Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2018,

Showing Page Number : 38 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1082
(OG)
150848-Impt / Reconst of road from Dalasa stop to Fatima to Hamza Khan to Chagharzo to Gujarabad to Sery to GHS, Bakhshali U/C Fatima, Bakhshali and Bala Garhi, UC Elaym, UC Mardan rural to Garyala, Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1092.468 415.719 250 336.342 336.342 336.342 752.061 426.749 61% 69%
January - 2018
Length 39.45 Km - 17.7 Km completed.
1083
(OG)
150974-Construction of BTR from Qutab Garh to Latif Khan Killi, village Jalala to Pir Saddu via Ghano Shah and Pre-Partition Bridge at Vill Pir Saddu Distt: Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 75 15.5 10 10 10 10 25.5 49.5 34% 34%
January - 2018
2/2 units in progress.
1084
(OG)
150975-Construction / Rehabilitation of Arbi Killi to Pomp Killi Khadi Killi to Mehtar Gundi Gujar Garhi Village road and Jandy to Malang Koroona to Said Abad road District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 90 31.117 58.383 58.383 43.788 35.703 66.82 0.5 99% 74%
January - 2018
Completed (10.7 Km).
1085
(OG)
150976-Construction of road from Miskeen Abad Jalala to Jewar via Gulpur Killi Distt Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 75 9.5 10 17 17 17 26.5 55.5 26% 35%
January - 2018
Length 5.5 Km - sub base 1.5 Km, RW 2 Km, drain 1000 mtr completed.
1086
(OG)
151079-Construction / Imp / Rehab of road from Machai Branch via Palo Dheri to Village Jalil Road and Dubai Adda to Village Chargah Road, District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 100 43.281 20 22.561 22.561 22.561 65.842 36.719 63% 66%
January - 2018
Length 3 Km - structure work in progress.
1087
(OG)
160623-F/S, Design & Construction of overhead / Flyover and bridges in UC Gujrat UC Galyara UC Bakhshali in District Mardan.
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 1975.619 11.254 100 230 180 124.463 135.717 1864.365 6% 7%
January - 2018
Work in progress on Jawad Chowk flyover and Katlang Chowk bypass.
1088
(OG)
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 429.16 302.948 30 25.65 18.15 10.65 313.598 96.212 78% 73%
January - 2018
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed. Road work on right side in progress.
1089
(OG)
70759-Re-construction of road alongwith bridge approach road Batkhela to Badwan (4.5-Kms), Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 616.053 594.505 20.298 20.298 15.224 10.149 604.654 1.25 100% 98%
January - 2018
Completed.
1090
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 130.276 20 23.502 23.502 12.1 142.376 62.993 70% 67%
January - 2018
Length 10 Km - BT 3 Km completed.
1) UC Palai (5 Km) 2) UC Agra (5 Km)
1091
(OG)
140919-F/S, Design & BT of road from Manzaray Baba to Khanoray, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 57.5 32.387 29.863 29.863 22.397 18.338 50.725 0 100% 88%
January - 2018
2 Km - 2 Km asphalt completed. Structure work in progress.
1092
(OG)
150840-Construction of Haryan Kot, Aghligah & UC's Warthair, Badaa, Selay Paty road, Sakhakot Jadeed Bandajat, UC's Kot & Ghari Usmani Khel in District Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 199.9 43.131 40 34.2 24.2 24.2 67.331 116.769 42% 34%
January - 2018
Length 20 Km - 16/16 units, 5 Km BT completed.
1093
(OG)
150841-Const & Rehab of roads Shulaway, Agra, Palay, Charat, Sharab Dara, Pirkhel and Jolagram, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 200 56.395 30 43.163 43.163 18.15 74.545 113.605 43% 37%
January - 2018
Length 20 Km 16/16 units in progress, BT 2 Km completed.
1094
(OG)
140637-F/S, Design and Construction of road from Khanano Dheri to Manjakot, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 75 11.75 63 63 31.5 19.652 31.402 0.25 100% 42%
January - 2018
Length 8 Km - 1.5 Km TST completed. Earth work, structure work, WBM in progress.
1095
(OG)
140638-F/S, Design, Improvement, BT and extension of Budal-Jabo road via Sher Ali (20 Km), District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 300 110.203 60 51.3 36.3 36.3 146.503 129.797 57% 49%
January - 2018
Length 20 Km - Pack-1 (1 to 12 Km) - earth work, structure in progress. Pack-2 (13 to 20 Km) - earth work. Structure work in progress.
1096
(OG)
140639-F/S, Design, Improvement, Widening and Extension of Nagrai Kandaro to Malka Road, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 65 22.486 20 17.1 7.1 2.838 25.324 22.514 65% 39%
January - 2018
Length 7.5 Km - earth work, structure work, sub base, WBM in progress.
1097
(OG)
140888-F/S, Design, Extension & BT of Daggar to Gokand road (12 Km), Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 144 31.744 20 20.515 20.515 12.1 43.844 92.256 36% 30%
January - 2018
Length 12 Km - earth work 50%, structure work 55% completed, 4 Km TST completed. Liability Rs.25 m.
1098
(OG)
150487-Construction of 10 Km Shingle Road / Jeepable tracks in PK-78 Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 126.05 17.75 50 42.75 17.75 17.75 35.5 58.3 54% 28%
January - 2018
Length 10 Km - 4 units in progress.
1099
(OG)
150798-Construction and Blacktopping of roads in PK-77 District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 200 12.25 20 17.1 12.1 12.1 24.35 167.75 16% 12%
January - 2018
Length 11.3 Km - 8 units in progress.
1100
(OG)
150803-(a) Impt and B/T of 15 Km roads (b) Construction and B/T of Swari Bypass road (c) Construction / extension & BT of Battara Akhun Kalay road via Koz Shamnal (i/c Cost of Land), Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 400 24.5 20 32.466 32.466 7.1 31.6 355.5 11% 8%
January - 2018
Length 21.2 Km - work started on all 10 units.
1101
(OG)
150846-Construction of road (a) Dokda to Jawari to Korsar via Poland (b) Construction of Multi Span box culverts at village Sultanwas and Ghazi Khanai, District Buner.
Buner
30-11--1 30-11--1 - 30-11--1 - 230 0.04 10 9.83 9.83 6.05 6.09 219.96 4% 3%
January - 2018
Dokada to Korsar via Poland (10 Km) - earth work in progress. Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79 - work order issued.
1) Dokada to Korsar via Poland (10 Km) 2) Multi Span/Box Culverts at Sultanwas and Ghazi Khani PK-79
1102
(OG)
130556-Improvement / construction of 8 Km road from Kirai to Mole Sar, Tehsil Besham District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 91.144 17.962 20 22.561 22.561 5.6 23.562 53.182 42% 26%
January - 2018
Length 4 Km - earth work 90% completed base Course upto 2 Km. SW started.
1) Kirai to Mole Sar road (4 Km)
1103
(OG)
130578-Improement / construction of 10 Km Road from Sasobay to Kormang, Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 137.065 37.553 20 25.122 25.122 15 52.553 79.512 42% 38%
January - 2018
Length 6 Km - Pack-1 - Km-1 - 3 - earth work 90% completed. Pack-2 - Km-4 - 6 - earth work 90% completed, structure work in progress.
1) Sasobay to Kormang road (6.065 Kms)
1104
(OG)
140953-F/S, Design & BT of Lilowni road (5 Km), Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 60 32.713 27.037 32.037 25.259 18.978 51.691 0.25 100% 86%
January - 2018
Length 5 Km - substantially completed.
1105
(OG)
140955-F/S, Design, Improvement / Widening & BT of Ranyal Chichloo Road (10 Km), Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 120 25.534 20 25.122 25.122 10 35.534 74.466 38% 30%
January - 2018
Length 10 Km - earth work 95%, masonry work 35% completed.
1106
(OG)
140956-Construction of Shahtoot Road, Tehsil Besham, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 74.763 14.462 59.211 59.211 19.586 12.067 26.529 1.09 99% 35%
January - 2018
Length 4 Km - earth work 98% completed, structure work in progress.
1107
(OG)
141004-F/S, Design and Rehabilitation of Roads (a) Martung to Dedal (b) Shikolai to Anawar (3 Km) (c) Awarai to Kandona (2 Km) & (d) Fiza to Alagram (1 Km), Shangla (12 Kms).
Shangla
30-11--1 30-11--1 - 30-11--1 - 188.14 44.905 20 24.963 24.963 10.998 55.903 123.235 34% 30%
January - 2018
Length 12 Km (4 units) - earth work, SW in progress.
1108
(OG)
150787-Widening / BT of Road from (a) Shahpoor to Logay (1.85 Km) (b) Banr Khuwargai Bazaar to Banr Kalay, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 50 7.25 45 45 22.5 20.997 28.247 0 100% 56%
January - 2018
Length 2.85 Km - RW started, earth work 60% completed. WBM (Shahpoor to Logay) asphalt in progress.
1109
(OG)
150789-Construction of Butyal to Khattak Sar (1 Km), Koz Kanra to Uch Lass road (1 Km) District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 50 9.75 45 45 22.5 14.29 24.04 0 100% 48%
January - 2018
Length 2 Km - 2 units - earth work 60% completed. SW in progress. Butyal to Khattak Sar - asphalt in progress.
1110
(OG)
150821-Construction and Rehabilitation of Biana Machkandi road, Gear Chagharzai Road, Begai Towa and Mandoria Road, District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 148.761 45.544 10 18.613 18.613 7.15 52.694 93.217 37% 35%
January - 2018
Length 14.1 Km - 4 units - all earth work in progress.
Namenclature changed.
1111
(OG)
160643-Construction of Gajee, Karshat Shingle Road (4 Km), District Shangla.
Shangla
30-11--1 30-11--1 - 30-11--1 - 40 0 30 30 10 10 10 10 75% 25%
January - 2018
4 Km shingle road - earth work 50% completed.
1112
(OG)
31122-Improvement and widening of Matta-Fazil Banda Road, Bagh Dheri - Rahat Kot Road, Gari Lalkoo Road, Beryum Gat Shawar and Gat Peochar Road, Swat (59 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 838.228 706.857 100 94.037 94.037 60.5 767.357 31.371 96% 92%
January - 2018
Out of 59 Km, 55.5 Km completed. Matta Fazil Banda Section - (21/23.5 Km BT), WBM in 8 Km completed, structure work in all packages in progress.
1) Matta Fazal Banda (Km-1 & 2) 2) Matta Fazal Banda (Km-3 to 23.5) 3) Matta Fazal Banda constn of 16 meter span bridge at Km-5 & 8 4) Bagh Dehrai Rahat Kot Road (2.50-KMs) 5) Ghari Lalkoo Road (KM-1) 6) Ghari Lalkoo Road (KM-2 to 4) 3-KMs 7) Rehabilitation of BerYum Shawar Gat Road (22-KMs)
1113
(OG)
140682-F/S, Design and Construction of Baryam to Gat Serai Road, Arkot to Biakand Road and Kabal to Kalla Kallay Road (20 Km), District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 300 253.75 38.75 38.75 19.375 19.375 273.125 7.5 98% 91%
January - 2018
Length 20 Km - 20 Km completed, structure work in progress.
1114
(OG)
140688-F/S, Design, Construction and Improvement / Rehabilitation of Mingora City Road i/c Bridge, District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 80 65.127 14.623 12.123 4.811 3.8 68.927 0.25 100% 86%
January - 2018
Length 4.8 Km - 5/5 packages - in progress. 3.7 Km BT completed. Road and structure work in progress.
1115
(OG)
140964-F/S, Design & Rehabilitation / BT of Kalam to Gujar Gabral road (flood damaged), Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 414.267 30.5 20 17.1 7.1 7.1 37.6 363.767 12% 9%
January - 2018
Length 12 Km - structure work, road work in progress (culverts and retaining wall).
1116
(OG)
140965-F/S, Design & improvement, Widening & BT of Mangwaltan to Toha Road (6.5 Km), District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 135.93 53.39 20 22.222 22.222 12.1 65.49 62.54 54% 48%
January - 2018
Length 6.5 Km - earth work 100% completed, structure work, RW, in progress, sub base 2 Km completed.
1117
(OG)
140968-F/S, Design & Construction of (a) Chapryal to Balasoor road, (b) Kherarai to Mandoor road, (c) Durash Khela to Baz Khela, (d) Mandal Daag Road & (e) Venai to Aghal road, (f) Dedpanai Village Road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 140 44.923 70 59.85 42.35 42.35 87.273 25.077 82% 62%
January - 2018
Length 14 Km - BT 5.9Km completed. Pack-1 - structure work, road work in progress. Pack-2 - structure work, road work in progress. Pack-3 - structure work, WBM in progress.
1118
(OG)
140969-F/S, Design & Construction of (a) Qalagy road UC Qalagy (b) Tall Chor Road UC Tall (c) Taran Road UC Kaley & (d) Talang Churkhai Road UC Kota, Swat (5 Km).
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 100 52.522 47.228 47.228 23.614 19.841 72.363 0.25 100% 72%
January - 2018
Length 5 Km - 4 Km completed, Work in progress (4 units).
1119
(OG)
140970-F/S, Design & Rehabilitation of Mingora Jambeel Gokand road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 450 65.688 100 100.866 100.866 58.761 124.449 284.312 37% 28%
January - 2018
Pack-1 (Km-1 to 7) - WBM Km-1 and 2 started, 1.3 Km BT. Pack-2 (Km-8 to 14) - earth work in progerss. Pack-3 (Km-15 to 20.75) - earth work in progress.
1120
(OG)
141030-Construction & Blacktopping of Manglawar to Malam Jabba Road 35 Km, District Swat.
Swat
PKHA
30-11--1 30-11--1 - 30-11--1 - 1299.6 290 10 8.55 6.05 0 290 999.6 23% 22%
January - 2018
Work order issued. Contractors mobilized.
Package-1 Package-2 Package-3
1121
(OG)
150805-Const / Repr / Reh / BT of Rahmabd Chwk-Watky Chwk, Main Gulkda, Sharifabad Quanj, Sharifabad Dheri, Hayatabad Internal, Shahidabad, Shahedabad from DAEWO Terml, Qambr Bypass-Marghozar Twn, Bhrma Khwargi, Sarinagar Twn, Yusafabad, Latifabad Mahronsh Twn, SKHA Clina, Landi Kas Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 199.99 15.944 30 34.613 34.613 18.15 34.094 154.046 23% 17%
January - 2018
14 units - all in progress.
a) Rahim abad Chowk Amankot to Watkay Chowk b) Main Road Gulkada UC Gulkada c) Sharif Abad Quanj Road UC Gulkada d) Sharif Abad Dherai Road UC Gulkada e) Hayatabad Internal Roads UC Shahdara f) Shahid Abad Road g) Shaheed Abad road from Daewoo Bus Terminal UC Rahim Abad h) Qambar Bypass to Marghazar Town Road UC Rahim Abad i) Bharama Khwargai Road UC Rangmohallah j) Sarinagar Town UC Rangmohallah k) Yousaf Abad Road UC Banr l) Latif Abad Road Mahronesh Town UC Banr m) Skha China Road UC Amankot n) Landikass Road UC Landikass  
1122
(OG)
150811-Const of road Ghalagay Dara Bypass, Balokaly to Jurbdy, Shingray to Zaray, Gogdara to Left Panjigrm, Rashaka to Topsin Sabonay, Amlok Dara to Sar Paty, Manglawar to Kas Shingral, Kas to Zary Kachakor, Ogahz, Jabba Bishbanr Gat, Sher Atraf Karbakar, Challganoray road, Qambar Road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 198.41 34.123 30 38.15 30.65 30.65 64.773 134.287 32% 33%
January - 2018
Length 19.5 Km (16 components) - all in progress.
1123
(OG)
150812-Construction of road from Nusrat Chowk to Langarr Chowk, Shamozai Jabbagai road District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 200 2.845 70 68.813 68.813 42.35 45.195 127.155 36% 23%
January - 2018
Length 9 Km - 4.7 Km BT completed. WBM, structure work in progress in remaining road.
1124
(OG)
150815-(a) Improvement / Widening & BT of Baikand to Nakhtar Kandaw road and Mian Killay to Sarbanda, Nazarabad to Ashar Banr road (b) Improvement / Widening & BT of Sigram to Malooka road (c) Construction/Rehabilitation of Malakabad to Gat road in Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 280 64 160 149.605 149.605 96.8 160.8 56 80% 57%
January - 2018
Length 18.5 Km - 3 Km BT completed.
1125
(OG)
150817-Construction / Rehabilitation / BT of Koray to Deran Patay Road, Hakeem Abad Darmay road, Sardan Road, Gamser road, Batkoo road, Azad Banda Road, Kharkai Koat road, Mula Patay road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 200 53.05 20 26.917 26.917 12.1 65.15 126.95 37% 33%
January - 2018
Length 15.9 Km - 8 units - in progress.
1126
(OG)
150819-F/S, Design, Construction and Widening of Shalpin to Jishar Road, Babu to Mashkomai Maira road,Topsin to Ganajir Top road, Chinkolai to Faqira road, Khwazakhela to Dumbara road, Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 231.52 56.924 60 58.983 58.983 36.3 93.224 114.596 51% 40%
January - 2018
Shalpin Jishar road - 40% completed. Topsin to Ganajir road - 40% completed. Khawza Khela to Dambara - 30% completed.
PK 86
1127
(OG)
150947-Construction of Mingora Kokray Marghuzar road District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 45 29 15 15 11.25 11.25 40.25 1 98% 89%
January - 2018
Length 2.6 Km - road work completed, ancillary works in completion stage.
1128
(OG)
160645-Widening & Blacktopping of Sakra to Gabeen Jabba Road (16 Km) District Swat.
Swat
HW
30-11--1 30-11--1 - 30-11--1 - 464.813 0 30 33.333 33.333 18.15 18.15 434.813 6% 4%
January - 2018
Length 13.2 Km - work started. Earth work in progress.
1129
(OG)
130669-Improvement and blacktopping of Mayar-Asmar Road, Dir Lower (Phase-II).
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 126.085 75.444 48.141 48.141 36.105 30.82 106.264 2.5 98% 84%
January - 2018
Length 7.8 Km - 7.8 BT Km completed.
1130
(OG)
140830-F/S, Design & Construction of BT roads (a) Mian Kalay to Kambat (b) Link road to Ghwara Banda, Gawardesh, Janpassa, Parata, Nawkoto and Hisarak District Dir Lower.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 1210.57 194.928 30 45.052 45.052 45.052 239.98 985.642 19% 20%
January - 2018
Length 43 Km - (a) Land acquisition under process in 22 Km. (b) Work in progress in 21 Km. BT 4 Km completed.
1131
(OG)
140831-F/S, Design and Construction of B/T Road from Damtal Ijara to Janbatai Barawal (6 Km) Districts Dir Lower and Dir Upper.
Dir Lower
30-11--1 30-11--1 - 30-11--1 - 91.62 3 40 24.2 14.2 14.2 17.2 48.62 47% 19%
January - 2018
Work on 10 Km in progress.
1) Dir Lower 4 Km (Km-1 to 4) 2) Dir Upper 6 Km (Km-5 to 10)