Progressive Review for the month(s) of : December - 2016,

Showing Page Number : 38 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
1136
(OG)
140620-Re-construction of Bridge at Tor Warsak Daggar & widening / improvement & BT of 18 Km leftover portion of Swarai Pir Qilla Puran Road, District Buner.
Buner
21-10-15 - - 19-05-15 - 776.39 30 53.39 53.39 22.444 22.444 52.444 693 11% 7%
December - 2016
Length 25 mtr - diversion, load test pile, pile 16/16, pile cape 3/3, pier shaft 5/5, transum 3/3, abutment A&B, RCC beam 12/12, deck slab 2/2, diaphragm 24/24, RW 44/240 completed.
1137
(OG)
140629-Construcction of Swat Motorway (Land Acquisition).
Swat
10-06-14 - - 29-07-16 - 5850 4668.987 10 10 10 10 4678.987 1171.013 80% 80%
December - 2016
Land payment of all the mozas of all districts made to the concerend revenue officers. 56 Km land acquired and handed over to FWO.
1138
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
04-09-15 - - 07-01-15 - 318.69 145 50 50 25 25 170 123.69 61% 53%
December - 2016
Pack-1 - earth work 90% completed, structure work in progress. Pack-2 - earth work 85% completed, structure work in progress.
1139
(OG)
90397-F/S and Construction of road from Chukiathan to Sheringal and Patrak by FHA (36 Km) Dir Upper.
Dir Upper
31-01-11 - - 07-01-15 - 1798.521 1251.587 50 50 25 25 1276.587 496.934 72% 71%
December - 2016
Length 32 Km - earth work 70%, sub-base 50%, WBM 50% completed, asphalt wearing course 1 Km completed.
1) Package-1 Km-0 to 9 (9 Kms)
2) Package-2 Km-9 to 16 (7 Kms)
3) Package-3 Km-17 to 24 (7 Kms)
4) Package-4 Km-24 to 31+797 m (7.8 Kms)
5) Package-5 3 Nos bridges
1140
(OG)
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper.
Dir Upper
08-10-15 - - 19-02-15 - 988.52 200 50 50 25 25 225 738.52 25% 23%
December - 2016
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started.
1141
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
- - - - - 344.978 0 50 50 25 25 25 294.978 14% 7%
December - 2016
Work started.
1142
(OG)
140619-Widening / Dualization of Muree Chowk - Thandiani Chowk and Nawasher Link Road District Abbottabad.
Abbottabad
29-12-15 - - 07-01-15 - 983.904 357 50 50 25 25 382 576.904 41% 39%
December - 2016
Length 7.1 Km - Pack-1, 2 and 3 - work started. Shifting of utilities in progress.
1143
(OG)
140877-Construction of Haripur Bypass Road (23 Km).
Haripur
30-09-15 - - 28-01-15 - 3712.05 980 500 500 250 250 1230 2232.05 40% 33%
December - 2016
Length 23 Km - Pack-1 to 6 work started. Land acquisition payment completed.
1144
(OG)
20665-Construction / Supervision of new Road Works.
Provincial
20-06-06 - - 20-03-06 - 1104.58 870.354 40 50 25 25 895.354 194.226 82% 81%
December - 2016
Construction supervision of new road works.
1145
(OG)
20675-F/S and Design of Projects of Various Roads.
Provincial
15-10-10 - - 23-08-11 - 253.57 153.496 25 25 12.5 12.5 165.996 75.074 70% 65%
December - 2016
Conusltancy services for feasilbility study and design and framing PC-I.
1146
(OG)
130198-Establishment of Axle Load Control Regime on Provincial Highways at 5-Stations.
Provincial
21-11-15 - - 17-04-14 - 498.16 131.25 10 10 5 5 136.25 356.91 28% 27%
December - 2016
8 weight station as per revised PC-I. Work started at 5 Nos sites. Work order issued for 3 additional sites.
1147
(OG)
140624-Dualization of Sherkot Hangu Section of Provincial Highway S-7 (24 Km), District Kohat and Hangu.
Hangu
21-10-15 - - 25-03-15 - 2759.858 220 40 121.93 101.93 101.93 321.93 2499.858 9% 12%
December - 2016
Pack-1 (6 Km) - embankment, in progress Km-1, 3, 4, 5, clearing/grubbing and NGC 90% completed. Pack-2 (6 Km) - Km-9, 10, 11 hillside cutting, RW in progress. Pack-3 (6 Km) - embankment in progress Km-16, 17, clearing/grubbing and NGC 80% completed. Pack-4 (6 Km) - clearing/grubbing Km-19, 20, embankment in progress. Pack-5 (4 bridges) - contractor machinery and staff mobilized on site. Design awaited for bridge pile from design consultant.
1148
(OG)
140878-Improvement & Widening of Nizampur - Kohat road (64 Kms), District Nowshera & Kohat.
Nowshera
04-09-15 - - 28-01-15 - 2796.766 427.25 50 131.93 106.93 106.93 534.18 2319.516 17% 19%
December - 2016
Pack-1 (7.3 Km) - earth work in progress, culverts and bridges in progress. Pack-2 (11.05 Km) - earth work, bridge and culverts in progress. Pack-3 (10 Km) - hillside cutting 90% completed. Pack-4 (8.55 Km) - earth work and culverts in progress. Pack-5 (10 Km) - earth work in progress.. Pack-6 (12.553 Km) - earth work in progress. Km-52 to 55 - clearing, grubbing and NGC in progress. Bridge at Km-52+600, 54+360 and 64+100 - confirmatory bore in progress.
1149
(OG)
160193-Project Directorate for Swat Expressway.
Swat
- - - 05-08-16 - 67.401 0 16.67 16.67 8.334 8.334 8.334 50.731 25% 12%
December - 2016
Project directorate setup.
1150
(OG)
160248-Project Implementation Unit (PIU) ADB Assisted "Provincial Road Rehabilitation Project".
Provincial
- - - 12-05-16 - 29.178 0 15 15 7.5 7.5 7.5 14.178 51% 26%
December - 2016
PIU setup, staff deputed.
1151
(OG)
160251-Construction of Swat Motorway Phase-I VGF Component for 2016-17.
Swat
- - - 29-07-16 - 6000 0 3000 6000 6000 6000 6000 3000 50% 100%
December - 2016
Work in progress.
1152
(New)
160630-F/S, Design and Construction of Flyover from Kanju Bridge to Mingora, District Swat.
Swat
- - - - Line Deptt 30 0 20 20 0 0 0 10 67% -
December - 2016
PC-II for Rs.30 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Option finalized, detail design in progress.
1153
(New)
160631-F/S and Design of Expressway from Chakdara to Mingora City, District Swat.
Swat
- - - - - 50 0 20 20 0 0 0 30 40% -
December - 2016
PC-II for Rs.50 m approved in DDWP-I on 19/07/2016. Consultant selected. Feasibility/survey completed. Alignment finalized. Detail survey in progress.
1154
(New)
160442-Constrcution of New RCC Bridge at Khazana Bypass over River Panjkora District Lower Dir (SDG).
Dir Lower
- - - - Line Deptt 3.75 0 30 30 0 0 0 0 100% -
December - 2016
PC-II for Rs.3.750 m approved in DDWP-I on 19/07/2016. Consultant selected. PC-I/DCE under preparation.
1155
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
- - - - Line Deptt 2250 0 20 20 0 0 0 0 - -
December - 2016
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1155
(New)
160249-Provincial Roads Rehabilitation Project "Under PKHA Portfolio" (ADB Assisted).
Peshawar
- - - - Line Deptt 15351 0 200 200 0 0 0 0 - -
December - 2016
Under process with ADB. Meeting with ADB held on 07/12/2016 and finalized portfolio.
1156
(New)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
- 30-06-17 - - Line Deptt 0.01 0 0.01 0.01 0 0 0 0 - -
December - 2016
PPTA consultancy TOR will be submitted by ADB. PC-II will be prepared.
1156
(New)
160450-Feasibility Study for Project Preparatory and Technical Assistance for Provincial road Rehabilitation Project (ADB Assisted).
Peshawar
- 30-06-17 - - Line Deptt 1000 0 1000 1000 0 0 0 0 - -
December - 2016
PPTA consultancy TOR will be submitted by ADB. PC-II will be prepared.
1157
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
15-03-11 - - 22-04-04 - 14594.25 12652.99 2553.84 2553.84 512.95 484.52 13137.51 0 100% 90%
December - 2016
Total 522 Km - Provl Highways 100.81 Km, 100.85 Km, Distt road 425.55 Km, 405.89 Km, Bridges length 699.55 mtrs (10 Nos), 482.25 mtr (9 Nos) completed.
18 districts of Khyber Pakhtunkhwa
Upto till Release Jan-2016 Rs.1304.09 m
1157
(OG)
31038-Emergency Rural Roads Rehabilitation Project (JICA Assisted).
F. Aided
15-03-11 - - 22-04-04 - 100 10.81 5 5 2.5 0 10.81 84.19 16% 11%
December - 2016
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Bannu
15-04-13 - - 25-10-11 - 114.982 131.482 0 0 0 0 131.482 0 - 100%
December - 2016
Completed.
1) RCC Bridge Ghundakai (PK-72)
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Battagram
01-11-12 - - 25-10-11 - 48.69 52.91 2 2 2 1.9 54.81 0 100% 100%
December - 2016
Completed (bridge span 45 mtr).
RCC Bridge on Nandehar Khawar at Deshan Hotel PK-59
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Buner
- - - 11-03-16 - 100.651 28 4 4 4 4 32 68.651 32% 32%
December - 2016
Bridge structure completed, approaches in progress.
1) RCC bridge on Barundu Khawar
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Dir Lower
06-12-12 - - 25-10-11 - 103.908 122.015 0 0 0 0 122.015 0 - 100%
December - 2016
Completed.
a) RCC Bridge at Badin Khawar Summer Bagh
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
15-09-15 - - 25-10-11 - 116.283 97.265 25 25 25 25 122.265 0 100% 100%
December - 2016
Brigde completed. TST/protection work in finishing stage.
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mansehra
06-12-11 - - 25-10-11 - 59.85 68.02 0 0 0 0 68.02 0 - 100%
December - 2016
Completed.
1) Mansehra City Bridge PK-53
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Mardan
HW
29-09-11 - - 25-10-11 - 349.12 295.181 0 0 0 0 295.181 53.939 - 85%
December - 2016
4/5 bridges completed, 1 in progress (Mayar Bridge) lauching in porgress.
1) RCC bridge over Kalpani Nullah on main road between village Mayar & village Shamat Pur PK-25 (120 m span) 3 span
2) RCC bridge in Gidder Mehmood Abad PK-25 (30 m span)
3) Bridge linking Shamilat Zarifee and Safi Abad PK-27 (50-M span)
4) RCC bridge at Kaudoro PK-27 (27 m span) 2 span
5) RCC bridge at Hamza Kot RD-157000 Machi Branch PK-29 (24 m span) 4 span
6) Bridge on under construction Malandray Masoom Baba road PK-29 (24 m span) 2 span
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Nowshera
HW
01-08-12 - - 25-10-11 - 45 48.737 0 0 0 0 48.737 0 - 100%
December - 2016
Completed.
1) RCC bridge at Qasim Ali Baig (Taru)
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
Provincial
29-09-11 - - 22-01-15 - 918.425 898.308 80 80 40 0 898.308 0 100% 98%
December - 2016
Work in progress (Umbrella).
1158
(OG)
100429-Construction of 13 Nos RCC Bridges in Khyber Pakhtunkhwa.
PS
- - - 25-10-11 - 0 2.2 0 0 0 0 2.2 0 - -
December - 2016
1159
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
D.I.Khan
HW
28-02-12 - - 13-03-14 - 51.424 38.5 0 0 0 0 38.5 12.924 - 75%
December - 2016
Completed.
1) Diyal bridge (200 feet span)
1159
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Dir Upper
14-08-12 - - 13-03-14 - 24.8 18.78 0 0 0 0 18.78 6.02 - 76%
December - 2016
Completed.
1) Doona Shar Dir Upper
1159
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Provincial
02-02-12 - - 25-10-11 - 764 279.438 45 45 22.5 0 279.438 0 - -
December - 2016
Work in progress.
1159
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Swat
HW
05-01-12 - - 13-03-14 - 174.45 155.188 0.515 0.515 0.515 0.515 155.703 18.747 89% 89%
December - 2016
Out of 7 bridges, 6 completed, 1 launching under process (Rahim Abad Bridge). Revised PC-I/DCE for Rs.316.644 m submitted to SOR on 26/10/2016.
1) Mula Baba Bridge
2) Amankot (Rahim Abad) Bridge
3) Rahim Abad Bridge
4) Barikot (Babaji Baba Bridge
5) Faiz Abad Bridge
6) Kuz Kalay Khwaza Khela Bypass bridge
7) Chinkolai Faqira Bridge
8) Payment to Pak Army for launching of ACROW Steel Bridges at Distt Swat
1159
(OG)
110388-Constn: of Abutments and Lauching of Canadian Steel Bridges provided to Pak Army for Khyber Pakhtunkhwa (CIDA Assisted).
Tank
01-10-12 - - 13-03-14 - 54.17 17.902 13.25 13.25 13.25 12.948 30.85 23.018 58% 57%
December - 2016
18/18 piles completed, transum in porgress. Both abutments completed, work on approaches in progress. Revised PC-I/DCE for Rs.67.825 m submitted to P&D.
1) Shah Alam bridge (180 feet)
1160
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Lakki Marwat
- - - 02-05-14 - 6.05 3.635 0 0 0 0 3.635 2.415 - 60%
December - 2016
PC-II approved. Consultant selected.
1160
(OG)
130391-F/S, Detailed Design and Supervision for RCC Bridges in Khyber Pakhtunkhwa.
Provincial
- - - 02-04-14 - 100 4.135 10 10 5 0 4.135 0 - -
December - 2016
PC-II approved.
1161
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Provincial
- - - 23-12-13 - 100 2.473 10 10 5 0 2.473 0 - -
December - 2016
PC-II approved.
1161
(OG)
130510-Feasibility Study, Detailed Designing and Supervision of various roads of C&W Khyber Pakhtunkhwa.
Swat
HW
- - - 09-02-16 - 61.2 2.473 0 0 0 0 2.473 58.727 - 4%
December - 2016
Technical evaluation completed.
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Buner
28-02-14 - - 17-04-14 - 151.056 126 4 4 4 4 130 21.056 86% 86%
December - 2016
All 3 bridges completed.
1) Sura Bridge
2) Sunigrame Bridge
3) Bagra Baridara
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Chitral
- - - 17-04-14 - 0 0 0 0 0 0 0 0 - -
December - 2016
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Lower
25-10-14 - - 17-04-14 - 127.977 95.837 0 0 0 0 95.837 32.14 - 75%
December - 2016
Completed (3 bridges).
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Dir Upper
- - - 17-04-14 - 122.148 72.389 11 11 11 11 83.389 38.759 68% 68%
December - 2016
Out of 4 bridges, 3 lauched, 1 in progress.
1) Steel bridge Sheringla Colony PK-92
2) Steel bridge Jan Bahtti PK-91
3) Steel bridge Sordam PK-92
4) Steel bridge Almas Dag Tarpatar PK-92
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Provincial
01-01-14 - - 17-04-14 - 1760.82 125.645 80 84.5 44.5 0 125.645 0 - -
December - 2016
Work in progress.
1162
(OG)
130528-Bridges of Malakand Division SH: Construction of Abutments / Approaches & Launching of Steel Bridges to be provided by DFID under Flood Damages Restoration Project in District Swat, Chitral, Dir Lower & Dir Upper Phase -II.
Provincial
- - - 17-04-14 - 800 0 12 12 0 0 0 0 - -
December - 2016