Progressive Review for the month(s) of : February - 2018,

Showing Page Number : 5 of 47

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
85
(New)
170407-Construction of AC Office cum Residence Peshawar.
Peshawar
BD-2
30-11--1 30-11--1 - 30-11--1 Line Deptt 13 0 2 2 0 0 0 0 - -
February - 2018
Site/scope of work is awaited. Letter No.476/9-M, dated 07/07/2017.
No Image
Peshawar
86
(New)
170166-Construction of Mazar of Ajmal Khattak at Moza Akora Khattak District Nowshera (i/c land acquisition).
Nowshera
30-11--1 30-11--1 - 30-11--1 - 3.747 0 3.747 4.435 4.435 2.512 2.512 0 100% 67%
February - 2018
Flooring completed. BW complted
No Image
Akora Khattak Nowshera
87
(New)
170642-Establishment of District Secretariate for Lower Kohistan.
Kohistan
30-11--1 30-11--1 - 30-11--1 - 349.501 0 0 0 0 0 0 349.501 - -
February - 2018
Land payment of Rs.70 m involved. Tender approval in progress.
No Image
Lower Kohistan
88
(New)
170168-Reconstruction of Damaged DC's Main Office / Tehsil Building Mansehra.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 228.246 0 5 5 0 0 0 223.246 2% -
February - 2018
Land payment involved of Rs.60 m. Tender approval under process.
No Image
Mansehra
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Bannu
30-11--1 30-11--1 - 30-11--1 - 136.452 0 0 0 0 0 0 136.452 - -
February - 2018
Tender approval in progress.
No Image
Bannu
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 103.45 0 0 0 0 0 0 103.45 - -
February - 2018
Work order issued. Land acquisition under process.
No Image
Construction of Tehsil Building Shabqaddar, District Charsadda
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Haripur
30-11--1 30-11--1 - 30-11--1 - 90.446 0 0 0 0 0 0 90.446 - -
February - 2018
Tender approval under process.
No Image
Haripur
89
(New)
170169-Construction of Tehsil Building Haripur, Shabqadar, Charsadda and Bakka Khel, Bannu.
Provincial
30-11--1 30-11--1 - 30-11--1 - 300 0 40 50 20 0 0 0 - -
February - 2018
No Image
90
(OG)
90428-Construction of Khan Abdul Wali Khan Multiplex in Civil Secretariat Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 389.729 316.768 48.681 48.681 21.906 16.267 333.035 24.28 94% 85%
February - 2018
Block-1 half portion - in progress. Day Care Center - GF finishing in progress. Ramp - finishing in progress.
No Image
Civil Secretariat, Peshawar
91
(OG)
120886-Design and Construction of Govt Officers Residences at Race Course Garden, Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 237.708 132.304 25 13.75 3.25 0.107 132.411 80.404 66% 56%
February - 2018
10 residences - 6 original scope completed & H/O. Site for balance 4 Nos. residences not yet H/O (Plot No.20).
No Image
Race Course Garden, Peshawar
92
(OG)
140701-Designing and Consruction of duplex residential accommodation of different categories for Govt Officers/Officials in Hayatabad Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 215.561 105.085 44 54 29.8 29.8 134.885 66.476 69% 63%
February - 2018
15 Nos - 5 Nos (5 marla) - finishing in progress. 8 Nos (10 marla) - roof tile in progress. 2 Nos (1 Kanal) - finishing in progress.
No Image
Hayatabad Peshawar (5 Marla Duplex House 5 Nos / 20 Marla Duplex House 2 Nos / 10 Marla Duplex House 8 Nos)
93
(OG)
140837-Construction of Hanger for MI-17 at Peshawar Airport.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 351.183 8 10 19.925 16.925 16.925 24.925 333.183 5% 7%
February - 2018
New site and scope NOC issued by Base Commander. Work in progress.
No Image
Peshawar
94
(OG)
140847-F/S and Master Plan for Race Course Gardens (RCG), Peshawar.
Peshawar
PBC-2
30-11--1 30-11--1 - 30-11--1 - 10 2.06 5.47 5.47 2.462 0.561 2.621 2.47 75% 26%
February - 2018
Presentation on master planning made to CA, changes suggested by CA, presentation prepared in light of CA observations, submitted to CA.
No Image
Race Course Garden, Peshawar
95
(OG)
150214-Construction of Cafeteria/Car Parking/Masjid in Provincial Assembly Building at Khyber road Peshawar.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 290.907 264.14 30 30 13.5 11.522 275.662 0 100% 95%
February - 2018
Main building (4 storeys) - 3 level car parking, 1 level cafeteria - finishing in progress.
No Image
Peshawar
96
(OG)
150622-Construction of residences for P&D Staff at Hayatabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 150.3 2.126 29.247 29.247 13.161 13.161 15.287 118.927 21% 10%
February - 2018
Work started (Package-I & II). Basemnet roof laid of 8 no. Residences
No Image
8 No, Residences (1 Kanal )
97
(OG)
90444-Creation of CSR/MRS Cell in C&W Department.
Peshawar
30-11--1 30-11--1 - 30-11--1 - 67.44 32.48 20 20 10 3.012 35.492 14.96 78% 53%
February - 2018
Financial bid of consultant opened on 22/02/2018. Combined evaluation in progress.
No Image
98
(OG)
100427-Construction of Dormitories for support staff in Khyber Pakhtunkhwa House Islamabad.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 82.715 53.21 33 33 14.85 14.85 68.06 0 100% 82%
February - 2018
Finishing in progress. Balance allocation demand for completion.
No Image
1. 4 Storey Domoritiees
2. Dev works
3. Tube well Bore
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 7.847 0 0 0 0 0 0 7.847 - -
February - 2018
Approved.
No Image
1) Construction of Mosque in Khyber Pakhtunkhwa House Abbottabad (CS Directive) 2) Parda Wall of Inspection Hut C&W Department Abbottabad 3) Rehabilitation and renovation of Govt Guest House Shimla Hill road Abbottabad 4) Renovation of C&W Rest House Kakool Abbottabad 5) Rehabilitation / Renovtion of Kala Pani Rest House Abbottabad 6) Construction of Lavatory Block and Record Room in C&W Division Office Abbottabad
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Peshawar
PBC-1
30-11--1 30-11--1 - 30-11--1 - 251.441 74.921 40.819 18.639 18.369 18.369 93.29 135.701 46% 37%
February - 2018
Bore, OHT completed. Work in CM Sectt and house in progress.
No Image
1) Boring of Tube Well and construction of overhead tank 2 SAQ Residence and the Minister's residences Peshawar
2) Construction of Office for the SE Provincial Building (Construction) Peshawar
3) Rehabilitation / Renovation of Res # 511 Hayatabad Peshawar
4) Rehabilitation / Renovation and Construction of 02 Nos Additional Room in Res # 518 at Hayatabad Peshawar
5) Construction of office and 2 Nos Barracks, Watch Tower, Security Wall Dhobi Gath, Barber Ship etc for security staff in Chief Minister House at Peshawar construction of BW in Chief Minister House / Secretariat (Additional Work of Tiel in CM House)
6) Additional Alteration of P&D Department Peshawar
7) Construction of Tube Well / OHWT at Gunner Lane Peshawar
8) Construction of Swimming Pool at Chief Minister House Peshawar (Open)
9) Construction of OHWT  at Gulshan Rehman Colony Kohat road Peshawar
10) Covered Walk Way from main parking upto Civil Secretariat Peshawar
11) Renovation Works at Commissioner's Ooffice Peshawar
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Provincial
30-11--1 30-11--1 - 30-11--1 - 240 103.604 40.819 40.819 18.369 0 103.604 0 - -
February - 2018
Work in progress.
No Image
99
(OG)
120362-Emergent nature and Additional Construction of Office/Residential Buildings.
Swat
30-11--1 30-11--1 - 30-11--1 - 10 0 0 0 0 0 0 10 - -
February - 2018
Land occupied by Pak Army. Work order issued.
No Image
Construction of C&W SDO office / residence at Kalam Swat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 53.378 54.013 0 0 0 0 54.013 0 - 100%
February - 2018
Completed & H/O (3 units).
No Image
1) Bachelor hostel (6 suits), C&W Colony Sikandarabad
2) Cat-II residence, Sujabdarabad (1 No)
3) Cat-II residence, Sikandarabad (1 No)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Bannu
30-11--1 30-11--1 - 30-11--1 - 62.375 59.299 3 3 3 3 62.299 0.076 100% 100%
February - 2018
Completed (6 units).
No Image
1) Category-III residence, Bannu
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Buner
30-11--1 30-11--1 - 30-11--1 - 31.391 18.5 0 0 0 0 18.5 12.891 - 59%
February - 2018
Main building - flooring, BW and joinery in progress.
No Image
Construction of Bachelor Hostel (6 suits) in District Buner PK-79
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 37.447 37.776 0 0 0 0 37.776 0 - 100%
February - 2018
Completed.
No Image
1) Bachelor Hostel (6 units)
2) Cat-III Residence (1 No)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Chitral
30-11--1 30-11--1 - 30-11--1 - 77.794 27 15 15 15 15 42 35.794 54% 54%
February - 2018
Residences, bachelor hostel - in progress.
ADP's Images
1) Residences
2) Bachelor Hostel
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
D.I.Khan
30-11--1 30-11--1 - 30-11--1 - 57.338 57.3 0 0 0 0 57.3 0.038 - 100%
February - 2018
Completed & H/O (2 units).
No Image
1) Bachelor Suits (10 Nos)
2) Category-II Residence
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Hangu
30-11--1 30-11--1 - 30-11--1 - 49.07 34 3 3 3 0 34 12.07 75% 69%
February - 2018
Type-III, IV residences, 6 Nos suits - in progress.
No Image
1) Type-III (1 No)
2) Type-IV Quarter (1 No)
3) Hostel (4 Nos suits at THQ and 2 suits at C&W office)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Karak
30-11--1 30-11--1 - 30-11--1 - 46.059 42.904 0 0 0 0 42.904 3.155 - 93%
February - 2018
Completed & H/O.
No Image
1) Bachelor Hostel (6 Nos suits)
2) Car Shed
3) Guard Room
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Kohat
30-11--1 30-11--1 - 30-11--1 - 47.193 46.83 0 0 0 0 46.83 0.363 - 99%
February - 2018
Completed & H/O.
ADP's Images
Construction of Residences and Bachelor Hostel for Govt Servants in District Kohat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Lakki Marwat
30-11--1 30-11--1 - 30-11--1 - 42.22 29 9 9 9 8.548 37.548 4.22 90% 89%
February - 2018
Bachelor hostel (6 suits) - in progress. Residence - flooring in progress.
ADP's Images
1) Bachelor Hostel (6 suits) / Residence (1 No)
2) Type-III residence
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 - 36.209 28.901 5 5 5 2.64 31.541 2.308 94% 87%
February - 2018
6 suits - GF/FF finishing in progress. Development work in progress. Demand bill of PESCO and Suigas awaited.
No Image
Mansehra (6 Nos suits)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Mardan
30-11--1 30-11--1 - 30-11--1 - 74.967 36 10 10 10 7 43 28.967 61% 57%
February - 2018
Bachelor hostel - joinery work in progress. Residences - joinery work in progress.
No Image
1) Bachelor Hostel for BPS-17-18 officer in Mardan Club Mardan
2) Officers residences (2 Nos) in Sheikh Maltoon Town Mardan PK-24
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Nowshera
30-11--1 30-11--1 - 30-11--1 - 89.376 67.5 0 0 0 0 67.5 21.876 - 76%
February - 2018
Type-IV quarters (3 Nos), bachelor hostel GF/FF, Tyep-III residences completed, BW in progress.
No Image
Type-III Residences (2 Nos)
Type-IV Residences (4 Nos)
Bachelor Hostel (06 units)
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt Servants in Khyber Pakhtunkhwa.
Provincial
30-11--1 30-11--1 - 30-11--1 - 410.966 654.943 150 160 85 0 654.943 0 100% 100%
February - 2018
Work in progress.
No Image
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Shangla
30-11--1 30-11--1 - 30-11--1 - 39.962 35.69 0 0 0 0 35.69 4.272 - 89%
February - 2018
Main building - completed. Developmental work, water tank, internal electrification in progress.
No Image
6 Nos suits in District Shangla
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Swabi
30-11--1 30-11--1 - 30-11--1 - 33.189 30.934 0 0 0 0 30.934 2.255 - 93%
February - 2018
Completed.
No Image
Bachelor hostel in District Swabi
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Swat
30-11--1 30-11--1 - 30-11--1 - 31.279 25.5 3 3 3 1 26.5 2.779 91% 85%
February - 2018
1 suit - complted.
No Image
Bachelor Hostel 06 suits in District Swat
100
(OG)
120626-Construction of Residences & Bachelor Hostel in all District Headquarters for Govt servants in Khyber Pakhtunkhwa.
Tank
30-11--1 30-11--1 - 30-11--1 - 44.174 23.797 9 9 9 8.754 32.551 11.377 74% 74%
February - 2018
Type-III residence, 6 suits - in progress.
ADP's Images
1) Suits (6 Nos)
2) Type-III residence (1 No)
101
(OG)
GPS Inzer Maira (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 19.994 0 0 0 0 0.037 0.037 19.994 - 0%
February - 2018
Footing concrete in T8 completed.
No Image
101
(OG)
GHS Gul Bandai (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 24 0 0 0 0 22.238 22.238 24 - 93%
February - 2018
Completed & H/O.
No Image
101
(OG)
GGPS Chuprial (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.88 0 0 0 0 12.08 12.08 13.88 - 87%
February - 2018
T5 -truss beam completed. Gable wall and trusses completed. PGI sheets in progress. LB and dev works - slab and plastering completed. BW in progress.
No Image
101
(OG)
GMS Gul Bandai (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 14.79 0 0 0 0 3.35 3.35 14.79 - 23%
February - 2018
T2 - truss beam form work and steel cutting completed. T4 - GF slab form work and steel cutting completed.
No Image
101
(OG)
BHU Kotanai PD (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.4 0 0 0 0 15.78 15.78 18.4 - 86%
February - 2018
Completed. Snag list issued.
No Image
101
(OG)
BHU Mashkomai PD (Militancy Affected)
Buner
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.866 0 0 0 0 3.56 3.56 12.866 - 28%
February - 2018
Main building completed. Truss fabrication in Cat- V, VI completed, PGI/CGI in progress. Brick work completed. Bore well completed. BW brick work completed, plastering in progress.
No Image
101
(OG)
GPS Mansooka (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
February - 2018
M7 - GF slab in progress. LB - footing completed. (previously local dispute).
No Image
101
(OG)
GPS Shahidan (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 15.004 0 0 0 0 2.97 2.97 15.004 - 20%
February - 2018
M4 - flooring and plastering completed in GF and FF. LB - structure completed. Bore well completed.
No Image
101
(OG)
GPS Mardand (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 12.719 0 0 0 0 0 0 12.719 - -
February - 2018
DEO Charsadda intimated that reconstruction of Mardand school is being carried out through provincial ADP and has suggested reconstruction of GGPS Mian Sahib Ghari.
No Image
101
(OG)
GGPS Samunat (Flood Affected)
Charsadda
30-11--1 30-11--1 - 30-11--1 Line Deptt 18.194 0 0 0 0 3.7 3.7 18.194 - 20%
February - 2018
M3 - structure, BBM and joinery work completed. Flooring and plastering in progress.
No Image
101
(OG)
GGPS Jhoke Gumla (Flood Affected)
D.I.Khan
30-11--1 30-11--1 - 30-11--1 Line Deptt 13.1 0 0 0 0 0 0 13.1 - -
February - 2018
M7 - GF column completed. Slab in progress (previously mutation issue of existing land).
No Image