Progressive Review for the month(s) of : July - 2017,

Showing Page Number : 36 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
- - - 03-11-16 - 231.52 56.924 60 60 21.3 0 56.924 114.596 51% 25%
July - 2017
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
PK 86
1127
(OG)
150947-Construction of Mingora Kokray Marghuzar road District Swat.
Swat
HW
10-02-16 30-06-18 - 20-08-15 - 45 29 15 15 5.325 0 29 1 98% 64%
July - 2017
Length 2.6 Km - road work completed, ancillary works in completion stage.
1128
(OG)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
- - - 03-11-16 - 464.813 0 30 30 10.65 0 0 434.813 6% -
July - 2017
length 13.2 KM-Work started. Earth work in progress.
1129
(OG)
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II).
Dir Lower
24-10-14 30-06-18 - 10-10-13 - 126.085 75.444 48.141 48.141 17.09 0 75.444 2.5 98% 60%
July - 2017
Length 7.8 Km - 4 Km completed. 2 Km sub base, WBM completed.
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
15-08-15 - - 14-04-15 - 1210.57 194.928 30 30 10.65 0 194.928 985.642 19% 16%
July - 2017
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
1131
(OG)
140831-F/S, Design and Construction of B/T Road from Damtal Ijara to Janbatai Barawal (6 Km) Districts Dir Lower and Dir Upper.
Dir Lower
- - - 27-01-17 - 91.62 3 40 40 14.2 0 3 48.62 47% 3%
July - 2017
Work on 15 Km in progress.
1) Dir Lower 4 Km (Km-1 to 4)
2) Dir Upper 6 Km (Km-5 to 10)
1132
(OG)
140900-F/S, Design & Improvement & BT of Kumber to Gumbat Banda Road (15 Km) Dir Lower.
Dir Lower
19-08-15 - - 28-01-15 - 162.54 34.5 30 30 10.65 0 34.5 98.04 40% 21%
July - 2017
Length 15 Km - out of 4 packages, all in progress. 2 Km BT.
1133
(OG)
140901-F/S, Design & Construction of Talash Kalpanai Bypass road (10 Km), Dir Lower.
Dir Lower
- - - 11-02-15 - 350 122 50 50 17.75 0 122 178 49% 35%
July - 2017
Land acquisition under process. Section-4 completed. Award not yet finalized. Earth work completed.
1134
(OG)
140989-F/S, Design and Construction of 4 Nos of RCC Bridges (a) Aghiraly and Arif (b) Darangal Khwar (c) Markhanai Maidan, Dir Lower.
Dir Lower
06-08-15 - - 28-01-15 - 174.826 107.833 30 30 10.65 0 107.833 36.993 79% 62%
July - 2017
Out of 4 bridges, all in progress (Agharily, Arif Killi, Darangal Khwar, Markhani Maidan bridges).
1135
(OG)
150835-Construction of RCC Bridges at Hajiabad, Munjai & Nasafa, Kano, Dir Lower.
Dir Lower
- - - 03-11-16 - 99.296 0 50 50 17.75 0 0 49.296 50% -
July - 2017
Test pile in progress.
RCC Bridges in Dir Lower (4 Nos) (a) RCC Bridge at Munjai
1136
(OG)
150837-Construction & Black Topping of Gudhar Takurro road UC Munda and Danjarri to Ijjara, Nawey Kallay, Bota & Qaziabad Tatar road Dir Lower.
Dir Lower
- - - 02-11-15 - 199.796 51.41 20 20 7.1 0 51.41 128.386 36% 26%
July - 2017
Length 12 Km - work in progress on all 6 units.
1137
(OG)
150838-Construction of RCC bridges Raidgay (Kotkay) & Gul Khawarr Maidan Dir Lower.
Dir Lower
- - - 03-11-16 - 190.549 0 20 20 7.1 0 0 170.549 10% -
July - 2017
Test pile in progress.
RCC Bridges in Dir Lower (a) RCC Bridge at Raidgay (Kotkay) (b) RCC Bridge at Gul Khawar Maidan
1138
(OG)
150839-Const of (a) Asband Swat (3 Km) (b) Shursheen (c) Joro Kashmir (2 Km) (d) Ghazo Chat Pat (e) Deghan (1 Km) (f) Dheri Tesko (3 Km) (g) Oskai (1.5 Km) (i) Laiko (1 Km) (j) Naw Kalay Bochake (2 Km) (k) Mayar Dogha (2 Km) Dir Lower.
Dir Lower
- - - 02-12-16 - 400 130.829 50 50 17.75 0 130.829 219.171 45% 33%
July - 2017
27 Km road - 10 Km completed. 17 Km in progress.
1139
(OG)
150963-Construction / Rehabiliation of roads Pato Atak & Barikot, Rabat Assigay Laram Danda, Sarbanda, Dod Khana, Shati, Mali, Watangay, Malakand Kohrey, Gadla, Banda, Karam Khel, Sparay, Danwa, Rani & Ghwaago Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 369.278 200.136 50 50 17.75 0 200.136 119.142 68% 54%
July - 2017
Length 30 Km - 12 Km BT, work in progress in all 17 units.
1140
(OG)
150964-Construction / Rehabiliation of roads Shaneey, Masho-Chinaroona, Banda Khonko Cheeno Dherey, Chinar Tangay, Ahmad Gali, Macho, Katon, Gumbat Amlok Dara, Chaman Abad, Seyar Gay, Yar Khan Banda & Nagri-Gumbat Kay, Anangro Khwar & Hajiabad Distt Dir Lower.
Dir Lower
- - - 02-11-15 - 367.574 193.674 20 20 7.1 0 193.674 153.9 58% 53%
July - 2017
Length 31 Km - 12 Km BT completed, 19 Km in prlogress.
1141
(OG)
150965-Construction / Black Topping of roads Raindalay & Kakas road UC Miskini, Union Council Mayar road, Union Council Samar Bagh and UC Kambat Road Dir Lower.
Dir Lower
- - - 02-11-15 - 275.308 37.943 10 10 3.55 0 37.943 227.365 17% 14%
July - 2017
Length 22 Km - 3 Km BT completed.
1142
(OG)
150966-Construciton of RCC Bridge at Matako Rahim Abad District Dir Lower.
Dir Lower
- - - 08-08-16 - 49.733 29.656 26.733 26.733 9.49 0 29.656 0 100% 60%
July - 2017
Length 110 mtr - piling completed, pile caping completed, launching of girders in progress.
1143
(OG)
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower.
Dir Lower
- - - 02-11-15 - 278.061 77.079 20 20 7.1 0 77.079 180.982 35% 28%
July - 2017
Length 20 - 3 Km BT completed, 17 Km in progress.
1144
(OG)
100382-Construction of Sairay Kalkot to Thall Kumrat road 10 Km, Dir Upper.
Dir Upper
11-10-12 - - 11-02-15 - 255.368 162.76 15 15 5.325 0 162.76 77.608 70% 64%
July - 2017
10 Km - 14 feet earth, structure, road work completed (original scope). Balance 4 feet wide earth work, strucuture work in progress. 10 Km road surfacing PCC completed.
PK-92 (Km-1 to 10)
1145
(OG)
140648-Construction of RCC Bridge at Khal Barkalay Bazaar PK-93 District Dir Upper.
Dir Upper
01-03-15 30-06-18 - 16-12-14 - 69.9 53.174 21.251 21.251 7.544 0 53.174 0 100% 76%
July - 2017
Completed. Approaches in progress.
1146
(OG)
140650-F/S, Design, Improvement & BT of Shingara Darra Road (8 Km) Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 120 51.348 68.152 68.152 24.194 0 51.348 0.5 100% 43%
July - 2017
Length 8 Km - earth work, structure work in progress.
1147
(OG)
140902-F/S, Design & Improvement, Rehabilitation and BT of Hattan Darra Road, Dir Upper.
Dir Upper
01-07-15 30-06-18 - 22-01-15 - 100 47.905 101.345 101.345 35.977 0 47.905 0 100% 48%
July - 2017
Length 5 Km - structure work. WBM on both side in progress. Revised PC-I submitted. Pre-PDWP held.
1148
(OG)
140903-Construction of PCC Road Samang Gulwadai Dara - 10 Km, District Dir Upper.
Dir Upper
01-07-15 - - - - 166.565 26.75 20 20 7.1 0 26.75 119.815 28% 16%
July - 2017
Length 10 Km - earth, structure work in progress .Revised PC-I submitted to Chief Infra.
1149
(OG)
140905-Construction of PCC Roads at Usherai Dara (10 Km), Dir Upper.
Dir Upper
01-07-15 - - - - 166.99 62.25 30 30 10.65 0 62.25 74.74 55% 37%
July - 2017
Revised PC-I/DCE submitted to Chief Infra.
1150
(OG)
140906-F/S, design and Widening & Rehabilitation of Nehagadra road (Phase-I) (27 Km) Dir Upper.
Dir Upper
01-06-15 - - 11-02-15 - 380.856 78.814 50 50 17.75 0 78.814 252.042 34% 21%
July - 2017
Length 27 Km - earth work, structure work, sub base, WBM in progress.
1151
(OG)
140979-F/S & Design of (a) Improvement & Rehabilitatioin of Dodba to Sheringal Swany Road (15 Km) including 3 Nos Bridges (b) Construction of RCC Bridge at Kotkay UC Sultan Khel District Dir Upper.
Dir Upper
01-08-15 - - 25-03-15 - 597.77 78.812 50 50 17.75 0 78.812 468.958 22% 13%
July - 2017
(a) 17 Km road (4 packages) - in progress in 13 Km. (b) 32/32 pile, 8 girders completed, launching in progress (Kotkay bridge).
1152
(OG)
150827-(a) Rehabilitaiton / Reconstruction of roads Ala Salamkot, Dobando Dara, Nasrat Dara, Darora Sharamkand & (b) Const of Maj General Sanullah Shaheed road at Dir Upper.
Dir Upper
01-06-16 - - 02-11-15 - 279 49.465 70 70 24.85 0 49.465 159.535 43% 18%
July - 2017
5 units - work in progress. Revised PC-I/DCE submitted to Chief Infra.
PK-91
1153
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
01-04-16 - - 02-11-15 - 325.5 50.06 40 40 14.2 0 50.06 235.44 28% 15%
July - 2017
6 units - all in progress.
PK-92
1154
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
01-04-16 - - 21-01-16 - 300 19.5 10 10 3.55 0 19.5 270.5 10% 7%
July - 2017
Out of 8 units, all in progress.
PK-93
1155
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 30-06-18 - 16-10-15 - 50 9.75 40 40 14.2 0 9.75 0.25 100% 20%
July - 2017
Length 25 Km - 70% structure work completed.
PK-91
1156
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 9.5 10 10 3.55 0 9.5 180.5 10% 5%
July - 2017
Length 13 Km - earth work 80% completed.
PK-93
1157
(OG)
151082-Construction of Bridge on Patrak-Kumrat and Kilot Road Dir Upper.
Dir Upper
- 30-06-18 - 24-06-16 - 24.712 0 14.612 14.612 5.187 0 0 10.1 59% -
July - 2017
Work started.
PK-92
1158
(OG)
70210-Construction of Khan Abdul Wali Khan By-pass road District Chitral.
Chitral
16-01-10 30-06-18 - 18-05-11 - 788.857 724.114 62.743 62.743 22.274 0 724.114 2 100% 92%
July - 2017
Completed (3.6 Km).
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
01-06-10 - - 09-03-15 - 1108.42 301.11 10 10 3.55 0 301.11 797.31 28% 27%
July - 2017
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress.
1159
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
01-06-10 - - 09-03-15 - 1108.42 0 0 0 0 0 0 1108.42 - -
July - 2017
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress. Rs.100 m demanded from Federal Govt.
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
- - - 11-02-15 - 130 5.142 5.325 5.325 5.325 0 5.142 119.533 8% 4%
July - 2017
RCC bridge in progress, 2 Km road work restarted.
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
28-10-15 - - 11-02-15 - 199.75 20.183 30 30 0 0 20.183 0 - -
July - 2017
1160
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
28-10-15 - - 11-02-15 - 69.75 47.933 5.325 5.325 5.325 0 47.933 16.492 76% 69%
July - 2017
Length 4.5 Km - 2.5 Km BT completed.
1161
(OG)
140984-F/S, Design and Construction of RCC Bridge at Ayun, Chitral.
Chitral
- - - 02-12-16 - 84.002 15 20 20 7.1 0 15 49.002 42% 18%
July - 2017
Test pile and approach road in progress.
1162
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
- - - 02-11-15 - 83.43 21.25 20 20 7.1 0 21.25 42.18 49% 25%
July - 2017
Out of 3 units, all in progress.
1163
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
- - - 02-11-15 - 75.851 42.805 21.503 21.503 7.634 0 42.805 11.543 85% 56%
July - 2017
Out of 3 units, all in progress.
1164
(OG)
170170-Rehabilitation of Internal Roads in Chitral and Drosh Cities District Chitral.
Chitral
- 30-06-18 - 02-12-16 - 41.24 0 21.24 21.24 7.54 0 0 20 52% -
July - 2017
Length 5 Km - BT 1.5 Km completed.
1) Chitral Sub Division Internal roads
2) Dorsh Sub Division Internal roads
1165
(OG)
170171-Immediate Rehabilitation of Flood Damaged (9 Nos Roads and Bridges each) due to Flash Flood and Golf 2015, District Chitral.
Chitral
- 30-06-18 - 27-01-17 - 550 0 179 179 63.545 0 0 371 33% -
July - 2017
9/9 roads work in progress. 2/9 bridges completed. 5/9 bridges in progress.
1) 9 Nos Bridges
2) 9 Nos Roads
1166
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
05-09-07 - - 25-03-15 - 406.458 183.405 30 30 10.65 0 183.405 193.053 53% 45%
July - 2017
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
1) Bataira to Mirbat Road PK-62 (B/W 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (B/W 7 KM)
1167
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 30-06-18 - 29-05-14 - 322.534 153.755 112.653 112.653 39.992 0 153.755 56.126 83% 48%
July - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach road earth work completed. 1/2 pier in progress.
1168
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
- - - 17-11-15 - 100 17.5 20 20 7.1 0 17.5 62.5 38% 18%
July - 2017
Length 6 Km - Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress.
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1169
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan.
Kohistan
- - - 17-11-15 - 200 19.3 30 30 10.65 0 19.3 150.7 25% 10%
July - 2017
Length 4.6 Km - 4 units - 1 land acquisition under process, 2 in progress (PCC road), 1 work started.
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
1170
(OG)
150875-Construction of road from Shaha to Sput Valley, Gabar Naala Road and Dong Naala Road District Kohistan.
Kohistan
- - - 10-09-15 - 80 8.5 10 10 3.55 0 8.5 61.5 23% 11%
July - 2017
Length 7 Km - 3 units - 1 earth work 100% completed, 2 work order issued (site disputed).
1) Construction of road from Soha to Sput 3 Km
2) Construction of Gabber Nullah road 2 Km
3) Construction of Dong Nullah road 2 Km
1171
(OG)
141025-F/S, Design and Construction of Road from Darman Tangay to Pashto Road, Battagram (5 Kms).
Battagram
25-05-15 30-06-18 - 28-01-15 - 69.8 35.7 33.05 33.05 11.733 0 35.7 1.05 98% 51%
July - 2017
Length 5 Km - earth work, sub-base, base course, masonry work in progress.
1172
(OG)
150845-Construction / Improvement and Black topping of internal roads of Tehsil Battagram District Battagram.
Battagram
- - - 03-11-16 - 136 0 15 15 5.325 0 0 121 11% -
July - 2017
22 units - stay vacated, work started.
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43