.
1069
(OG)
160497-(a) Construction and BT of Mian Essa Chowk to Jehangira Road 1 Km (b) Constn of PCC road of Mian Essa to Police Chowk and Mohalla Awan Jehangira Road (0.8 Km), District Swabi.
Swabi
- 30-06-18 - 14-10-16 - 27.838 0 22.838 22.838 8.107 0 0 5 82% -
July - 2017
Length 1.8 Km - in progress.
1070
(OG)
160641-Improvement of road village Tordher, Swabi.
Swabi
- 30-06-18 - 26-10-16 - 40 0 35 35 12.425 0 0 5 88% -
July - 2017
Work in progress.
1071
(OG)
140669-F/S, Design and Construction of Bridge and Approach Roads on Khan Gari Kalpani Nullah to Arbi Banda U/C Jehangir Abad and Sari Bahlol (5 Km including Bridge), District Mardan.
Mardan
HW
21-10-15 30-06-18 - 22-01-15 - 85.614 55.654 27.36 27.36 9.713 0 55.654 2.6 97% 65%
July - 2017
5 Km/Bridge - deck slab 2/4, work on road work started.
5 Kms including bridge PK-26
1072
(OG)
140925-F/S, Design, Construction & BT of (a) Chiragh din Killy to Fazle Abad UC Maday Baba & (b) Safi Abad to Dheri Killy Hathian, Mardan.
Mardan
HW
- - - 23-12-16 - 130.656 58.927 10 10 3.55 0 58.927 61.729 53% 45%
July - 2017
Length 7.5 Km - BT 2.9 Km completed.
1) Chiragh Din Killi to Fazle Abad UC Maday Baba PK-27
2) Safi Abad to Dheri Killi Hatthian PK-27
1073
(OG)
140929-F/S, Design & Construction of roads (a) Katlang to Qadar Village (b) Kot Ismailzai (c) Shahand Maqbara to Kareem Abad (d) Toot Killy Nehar to Babanay & (e) Toot Killy Nehar to Chaghzau village, Mardan.
Mardan
HW
01-08-15 30-06-18 - 11-02-15 - 155.359 134.183 28.049 28.049 9.957 0 134.183 0 100% 86%
July - 2017
Completed (12 Km).
1) Main Katlang road to Gadar village (1.950 Kms) PK-30
2) Kot Ismailzai (1.700 Kms) PK-30
3) Shaheedano Muqbara to Kareem Abad (1.100 Kms) PK-30
4) Toot Killi road to Babaney village (1.200 Kms) PK-30
5) Toot Killi Nehar road to Chaghrzau road (0.800 Kms) PK-30
6) Construction and Black topping of Dobai Adda to Gul Abad 1.5 km.
1074
(OG)
140931-F/S, Design & Construction (a) Battagram Nehar to Zai (b) Katlang to Kudi Noor (c) Dubi Ada to Srekh (d) Katlang to Qaziabad (e) Bakhshali Dheri to Jangirh (f) Gazi Shek Babuzi (g) Charsada to Dheray Baba (h) Pir Gari (i) Fatima to GGPS (j) Main to Bala Gari (k) Muhib to Husain Madrasa, Mardan.
Mardan
HW
13-06-15 - - 11-02-15 - 110.647 83.485 26.662 26.662 9.465 0 83.485 0.5 100% 75%
July - 2017
Original scope completed (9 Km). Revised PC-I/DCE under preparation.
1) Battagram Nehar to Daulatzai road (1.700 Kms) PK-30
2) Katlang road to Khudai Noor village (1.500 Kms) PK-30
3) Dubai Adda to Sreekh village road (1.200 Kms) PK-30
1075
(OG)
140933-F/S, Design & Construction of bridge on Naranji drain on Garhi Ismail Zai Kandar area near Panjbir Baba, Mardan.
Mardan
HW
- 30-06-18 - 03-03-17 - 32.53 0.973 31.558 31.558 11.203 0 0.973 0 100% 3%
July - 2017
Test pile completed.
PK-25