Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : February - 2018,

Showing Page Number : 30 of 47

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 12.665 0 0 0 0 0 0 12.665 - -
February - 2018
No Image
District Jail Charsadda
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Karak
30-11--1 30-11--1 - 30-11--1 - 19.598 0 0 0 0 0 0 19.598 - -
February - 2018
No Image
Sub Jail Karak
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Kohat
30-11--1 30-11--1 - 30-11--1 - 73.087 0 0 0 0 0 0 73.087 - -
February - 2018
No Image
District Jail Kohat
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 29.067 0 0 0 0 0 0 29.067 - -
February - 2018
No Image
District Jail Mansehra
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Mardan
30-11--1 30-11--1 - 30-11--1 - 112.042 0 0 0 0 0 0 112.042 - -
February - 2018
No Image
High Security Prison Mardan
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
No Image
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Provincial
30-11--1 30-11--1 - 30-11--1 - 367.069 0 30 30 0 0 0 0 - -
February - 2018
No Image
724
(OG)
130281-Solar Energization of various Jails in Khyber Pakhtunkhwa except Central Prison Haripur.
Tank
30-11--1 30-11--1 - 30-11--1 - 3.296 0 0 0 0 0 0 3.296 - -
February - 2018
No Image
Judicial Lockup Tank
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 152.549 0 7.5 7.5 7.5 7.5 7.5 145.049 5% 5%
February - 2018
Barracks - foundation in progress. Site handed over on 01/12/2017.
No Image
Bannu
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received.
No Image
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 152.728 13.5 10 10 10 10 23.5 129.228 15% 15%
February - 2018
Column upto roof level. Rs.30 m demanded.
No Image
DI.Khan
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Haripur
30-11--1 30-11--1 - 30-11--1 - 123.961 0 7.5 7.5 7.5 7.07 7.07 116.461 6% 6%
February - 2018
Layout given.
ADP's Images
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
PC-II for Rs.3.633 m submitted to CE North on 03/04/2016.
No Image
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
PC-II under preparation.
No Image
725
(OG)
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 450.7 13.5 50 50 0 0 13.5 387.2 14% 3%
February - 2018
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
Dropped.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.15.474 m submitted to Supdt Jail on 17/09/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Buner
30-11--1 30-11--1 - 30-11--1 - 50 0 20 20 10 0 0 30 40% -
February - 2018
Raft in progress.
No Image
District Jail Buner
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.7.052 m submitted to IG Prisons on 21/01/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Chitral
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE under preparation.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Dir Lower
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE under preparation.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Karak
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
Buner unit only left, other units removed.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE under preparation.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Kohistan
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
4 / 5 units dropped by the client deptt. XEN Buner to submitt PC-I /DCE on the new scope of work.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
Space not available in existing jail. PC-I/DCE under preparation.
No Image
Construction of 1 No Barrack at District Jail Lakki Marwat for security personnel
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE submitted.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Peshawar
BD-1
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.158.104 m submitted to AD Admin O/O IG Prisons Peshawar on 27/04/2016.
No Image
726
(OG)
150277-Construction of One Barrack in Selected Jails of Khyber Pakhtunkhwa for Security Personnel.
Provincial
30-11--1 30-11--1 - 30-11--1 - 50 0 40 40 0 0 0 0 - -
February - 2018
PC-I/DCE submitted.
No Image
727
(OG)
150281-Capacity Building of Staff in various Jails of Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 57 0 42 42 0 0 0 0 - -
February - 2018
No Image
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
Dropped.
No Image
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.64 5 5 5 5 3.424 8.424 5.64 64% 54%
February - 2018
Flooring in progress.
No Image
Sub Jail Buner
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.827 8 5.827 5.827 5.827 5.514 13.514 0 100% 98%
February - 2018
Completed & H/O (staff mess).
No Image
Karak
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Kohistan
30-11--1 30-11--1 - 30-11--1 Line Deptt 8.536 3 5.536 5.536 5.536 1.014 4.014 0 100% 47%
February - 2018
Finishing in progress.
ADP's Images
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 16.354 3.5 5.82 5.82 5.82 3.118 6.618 7.034 57% 40%
February - 2018
Roofing in progress (hall, kitchen, store.
No Image
Mansehra
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.643.960 m submitted to Supdt High Security Prison on 09/06/2016.
No Image
District Mardan
728
(OG)
150282-Construction / Improvement of messing facilities for Staff & Prisoners in the Jails of Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 54.366 19.5 44.366 44.366 0 0 19.5 0 - -
February - 2018
PC-I/DCE submitted.
No Image
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 6.548 0 3 3 3 1.453 1.453 3.548 46% 22%
February - 2018
Repair work in progress.
No Image
District Jail Buner
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 21.509 0 3 3 3 3 3 18.509 14% 14%
February - 2018
SS in progress.
No Image
District Jail Timergara
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Haripur
30-11--1 30-11--1 - 30-11--1 - 5.335 0 3 3 3 1.363 1.363 2.335 56% 26%
February - 2018
60% work completed.
No Image
Central Prison Haripur
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
No Image
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2018
No Image
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 1.396 0 1.396 1.396 1.396 0.264 0.264 0 100% 19%
February - 2018
Repair nature - work in progress.
No Image
Sub Jail Dassu Kohistan
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 106.326 0 4.019 4.019 4.019 4.019 4.019 102.307 4% 4%
February - 2018
Flooring/plastering in progress (3 Barracks).
No Image
District Jail, Mansehra
729
(OG)
160129-Re-construction of the damaged Prisons due to 26 October 2015 earthquake in Khyber Paktunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 141.114 0 50 50 0 0 0 91.114 35% -
February - 2018
No Image
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Battagram
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE re-submitted to IG Prison on 11/07/2017. Revised scope received oand re-submitted by Battgarm to XEN Haripur. Will be submitted again as per newest requirements observation, under process.
No Image
Battagram
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE submitted to IG Prison on 11/07/2017. Will be submitted again as per newest requirements observation. Under process.
No Image
Buner
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Karak
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE submitted to IG Prison on 11/07/2017.
No Image
District Jail Karak
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Kohat
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE submitted to IG Prison on 11/07/2017. Will be submitted again as per newest requirements observation. Under process.
No Image
District Jail Kohat
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Kohistan
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE re-submitted to IG Prison on 11/07/2017. Will be submitted again as per newest requirements observation. Under process.
No Image
730
(OG)
160130-Re-habilitation of Existing Jails for maintaining security and Enhacing their capacity.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
XEN Haripur (focal person) - Pre-PDWP held, observation under process. PC-I/DCE re-submitted to IG Prison on 11/07/2017. Will be submitted again as per newest requirements observation. Under process.
No Image
1) District Jail (Internment Center) Lakki Marwat
2) Repair/Rehabiliation of old barracks interview rooms and sewerage line
3) Constructio of Warder/Security Barracks (2 Nos)