Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : June - 2017,

Showing Page Number : 38 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1036
(OG)
150829-Rehabilitation / Reconstruction of (a) RCC roads Kumrat, Badgoai & Jandrai Road (b) Doag Dara, Usorai Dara, Kadi Khel Dara Dir Upper.
Dir Upper
01-04-16 - - 02-11-15 - 325.5 15 5 35.06 35.06 35.06 50.06 305.5 6% 15%
June - 2017
6 units - all in progress.
PK-92
1037
(OG)
150833-Rehab / Reconstn of Sultan Khail Dara (left & right), Roghano Darra & Karro Darra road (left & right), Lugman Banda via Adhokay and Safaray Qamar Tall Distt: Dir Upper.
Dir Upper
01-04-16 - - 21-01-16 - 300 10 10 9.5 9.5 9.5 19.5 280 7% 7%
June - 2017
Out of 8 units, all in progress.
PK-93
1038
(OG)
150988-Construction of RCC Bridges at Swausar Kasai, Gulibagh & Sromanzai Dir Upper.
Dir Upper
- - - - Line Deptt 100 0 5 0 0 0 0 0 - -
June - 2017
PC-I/DCE for Rs.155 m submitted to CE.
PK-91
1039
(OG)
151071-Construction / Rehabilitation of Dir Mattaka Road, Dir Upper.
Dir Upper
01-03-16 - - 16-10-15 - 50 5 5 4.75 4.75 4.75 9.75 40 20% 20%
June - 2017
Length 25 Km - 70% structure work completed.
PK-91
1040
(OG)
151076-Construction of Nehag Dara Road (Phase-II) District Dir Upper.
Dir Upper
01-08-16 - - 09-02-16 - 200 0 10 9.5 9.5 9.5 9.5 190 5% 5%
June - 2017
Earth work 80% completed.
PK-93
1041
(OG)
151082-Construction of Bridge on Patrak-Kumrat Road.
Dir Upper
- - - - - 24.712 0 10 0 0 0 0 14.712 40% -
June - 2017
Work order issued.
PK-92
1042
(OG)
70210-Construction of Khan Abdul Wali Khan By-pass road District Chitral.
Chitral
16-01-10 - - 18-05-11 - 788.857 686.114 40 38 38 38 724.114 62.743 92% 92%
June - 2017
Completed (Length 3.6 Km).
1043
(OG)
70216-Improvement / Black Topping of Booni, Mastuj Shandoor Road (70 Km) at Chitral (PSDP Funded).
Chitral
02-05-08 - - 09-03-15 - 2323.914 204.101 10 0 0 0 204.101 2109.813 9% 9%
June - 2017
Execution by NHA.
1043
(OG)
70216-Improvement / Black Topping of Booni, Mastuj Shandoor Road (70 Km) at Chitral (PSDP Funded).
Chitral
02-05-08 - - 09-03-15 - 2323.914 204.101 0 0 0 0 204.101 2119.813 - 9%
June - 2017
Execution by NHA.
1044
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
01-06-10 - - 09-03-15 - 1108.42 204.11 10 12.5 12.5 12.5 216.61 894.31 19% 20%
June - 2017
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress.
1044
(OG)
90417-Widening & Carpeting of Booni Buzand Torkhow road (28 Km) District Chitral (PSDP Funded).
Chitral
01-06-10 - - 09-03-15 - 1108.42 204.11 100 100 100 100 304.11 804.31 27% 27%
June - 2017
Original approval for Rs.279.922 m. PSDP share - 100%, GoKP share - 0%. The work started in 2010-11. Length 28 Km - earth work 65%, structure work 60% in progress.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Chitral
- - - 11-02-15 - 130 5.142 5 26.556 26.556 26.556 31.698 119.858 8% 24%
June - 2017
RCC bridge in progress, 2 Km road work restarted.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Provincial
28-10-15 - - 11-02-15 - 199.75 20.183 10 62.806 62.806 62.806 82.989 0 - -
June - 2017
Work in progress.
1045
(OG)
140967-F/S, Design & Construction of (a) Chamtalai to Taroghai road District Swat (b) Garam Chashma to Kandujal Road, District Chitral (9 Km).
Swat
HW
28-10-15 - - 11-02-15 - 69.75 12.183 35.75 35.75 35.75 35.75 47.933 21.817 69% 69%
June - 2017
Length 4.5 Km -2.5 Km BT completed.
1046
(OG)
140984-F/S, Design and Construction of RCC Bridge at Ayun, Chitral.
Chitral
- - - 02-12-16 - 84.002 0 5 15 15 15 15 79.002 6% 18%
June - 2017
Test pile and approach road in progress.
1047
(OG)
150822-Realignment and Black Topping of Garam Chashma road from Shaghore to Mough including bridges District Chitral.
Chitral
- - - - Line Deptt 1293 0 5 0 0 0 0 0 - -
June - 2017
Execution by NHA.
1048
(OG)
150824-Construction / rehabilitation / widening / completion of incomplete Molkoh road, Boni bridge to Boni Bazar via Bazar to Government Guest House in Tehsil Mastuj District Chitral.
Chitral
- - - 02-11-15 - 83.43 7.5 5 13.75 13.75 13.75 21.25 70.93 15% 25%
June - 2017
Out of 3 units, all in progress.
1049
(OG)
150844-Construction / widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral.
Chitral
- - - 02-11-15 - 75.851 7.5 10 35.305 35.305 35.305 42.805 58.351 23% 56%
June - 2017
Out of 3 units, all in progress.
1050
(OG)
160636-Reconstruction of washedway Mozh Gole Suspension bridge and approach Mulkhow due to flood in July August 2015 District Chitral.
Chitral
- - - 12-05-16 - 19.8 0 5 20 20 20 20 14.8 25% 100%
June - 2017
Completed.
1051
(OG)
160638-Restroation of flood affected roads and bridge etc. due to torrential and thunderstorm rain during mid August September 2015, District Chitral.
Chitral
- - - 12-05-16 - 15.01 0 10 16 16 16 16 5.01 67% 100%
June - 2017
Completed.
1052
(OG)
160639-Restoration of Rehun Power House road damaged due to torrential rain / glacial lake outburst flood (GLOF) in July & August 2015, District Chitral.
Chitral
- - - 12-05-16 - 12.627 0 5 10.267 10.267 10.267 10.267 7.627 40% 81%
June - 2017
Completed.
1053
(OG)
50209-Construction, BT & Rehabilitation of 14 Km road in District Kohistan.
Kohistan
05-09-07 - - 25-03-15 - 406.458 129.981 10 53.424 53.424 53.424 183.405 266.477 34% 45%
June - 2017
Length 14 Km - 4 Km completed. Km-1, 2, 13, 14 - earth work in Km 3, and 12 in progress.
1) Bataira to Mirbat Road PK-62 (B/W 7 Km)
2) Palas Bridge to Mehreen Road PK-62 (B/W 7 KM)
1054
(OG)
130420-Construction of Pre Stressed RCC Bridge over Indus River from KKH to Seo village at Dassu Kohistan.
Kohistan
15-05-10 - - 29-05-14 - 322.534 115.755 40 38 38 38 153.755 166.779 48% 48%
June - 2017
35/48 piles, 6/9 girder, left abutment completed. Piling on right side in progress. Right approach rod earth work completed. 1/2 pier in progerss. High level meeting on 20/01/2017 decided to transfer the scheme to WAPDA for execution.
1055
(OG)
140916-F/S, Design & Improvement / Construction of Mahreen to Mehar Bat road, Barparo road & Kanisher roads, Kohistan.
Kohistan
- - - 17-11-15 - 100 0 10 17.5 17.5 17.5 17.5 90 10% 18%
June - 2017
length 6 km. Bar Paro (3 Km) - earth work upto 1.5 Km completed. Kunsher (3 Km) - earth work in progress.
1) Construction of shingle road Bar Paro (3 Km)
2) Construction of shingle road Kunsher (3 Km)
1056
(OG)
150874-Black topping / widening of road from KKH to Pattan Bazar road, Shingle road in rural areas and Construction of suspension Bridges, Bailey Bridges and Bridge on Sindh River in District Kohistan.
Kohistan
- - - 17-11-15 - 200 0 10 19.3 19.3 19.3 19.3 190 5% 10%
June - 2017
Length 4.6 km- 4 units - 1 land acquisition under process, 2 in progress, 1 work started.
1) Construction of shingle road Bar Paro 3 Km
2) Construction of shingle road Kunsher 3 Km
1057
(OG)
150875-Construction of road from Shaha to Sput Valley, Gabar Naala Road and Dong Naala Road District Kohistan.
Kohistan
- - - 10-09-15 - 80 3.75 5 4.75 4.75 4.75 8.5 71.25 11% 11%
June - 2017
length 7km- 3 units - 1 earth work 100% completed, 2 work order issued.
1) Construction of road from Soha to Sput 3 Km
2) Construction of Gabber Nullah road 2 Km
3) Construction of Dong Nullah road 2 Km
1058
(OG)
141025-F/S, Design and Construction of Road from Darman Tangay to Pashto Road, Battagram (5 Kms).
Battagram
25-05-15 - - 28-01-15 - 69.8 32.25 11 3.45 3.45 3.45 35.7 26.55 62% 51%
June - 2017
Length 5 Km - earth work, sub-base, base course, masonry work in progress.
1059
(OG)
150845-Construction / Improvement and Black topping of internal roads of Tehsil Battagram District Battagram.
Battagram
- - - 03-11-16 - 136 0 10 0 0 0 0 126 7% -
June - 2017
Stay vacated, work started.
1060
(OG)
150873-Construction / rehabilitation / widening road Chata Bata, Landay road, Chilar Sokadr, Sarkheli Banda, Chapar Gram Markhani and Batangi road District Battagram.
Battagram
06-03-16 - - 10-09-15 - 80 10.59 5 31.5 31.5 31.5 42.09 64.41 19% 53%
June - 2017
6 units - earth work, PCC road, masonry work in progress.
1061
(OG)
150946-F/S and Design for improvement / Rehabilitation of Oghi Battagram Road and Construction of RCC bridge at Biari Khwar, District Battagram.
Battagram
- - - 03-11-16 - 249.995 0 20 0 0 0 0 229.995 8% -
June - 2017
Work started.
1062
(OG)
140670-F/S, Design & Construction / Improvement of (a) Kulhari Gharbi Road (2.5 Km) (b) PCC Road from GHSS Baffa to Kharah (Kulhari Sharqi) & (c) Kulhari Sharqi Baffa (1 Km), District Mansehra.
Mansehra
30-05-15 30-06-17 - 13-02-15 - 50 33.6 8 7.6 7.6 7.6 41.2 8.4 83% 82%
June - 2017
Length 4.8 Km - 2.5 Km completed.
1063
(OG)
140675-F/S, Design and Construction of Sabir Shah Nakot Bridge, Manshera.
Mansehra
16-12-15 - - 06-03-15 - 122.187 20.945 15 18.75 18.75 18.75 39.695 86.242 29% 32%
June - 2017
125.43 mtr - 15/32 piles completed. 1 pile cap completed. 21/21 girders completed left side approach in progress. Launching of girders in progress.
1064
(OG)
140676-F/S, Design and Construction of Sum Bridge, Mansehra.
Mansehra
- - - 08-01-15 - 46.516 40.893 10 3 3 3 43.893 0 100% 94%
June - 2017
62.35 mtr - 12 working piles, 4 girders completed. Work in progress. Revised PC-I/DCE for Rs.74.355 m submitted to Chief Infra P&D on 14/10/2016.
1065
(OG)
140707-F/S, Design and Improvement of Road from Khaki to Fazalabad, District Mansehra.
Mansehra
25-05-15 - - 22-01-15 - 80 35.942 5 29.75 29.75 29.75 65.692 39.058 51% 82%
June - 2017
Length 6.7 Km - 4 Km BT. Earth work 90%, structure work 100%, sub-base 600 meter, base course 2.5 Km, RW completed. Locals of the ares blocked the Manshera Oghi road due to delay in the BT of the road.
1066
(OG)
140920-F/S, design and Construction of (a) Chor Kalan road & (b) Jabbori to Methal Kayian Road via Banda Gee Such, Mansehra.
Mansehra
01-09-15 - - 11-02-15 - 120 26.568 5 20.25 20.25 20.25 46.818 88.432 26% 39%
June - 2017
Length 7.6 Km - (a) Chor Kalan road 3.6 Km - earth work 5 Km completed. (b) Jabbori to Methal Kayan road - 2 Km WBM completed. 1700 mtr site cut, earth work cutting 1.7 Km completed.
1067
(OG)
150842-Construction and Blacktopping of roads from (a) Darband to Kandgran (b) Sehkibala to Sokal UC Darra Shanaya District Mansehra.
Mansehra
15-10-16 - - - - 35 0 5 7.75 7.75 7.75 7.75 30 14% 22%
June - 2017
2 units - earth work, structure work in progress.
1068
(OG)
150843-Construction of PCC Roads (a) Seri Goria (b) Batkarar (c) village Manshera Miangan (d) village Pondnial (e) Tambeela (f) Ismail Bandi and Shingle road village Ramkot UC Shergarh, Mansehra.
Mansehra
03-09-16 - - - - 17 0 5 10.212 10.212 10.212 10.212 12 29% 60%
June - 2017
Work in progress on all 4 units.
1069
(OG)
150869-Improvement / widening & Rehabilitation of Chakia Junglan Sundar Kalarian road and Shahkail Garhi Pairan road District Manshera.
Mansehra
- - - 10-09-15 - 100 7.5 5 4.75 4.75 4.75 12.25 87.5 13% 12%
June - 2017
Length 7 Km - earth work 60%, WBM 40%, structure work 55% completed.
1070
(OG)
150870-Improvement / carpeting of road from Dhodial to Shatay Road, Baffa Doraha to Khwajgan and Dhodial to Shatay Road PK-55 District Manshera.
Mansehra
01-11-16 - - 10-09-15 - 100 14.9 5 4.75 4.75 4.75 19.65 80.1 20% 20%
June - 2017
Length 7 Km - Dhodial to Shatay road - earth work 90%, masonary work 80%, X-drainage work 50%, road work 50% completed. Baffa Doraha to Khawjgan road - plant pre-mix 3.500 Km.
1071
(OG)
150871-Construction / rehabilitation of Oghi to Ahl, Saldhar Chulundrian, Shahkot Chulundrian and Jishkot, Chattar to Raitra, Khabal, Chappra Bala and Payan Jacha road Chajri, District Mansehra.
Mansehra
- - - 02-11-15 - 100 8.5 5 24.936 24.936 24.936 33.436 86.5 14% 33%
June - 2017
Length 9 Km - earth work structure work, road work in progress.
1072
(OG)
150949-Construction / Rehabilitation of roads Sufaida, Ghania Kangu, Arbora Batta Syedan, Deedwar Tarwai, Sheikh Abad, Guldheri, Titoli, Gorian and Belian road District Mansehra.
Mansehra
- - - 02-11-15 - 100 7.5 5 37.405 37.405 37.405 44.905 87.5 13% 45%
June - 2017
Length 9 Km - 4 Km completed, earth work structure work, road work in progress.
1073
(OG)
160190-Rehabilitation of Saiful Malook Road (8.55 Kms), District Mansehra.
Mansehra
- - - - - 152 0 5 0 0 0 0 147 3% -
June - 2017
2nd Revised PC-I/DCE for Rs.263.331 m submitted to SOR on 27/07/2016. DG M&E conducted inspection through DMO and submitted their report. Report submitted by DMO.
1074
(OG)
140630-F/S, Design and Construction of Barthan to Kasala Bara Road, District Abbottabad (8 Kms).
Abbottabad
06-06-15 - - 27-03-15 - 80 39 5 17.95 17.95 17.95 56.95 36 55% 71%
June - 2017
Length 8 Km - earth work 100%, structure work 80%, road work 20%, WBM completed.
PK-47
1075
(OG)
140782-F/S, Design, Construction, Improvement and Black Topping of Roads in Galyat Region, Abbottabad.
Abbottabad
13-10-15 - - 14-04-15 - 324.287 27 15 50.5 50.5 50.5 77.5 282.287 13% 24%
June - 2017
Length 26 Km - earth work, structure work in progress (5 units).
PK-48
1076
(OG)
140785-Improvement and Blacktopping of Butti to Lower Surjal and Dana - 10 Km, District Abbottabad.
Abbottabad
- - - 28-03-17 - 65 0 2 0 0 0 0 63 3% -
June - 2017
Tender opened on 06/06/2017.
1077
(OG)
140880-PPC / Imp / Rehab / Widening of (a) Maira Kalan Village road (b) Parr Nakkar to Kahala Kai Surmalagali Helipad road, (c) Jaster Village road, (d) Noormang Village road and (e) GGMS Tharyati road, Abbottabad.
Abbottabad
- - - 30-11-15 - 50 5 5 27.25 27.25 27.25 32.25 40 20% 65%
June - 2017
Length 7.5 Km - work in progress (5 units).
PK-48
1078
(OG)
140881-F/S, Design, BT and Extention of road from Sujal Kot to Thesi (8 Km), Abbottabad.
Abbottabad
14-10-15 - - - - 80 15 5 18.136 18.136 18.136 33.136 60 25% 41%
June - 2017
Length 8 Km - earth work 80%, masnory work 45% completed.
1079
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
01-05-16 - - 21-05-15 - 49.04 5.219 15 14.25 14.25 14.25 19.469 28.821 41% 40%
June - 2017
Length 32 mtr - pile cap in progress.
PK-46
1080
(OG)
140883-F/S, Design & BT of roads (a) Nakka Galli Khuthialla to Mubaraka (b) Chaitri to Sher Bai Mangal Bridge viz Bandi Matrach (c) Gramry including Siyal Sargal UC Pawa, District Abbottabad.
Abbottabad
05-03-16 - - 18-08-15 - 228.89 5.502 10 32.087 32.087 32.087 37.589 213.388 7% 16%
June - 2017
Length 19.5 Km. Out of 4 units, all 4 in progress.
PK-46
1081
(OG)
140884-F/S, design and Construction of (a) Arro Kas Summa to Lora via Banwari (b) Improvement / Widening & BT of Tajwal to Bagan Road (c) Garhi Chanali road via Seri, Abbottabad.
Abbottabad
- - - 14-04-15 - 180.78 19.44 5 28.174 28.174 28.174 47.614 156.34 14% 26%
June - 2017
Length 8 Km. Out of 3 units, all in progress.
PK-48
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46