Progressive Review for the month(s) of : January - 2018,

Showing Page Number : 5 of 46

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
January - 2018
Tender approval under process.
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
January - 2018
Work order issued.
Construction of Tehsil Building Shabqaddar, District Charsadda
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
January - 2018
Tender approval under process.
Haripur
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Provincial
30-11--1 30-11--1 - 30-11--1 - 300 0 40 50 20 0 0 0 - -
January - 2018
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 16.267 333.035 24.28 94% 85%
January - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
91
(OG)
120886-Design and Construction of Govt Officers Residences at Race Course Garden, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 237.708 132.304 25 13.75 3.25 0 132.304 80.404 66% 56%
January - 2018
10 residences - 6 original scope completed & H/O. Site for balance 4 Nos. residences not yet H/O (Plot No.20).
92
(OG)
140701-Designing and Consruction of duplex residential accommodation of different categories for Govt Officers/Officials in Hayatabad Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 215.561 105.085 44 54 29.8 28.837 133.922 66.476 69% 62%
January - 2018
15 Nos - 5 Nos (5 marla) - finishing in progress. 8 Nos (10 marla) - roof tile in progress. 2 Nos (1 Kanal) - finishing in progress.
1) 5 Marla Duplex House (5 Nos) 2) 20 Marla Duplex House (2 Nos) 3) 10 Marla Duplex House (8 Nos)
93
(OG)
140837-Construction of Hanger for MI-17 at Peshawar Airport.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 351.183 8 10 19.925 16.925 16.925 24.925 333.183 5% 7%
January - 2018
New site and scope NOC issued by Base Commander. Work in progress.
Peshawar
94
(OG)
140847-F/S and Master Plan for Race Course Gardens (RCG), Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 10 2.06 5.47 5.47 2.462 0.561 2.621 2.47 75% 26%
January - 2018
Presentation on master planning made to CA, changes suggested by CA, presentation prepared in light of CA observations, submitted to CA.
95
(OG)
150214-Construction of Cafeteria/Car Parking/Masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290.907 264.14 30 30 13.5 11.522 275.662 0 100% 95%
January - 2018
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
Peshawar
96
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 2.126 29.247 29.247 13.161 12.886 15.012 118.927 21% 10%
January - 2018
Work started (Package-I & II). Excavation in progress.
Peshawar
97
(OG)
90444-Creation of CSR/MRS Cell in C&W Department.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 67.44 32.48 20 20 10 2.58 35.06 14.96 78% 52%
January - 2018
RFP published for 2nd time for hiring of consultancy services for inclusion of NSI's and improving drafting standards. Market survey is started for collection of items rates for updation of MRS-2018.
98
(OG)
100427-Construction of Dormitories for support staff in Khyber Pakhtunkhwa House Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 82.715 53.21 33 33 14.85 14.85 68.06 0 100% 82%
January - 2018
Finishing in progress. Balance allocation demand for completion.
Islamabad
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 7.847 0 0 0 0 0 0 7.847 - -
January - 2018
Approved.
1) Construction of Mosque in Khyber Pakhtunkhwa House Abbottabad (CS Directive) 2) Parda Wall of Inspection Hut C&W Department Abbottabad 3) Rehabilitation and renovation of Govt Guest House Shimla Hill road Abbottabad 4) Renovation of C&W Rest House Kakool Abbottabad 5) Rehabilitation / Renovtion of Kala Pani Rest House Abbottabad 6) Construction of Lavatory Block and Record Room in C&W Division Office Abbottabad
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 233.594 74.921 40.819 18.639 18.639 13.348 88.269 117.854 50% 38%
January - 2018
Bore, OHT completed. Work in CM Sectt and house in progress.
1) Boring of Tube Well and construction of overhead tank 2 SAQ Residence and the Minister's residences Peshawar 2) Construction of Office for the SE Provincial Building (Construction) Peshawar 3) Rehabilitation / Renovation of Res # 511 Hayatabad Peshawar 4) Rehabilitation / Renovation and Construction of 02 Nos Additional Room in Res # 518 at Hayatabad Peshawar 5) Construction of office and 2 Nos Barracks, Watch Tower, Security Wall Dhobi Gath, Barber Ship etc for security staff in Chief Minister House at Peshawar construction of BW in Chief Minister House / Secretariat (Additional Work of Tiel in CM House) 6) Additional Alteration of P&D Department Peshawar 7) Construction of Tube Well / OHWT at Gunner Lane Peshawar 8) Construction of Swimming Pool at Chief Minister House Peshawar (Open) 9) Construction of OHWT  at Gulshan Rehman Colony Kohat road Peshawar 10) Covered Walk Way from main parking upto Civil Secretariat Peshawar 11) Renovation Works at Commissioner's Ooffice Peshawar
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Provincial
30-11--1 30-11--1 - 30-11--1 - 240 103.604 40.819 40.819 18.369 0 103.604 0 - -
January - 2018
Work in progress.
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Swat
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 10 - -
January - 2018
Land occupied by Pak Army. Work order issued.
Construction of C&W SDO office / residence at Kalam Swat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 53.378 54.013 0 0 0 0 54.013 0 - 100%
January - 2018
Completed & H/O (3 units).
1) Bachelor hostel (6 suits)
2) Cat-II residence Sujabdarabad (1 No)
3) Cat-II residence Abbottabad (1 No)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 62.375 59.299 3 3 3 0.457 59.756 0.076 100% 96%
January - 2018
Completed (6 units).
1) Category-III residence
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 31.391 21.5 0 0 0 0 21.5 9.891 - 68%
January - 2018
Main building - flooring, BW and joinery in progress.
Bachelor Hosetl (6 suits) in District Buner PK-79
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 37.447 37.776 0 0 0 0 37.776 0 - 100%
January - 2018
Completed.
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 77.794 27 15 15 15 15 42 35.794 54% 54%
January - 2018
Residences, bachelor hostel - in progress.
1) Residences 2) Bachelor Hostel
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.338 57.3 0 0 0 0 57.3 0.038 - 100%
January - 2018
Completed & H/O (2 units).
1) Bachelor Suits (10 Nos) 2) Category-II Residence
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Hangu
30-11--1 30-11--1 - 30-11--1 - 49.07 34 0 0 0 0 34 15.07 - 69%
January - 2018
Type-III, IV residences, 6 Nos suits - in progress.
1) Type-III (1 No) 2) Type-IV Quarter (1 No) 3) Hostel (4 Nos suits at THQ and 2 suits at C&W office)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 46.059 42.903 0 0 0 0 42.903 3.156 - 93%
January - 2018
Completed & H/O.
1) Bachelor Hostel (6 Nos suits)
2) Car Shed
3) Guard Room
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 47.193 46.83 0 0 0 0 46.83 0.363 - 99%
January - 2018
Completed & H/O.
Construction of Residences and Bachelor Hostel for Govt Servants in District Kohat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 42.22 29 9 9 9 7.334 36.334 4.22 90% 86%
January - 2018
Bachelor hostel (6 suits) - in progress. Residence - flooring in progress.
1) Bachelor Hostel (6 suits) / Residence (1 No) 2) Type-III residence
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 36.209 28.901 5 5 5 2.64 31.541 2.308 94% 87%
January - 2018
6 suits - GF/FF finishing in progress. Development work in progress. Demand bill of PESCO and Suigas awaited.
6 Nos suits
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 - 74.967 36 10 10 10 7 43 28.967 61% 57%
January - 2018
Bachelor hostel - joinery work in progress. Residences - joinery work in progress.
1) Bachelor Hostel for BPS-17-18 officer in Mardan Club Mardan 2) Officers residences (2 Nos) in Sheikh Maltoon Town Mardan PK-24
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.376 64.5 0 0 0 0 64.5 24.876 - 72%
January - 2018
Type-IV quarters (3 Nos), bachelor hostel GF/FF, Tyep-III residences completed, BW in progress.
Type-III Residences (2 Nos), Type-IV Residences (4 Nos), Bachelor Hostel (06 units)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt Servants in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 410.966 654.943 150 160 85 0 654.943 0 100% 100%
January - 2018
Work in progress.
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Shangla
30-11--1 30-11--1 - 30-11--1 - 39.962 35.69 0 0 0 0 35.69 4.272 - 89%
January - 2018
Main building - completed. Developmental work, water tank, internal electrification in progress.
6 Nos suits in District Shangla
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Swabi
30-11--1 30-11--1 - 30-11--1 - 33.189 30.934 0 0 0 0 30.934 2.255 - 93%
January - 2018
Completed.
Bachelor hostel in District Swabi
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Swat
30-11--1 30-11--1 - 30-11--1 - 31.279 25.5 3 3 3 1 26.5 2.779 91% 85%
January - 2018
1 suit - finishing in progress.
Bachelor Hostel 06 suits in District Swat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Tank
30-11--1 30-11--1 - 30-11--1 - 44.174 23.797 9 9 9 7.204 31.001 11.377 74% 70%
January - 2018
Type-III residence, 6 suits - in progress.
1) Suits (6 Nos) 2) Type-III residence (1 No)
101
(OG)
GHS Gul Bandai (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 24 0 0 0 0 22.238 22.238 24 - 93%
January - 2018
Completed & H/O.
101
(OG)
GGPS Chuprial (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.88 0 0 0 0 12.08 12.08 13.88 - 87%
January - 2018
T5 -truss beam completed. Gable wall and trusses completed. PGI sheets in progress. LB and dev works - slab and plastering completed. BW in progress.
101
(OG)
GMS Gul Bandai (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 14.79 0 0 0 0 3.35 3.35 14.79 - 23%
January - 2018
T2 - truss beam form work and steel cutting completed. T4 - GF slab form work and steel cutting completed.
101
(OG)
BHU Kotanai PD (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.4 0 0 0 0 15.78 15.78 18.4 - 86%
January - 2018
Completed. Snag list issued.
101
(OG)
BHU Mashkomai PD (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.866 0 0 0 0 3.56 3.56 12.866 - 28%
January - 2018
Main building completed. Truss fabrication in Cat- V, VI completed, PGI/CGI in progress. Brick work completed. Bore well completed. BW brick work completed, plastering in progress.
101
(OG)
GPS Inzer Maira (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 19.994 0 0 0 0 0.037 0.037 19.994 - 0%
January - 2018
Footing concrete in T8 completed.
101
(OG)
GPS Shahidan (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.004 0 0 0 0 2.97 2.97 15.004 - 20%
January - 2018
M4 - flooring and plastering completed in GF and FF. LB - structure completed. Bore well completed.
101
(OG)
GPS Mardand (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
January - 2018
DEO Charsadda intimated that reconstruction of Mardand school is being carried out through provincial ADP and has suggested reconstruction of GGPS Mian Sahib Ghari.
101
(OG)
GGPS Samunat (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.194 0 0 0 0 3.7 3.7 18.194 - 20%
January - 2018
M3 - structure, BBM and joinery work completed. Flooring and plastering in progress.
101
(OG)
GPS Mansooka (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
January - 2018
M7 - GF slab in progress. LB - footing completed. (previously local dispute).
101
(OG)
GGPS Jhoke Gumla (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
January - 2018
M7 - GF column completed. Slab in progress (previously mutation issue of existing land).
101
(OG)
GPS Makkar (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.739 0 0 0 0 2.07 2.07 18.739 - 11%
January - 2018
M3 - plaster work in progress. LB - slab done. Finishing in progress.
101
(OG)
GPS No.1 Yarak (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 21.009 0 0 0 0 0 0 21.009 - -
January - 2018
M7 - column completed in both modules. BBM in progress. BW in progress.
101
(OG)
GPS Jhoke Umary Wali (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
January - 2018
M7 - plinth beam done. Mutation issue at new site BW completed.
101
(OG)
GPS Rorra Now (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 1.77 1.77 13.1 - 14%
January - 2018
M7 - plaster work in progress. LB - slab done. Finishing in progress. Bore well completed.