Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : November - 2016,

Showing Page Number : 32 of 43

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks
862
(OG)
150793-Rehabilitation / BTR road from Baran Dam to Jani Khel and Police Station Miryan to Hawaid road District Bannu.
Bannu
- - - - Line Deptt 200 0 10 10 0 0 0 0 - -
November - 2016
LOA issued on 07/01/2016. PC-I/DCE for Rs.470 m Ready for submission. Summary for enhancement in cost re submittd to CA for correction of ADP cost. PC-I/DCE submitted to SOR for enhanced cost. Pre-PDWP held on 05/12/2016 for 200 m.
863
(OG)
150878-Repair and Rehabilitation of Jandu Khel Road and Bannu DI.Khan road to Nar Dilasa Shah road, District Bannu.
Bannu
- - - 28-08-15 - 40 0 10 7.5 2.5 0 0 30 25% -
November - 2016
Length 10 Km. Revised estimate submited for conversion form TST to plant premix.
864
(OG)
151077-Construction / Rehabilitation of Road, UC Nar Jaffar, UC Kakki-I, UC Baharat, UC Kausar Fateh Khel, UC Mandan, District Bannu.
Bannu
- - - 02-11-15 - 150.1 0 10 7.5 0.073 0 0 140.1 7% -
November - 2016
Pre-qualification approved on 01/07/2016. Stay vacated on 13/06/2016. Revised PC-I/DCE under preparation for the change of specification from TST to Premix, will be submitted by 19/09/2016.
865
(OG)
151078-Construction / Rehabilitation of Road, UC Mira Khel, UC Kakki-II, UC Ismail Khel, UC Qalandar, UC Khujare, UC Khujamad Mandan, UC Kala Khel, District Bannu.
Bannu
- - - 02-11-15 - 150.1 0 10 7.5 0 0 0 140.1 7% -
November - 2016
Pre-qualification approved on 01/07/2016. Stay vacated on 13/06/2016. Revised PC-I/DCE under preparation for the change of specification from TST to Premix, will be submitted by 19/09/2016.
866
(OG)
140700-F/S, Design and Construction of Roads, Odin Shah Kalay to Jarasi Banda, Takhte Nasrati to Sarki Lawaghar Road via Poya, Latamber to Kamali Banda Road, Latamber to Indus Highway Road via Warana (11 Kms), District Karak.
Karak
19-06-15 - - 28-01-15 - 157.738 32.239 10 10 5 5 37.239 115.499 27% 24%
November - 2016
Length 11 Km - earth work, sub-base, WBM structure work in progress (3 units).
1) Odin Shah Killa to Jarasi 4 Kms (BTR)
2) Takhti Nasratti to Sarki Lawaghar via Poya 4 Kms (BTR)
3) Latambar to Kamali Banda road 3 Kms (BTR)
4) Latamber to Indus Highway road via Warana 4 Kms (BTR)
867
(OG)
141016-F/S, Design and Construction / Rehabilitation of Road from Karak City to Rehmat Abad, Karak (6 Km).
Karak
19-06-15 - - 28-01-15 - 84 41.279 10 10 5 5 46.279 32.721 61% 55%
November - 2016
Length 6 Km - 1.5 Km BT completed. Earth work, sub-base completed. WBM in progress.
868
(OG)
141017-Dualization of Road from Indus Highway Chowk to Karak City, Karak (4.225 Km).
Karak
20-12-15 - - 28-01-15 - 390.218 215.249 10 10 5 0.16 215.409 164.969 58% 55%
November - 2016
Length 4.225 Km - earth work, sub base in progress. DMC contractror terminated. New consultant selection under process. Contractor on field but payment cant be made due to absence of consultant.
869
(OG)
150858-Construction / Rehabilitation of Road from (a) Nari Panoos to Teri Chowk Banda Daud Shah (b) BT from Kando Khel to Faqir Abad and Construction of Bridge at Kandawo Algada UC Sabir Abad, District Karak (10 Km).
Karak
- - - 10-09-15 - 150 10 10 10 5 5 15 130 13% 10%
November - 2016
(a) 10% earth work completed. (b) 80% sub base completed.
870
(OG)
150859-Construction and Black Topping of Road from Sarki Lawagher to Alam Sheri, District Karak (12 Km).
Karak
- - - 10-09-15 - 150 7.5 10 10 5 5 12.5 132.5 12% 8%
November - 2016
(a) Clearing and grubbing in 3 Km in progrerss. (b) earth work 50%, sub base 30% completed. Revised PC-I/DCE for Rs.164.375 m submitted to SOR on 26/08/2016.
871
(OG)
140913-F/S, Design and Construction of RCC Bridge at Ziarat Sheikh Allah Dad Chorlaki Nizampur Road, Kohat.
Kohat
29-05-15 - - 28-01-15 - 76.737 34.125 10 10 5 5 39.125 32.612 58% 51%
November - 2016
Bridge 42 mtr structure completed, approaches in progress.
Nizampur road Kohat PK-37
872
(OG)
140990-F/S, Design and Improvement / Rehabilitation of Road from Gulshan Abad Chowk to OTS Chowk via Jungle Khel (5 Km), Kohat.
Kohat
02-06-15 - - 10-09-15 - 260.114 138 85 85 42.5 42.5 180.5 37.114 86% 69%
November - 2016
Length 5 Km - sub grade, sub-base, WBM, asphalt base course 5 Km completed. Work on bridge started.
Kohat PK-38
873
(OG)
150855-Construction & BT of Roads (a) Bahadar Kot Road, Bazi Khel Road, Bazi Khel road, Paracha Town Road (b) UC Kharmatu (c) UC Chorlakii (d) UC Khushal Garh, District Kohat.
Kohat
- - - 10-09-15 - 100 10.241 5 5 2.5 2.5 12.741 84.759 15% 13%
November - 2016
Bahadar Kot - base course 90% completed. Bazid Khel - sub base/base course in progress. Paracha Town - base course completed.
874
(OG)
150857-Construction and BT of Roads from Jarma Bridge to Mosam Khan Banda, Zara Mela to Botan Shareef Bannu road to Surgul Kamar Dhand Road, Shahpur Road UC Shahpur Lachi to Tablighai Markaz Road UC Lachi, Rehman Abad Road UC Rural-II Shahdardara, District Kohat.
Kohat
- - - 02-11-16 - 99.91 15 5 5 2.5 2.5 17.5 79.91 20% 18%
November - 2016
Shahpur road 2 Km BT - asphalt carpeting completed. Surgaul road 2 Km - sub base in progress.
Namenclature changed.
875
(OG)
150962-Construction of PCC Roads at Togh-I, Togh-II, Bazid Khel, Sheikhan, Bahadar Kot, Dhoda, Ghulam Banda, Shadi Khel, Daud Khel, Dan Banda-1, Gumbat, Bilitang, Pershai, Gul House Banda, Marchungi, Rahdi Dhoke, Kata Kani, District Kohat.
Kohat
- - - 02-11-15 - 100.1 2 5 5 2.5 2.5 4.5 93.1 7% 4%
November - 2016
Bahadur Kot PCC road - 55% completed. UC Dhoda Shadi Khel - 30% completed.
Namenclature changed.
876
(OG)
150968-Const & BT of Roads (a) UC Urban-1, Tanga to Kitab Ghar, Mian Khel Bazar, Bannu Bazar, Railway Station (b) UC Urban-2, Quresh Abad to Eidgah, Akbarabad, Noorabad, Habib Banda to Ambar Banda, Regi Shino Khel, Terah Bazar to Police Line, Kohat.
Kohat
- - - 28-08-15 - 40 9.796 10 10 5 5 14.796 20.204 49% 37%
November - 2016
Quresh Abad to Eidgah road - completed. Akbar Abad - WBM started. Terah Bazar to Police Line - work on drain started.
877
(OG)
150969-Construction & BT of Roads of UCs (a) Urban-3, OTS-Bawana, Gulu Bera-Camp-3, Gulu Bera-OTS, Chashma Jat Flyover (b) Urban-4, Spring Vally, KDA Gate-3, Ghamkol Darba, Malangabad Pir Khel Road, Kohat.
Kohat
18-01-16 - - 28-08-15 - 40 20 15 15 7.5 7.5 27.5 5 88% 69%
November - 2016
OTS to Bawana, Ghamkol road - completed. Gulu Bera to Camp-3 - 80% completed.
878
(OG)
150970-Construction & BT of Roads (a) UC-Urban-6, Mir Ahamd (b) UC Mohd Zai, Ublan Camp Nawy Kaly, Nawy Kaly to Lal Mela, Mohd Zai to Mian Garhi (c) UC Nasrat Khel, Dr Banda to Hangu Road, Kaghazai to Ambar Banda rd, Nasrat Khel Village rd, Kohat.
Kohat
- - - 28-08-15 - 40 14 5 5 5 2.5 16.5 21 48% 41%
November - 2016
Ublan Camp, Navey Kallay - TST completed. Nasrat Khel - 1 Km sub base in progress.
879
(OG)
150971-Construction & BT of Roads (a) UC Ali Zai, Ali Zai to Khade Zai Road, Bosi Tang Road, Kam Sam Road (b) UC Sherkot (c) UC Uster Zai, Kohat.
Kohat
- - - 28-08-15 - 30 17.524 5 5 2.5 2.5 20.024 7.476 75% 67%
November - 2016
Alizai to Khadizai road, Kamsam road, UC Usterzai Musa Khel - completed. UC Usterzai GPS to HBL, UC Sherkot - work not started. UC Sherkot, Kacha Paka to Husain Ziarat Colony - 80% completed.
880
(OG)
150972-Construction of PCC Roads of UCs (a) Urban-1 (b) Urban-2 (c) Urban-3 (d) Urban-4 (e) Urban-5 (f) UC Mohd Zai (g) Nasrat Khel (h) Ali Zai & (i) Sherkot, Kohat.
Kohat
- - - 28-08-15 - 50 0.235 10 10 5 5 5.235 39.765 20% 10%
November - 2016
23 units - 4 units completed (PCC) Muhammad Zai - 2100 rft completed. Chatar Kot Bala 600/1000 RFT completed. Shah Nawaz - completed.
881
(OG)
150973-Construction and Blacktopping of Banda Fateh Khan Road Darmalak road, Darmalak to Ghorzandi road, Darsha Khel Road Rehman Abad Pakka road, Krappa Shakardara road including bridge & PCC Roads in Ucs, Sodhal, Lachi Rural, Mandori District Kohat.
Kohat
- - - 24-08-16 - 249.927 0.204 160 160 40 3.316 3.52 89.723 64% 1%
November - 2016
Work started on road and bridge.
AA where???
882
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
11-06-10 - - 26-03-10 - 975.402 441.534 15 15 15 11.521 453.055 518.868 47% 46%
November - 2016
15/20 Km BT completed, structure work in progress.
1) 20 KM under jurisdiction of this Division
882
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
25-05-10 - - 26-03-10 - 440.41 425.182 0 0 0 0 425.182 15.228 - 97%
November - 2016
Length 22.35 Km - road work 90%, earth work 95% completed, structure work in progress (22.35 Km).
1) Package-II (22.35 Kms) from Lachi side
882
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Provincial
11-06-10 - - 13-12-11 - 655.054 866.716 30 30 7.5 0 866.716 0 100% 100%
November - 2016
Work in progress.
883
(OG)
140652-F/S, Design and Construction / Improvement of Hangu Samana Main Road (10 Kms), District Hangu.
Hangu
08-09-15 - - 28-01-15 - 100 25 10 10 5 1.325 26.325 65 35% 26%
November - 2016
Length 6 Km - earth work 70%, sub-base 40%, WBM 5 km completed.
884
(OG)
140907-F/S, Design, Improvement and Widening of Doaba Tora Wari Road, District Hangu (4.5 Km).
Hangu
16-06-15 - - 30-12-14 - 50.614 30.25 15.364 15.364 7.682 7.682 37.932 5 90% 75%
November - 2016
Length 4.5 Km - 2 Km BT completed, 2.5 Km WBM completed.
885
(OG)
150860-Construction / Rehabilitation of Road from (a) Bangash Chapper Road, Link Road at Shanawari to Wrasta, Darr Makhadu Quba road (b) Mula Tabi Road Samana, Nawa Killay Samana Road, District Hangu.
Hangu
16-06-15 - - 10-09-15 - 150 5 5 5 2.5 2.5 7.5 140 7% 5%
November - 2016
4 units - Bangash Chapper road, link road at Shenawari - sub base in progress.
886
(OG)
140678-F/S, Design and Construction of (1) BT of Road from Takht Abad to Liaqat Bagh via Babu Zai Jadeed 2 Km (2) Bridge over Shah Alam River (3) Culvert at Kata Behram Khan, District Peshawar.
Peshawar
HW
25-06-15 - - 13-02-15 - 49.933 17.923 15 15 7.5 7.5 25.423 17.01 66% 51%
November - 2016
Bridge 60 mtr - Deck slab laid and base course in progress.
887
(OG)
140942-Construction / Rehabilitation of Roads (a) Urmar Payan towards Kaskai Warsak Canal (b) Urmar Miana to Warsak Canal (c) Urmar Payan via Qasim Ali Baig to GT Road and (d) Urmar Payan to Mashan Khel, Peshawar (10 Km).
Peshawar
HW
24-05-15 - - 22-01-15 - 95.896 47 10 10 7.5 7.5 54.5 38.896 59% 57%
November - 2016
10/10 Km base course completed.
888
(OG)
140943-F/S, Design, Improvement & BT of Road from Mustajab Ghari to Shahibala (20 Km), Peshawar.
Peshawar
HW
10-06-15 - - 22-01-15 - 188.067 48.404 10 10 7.5 7.5 55.904 129.663 31% 30%
November - 2016
Length 20 Km - 2.7 Km asphalt and 3.3 Km base course, structure work completed.
PC-II Rs.10.000 m dated 07/08/2014
889
(OG)
140944-F/S, Design and Construction of Road from Nothia Stop to Kohat Road and from Nothia Phattak to Swati Phattak, Peshawar.
Peshawar
HW
10-06-15 - - 07-01-15 - 149.907 58.86 10 10 7.5 7.5 66.36 81.047 46% 44%
November - 2016
4/10 Km asphalt completed. Drain both side in progress.
PC-II Rs.7.500 m dated 07/08/2014
890
(OG)
140945-F/S, Design & Construction of birdge at Talib Koroona Sufaid Sung, Peshawar.
Peshawar
HW
25-06-15 30-06-17 - 08-01-15 - 31.376 14.376 8.689 8.689 4.349 4.349 18.725 8.311 74% 60%
November - 2016
Bridge 30 mtr span -girder and abutment completed, approaches in progress.
PC-II Rs.1.500 m dated 07/08/2014
891
(OG)
140949-F/S, Design and Construction / Improvement of 15 Km Roads in PK-01, District Peshawar.
Peshawar
HW
01-06-15 - - 07-01-15 - 149.814 49.5 10 10 10 10 59.5 90.314 40% 40%
November - 2016
8/13 Km asphalt completed.
PC-II Rs.7.500 m dated 07/08/2014
892
(OG)
140950-F/S, Design and Dualization of 16 Km Road from Jamil Chowk (Ring Road) towards Urmar Payan Peshawar.
Peshawar
HW
05-06-15 - - 19-02-15 - 1046 118 60 58 58 58 176 868 17% 17%
November - 2016
8 Km base course completed. 3/4 bridges in progress. 1 bridge land acquisition under process.
PC-II Rs.8.000 m dated 07/08/2014
893
(OG)
140951-Construction / Rehabilitation of 10 Km roads in PK-05, Peshawar.
Peshawar
HW
24-05-15 - - 07-01-15 - 109.326 57.5 15 15 7.5 7.5 65 36.826 66% 59%
November - 2016
Length 10 Km - 8 Km asphalt, 3.01 Km base course completed.
PC-II Rs.6.000 m dated 07/08/2014
894
(OG)
140997-F/S, Design and Construction / Rehabilitation of Roads (a) Dalazak to Jala Bela (b) Butai to Ranoo Ghari - Kandi Kalo Khel (c) Charsadda Road to Takhta Abad (d) Budni Road to Dalazak Road via Wadpaga Peshawar (20 Km).
Peshawar
HW
24-06-15 - - 22-01-15 - 195.896 84.148 10 10 10 10 94.148 101.748 48% 48%
November - 2016
Length 15 Km - 8 Km asphalt, 7 Km base course completed.
PC-II Rs.10.000 m dated 07/08/2014
895
(OG)
141006-F/S, Design, Construction & BT of Roads (a) Achini Ada to Janazgah Sangu (b) Hazrat Baba to Waliabad (c) Moh: Haya Khel to Ring Road (d) Insaf Road to Gharoor Abad (e) Bazi Khel road (f) Canal road to Merozai road Peshawar.
Peshawar
HW
19-05-15 - - 28-01-15 - 120 41 10 10 10 10 51 69 43% 43%
November - 2016
Length 11 Km - 6 Km base course, 5 Km sub-base and structure work completed.
PC-II Rs.6.000 m dated 07/08/2014
896
(OG)
150779-Construction / Improvement of Hasanghari Sheri Jahngi road, Khalsa 2 and surrounding areas road Peshawar.
Peshawar
HW
01-06-16 - - 10-09-15 - 150 0 10 10 7.5 7.5 7.5 140 7% 5%
November - 2016
Length 10 Km - 1.5 Km asphalt completed, sub base, base course in progress.
897
(OG)
150791-Construction / Widening / BT of internal roads of UC-31, UC-32, UC-33, UC-34, UC-35, UC-36 District Peshawar.
Peshawar
HW
01-05-16 - - 02-11-15 - 99.882 10 5 5 3.75 3.75 13.75 84.882 15% 14%
November - 2016
Length 7.5 Km - 0.75 Km asphalt completed, remaining base course, structure work in progress.
898
(OG)
150792-Construction / Rehabilitation of internal roads of UC-Tehkal, UC Shaheen Town, University Town, Malkandher District Peshawar.
Peshawar
HW
20-04-16 - - 02-11-15 - 99.736 10 5 5 3.75 3.75 13.75 84.736 15% 14%
November - 2016
Length 6.9 Km - 1.50 Km asphalt completed, base course in progress.
899
(OG)
150794-Construction / Rehabilitation of Deh Bahadar, Chalozan Colony, Achni Bala Pishtakhara Bala, Sufaid Dheri roads, Peshawar.
Peshawar
HW
05-04-16 - - 02-11-15 - 99.81 5 5 5 3.75 3.75 8.75 89.81 10% 9%
November - 2016
Length 9 Km - sub-base in progress.
900
(OG)
150796-Construction / Rehabilitation of (a) warsak road People Stop to Chagharmatti and in UC Mathra (b) Badizi UC Reggi and (c) Hindu Kasay UC Panam Dheri District Peshawar.
Peshawar
HW
02-05-16 - - 02-11-15 - 99.91 0 5 5 3.75 3.75 3.75 94.91 5% 4%
November - 2016
Length 9 Km - structure work, sub base in progress.
901
(OG)
150799-Construction and Blacktopping of roads from Yousafabad to Gohi Arat Mera road, Nasapa Bala road, Toda to Muslim Abad, Mandra Khel road, Landi Sarak, Choli to Khurasan road, District Peshawar.
Peshawar
HW
14-04-16 - - 28-08-15 - 30 5 10 10 7.5 7.5 12.5 15 50% 42%
November - 2016
Length 3 Km - sub base, base course in progress.
902
(OG)
150801-(a) Improvement / Rehabilitation of service roads from Northern bypass upto Akbar Pura and Jaba Daudzai village PK-09 to PK-13 (b) Const/Rehab. of Mian Gujar to Charsadda road via Damne Afgani, Kharakay and Shakarpura etc road, Peshawar.
Peshawar
HW
18-03-16 - - 03-11-16 - 200 5 10 10 10 10 15 185 8% 8%
November - 2016
Length 10 Km - 5 Km base course completed.
903
(OG)
150802-(a) Const / Rehab Adezay to Sherkera (Ithad Chowk) to Hameed Khan (Machine) road (b) Rehabilitation of internal roads of UC Badaber Maira Korizay and construction of Maryam Zai Deli Dher road alongwith RCC Bridge, Peshawar.
Peshawar
HW
14-04-16 - - 03-11-16 - 250 5 120 120 90 90 95 125 50% 38%
November - 2016
Length 12 Km - 10/13 Km asphalt completed, 3 Km, base course in progress.
904
(OG)
150804-Construction / Rehabilitation of Chua Gujar road, Musazai Main road, Adda road Musazai, Sheikhan road Musazai, Eidgah road Musazai Faqirabad Chowk Towards Aziz Market, Warsak Canal & Frontier road, Afridi Abad road Sheikhan, Sheikhan Main road, Peshawar.
Peshawar
HW
11-02-16 - - 28-08-15 - 50 5 5 5 3.75 3.75 8.75 40 20% 18%
November - 2016
Length 3.5 Km - base course (1.5 Km) in progress.
905
(OG)
150950-Construction of road from Garhi Taj Muhammad to Garhi Mir Tayyab road, Tubewell Koroona road, Mamo Khatki to Bela Baramad Khel, Haryana Bala road to Garhi Sher Afzal, Maqsood Abad road, District Peshawar.
Peshawar
HW
16-03-16 - - 28-08-15 - 30 5 5 5 3.75 3.75 8.75 20 33% 29%
November - 2016
Length 3 Km - 2 Km asphalt, base course in progress.
906
(OG)
150952-Construction / Rehabilitation of Haji Jalndhar Graveyard towards Warsak Canal, Police Chowki Afridi Abad towards Speen Qabar, Zangli Nehr Towards Sheen Rang, Sheikh Muhammadi Main road Towards Kohat road Toheedabad, Warsak Canal towards Kagawal, Peshawar.
Peshawar
HW
15-03-16 - - 18-11-15 - 50 5 5 5 2.5 2.5 7.5 40 20% 15%
November - 2016
Length 4 Km - 1.5 Km asphalt completed, base course in progress.
907
(OG)
140889-F/S, Construction & BT of Road i/c Bridge from Pir Qala to Major Qala and Shabqadar Bazar to Kangra, Charsadda (14 Km).
Charsadda
24-04-05 - - 21-01-16 - 350.459 124.631 50 50 25 25 149.631 175.828 50% 43%
November - 2016
(a) Length 6 Km - earth 3 Km, sub-base 3 Km, 50% structure work completed. (b) Length 4 Km - earth 4 Km, sub-base 4 Km, WBM 4 Km completed. Bridge - 145 mtr 12/12 piles completed.
908
(OG)
140890-F/S, Design, Reconstruction and Rehabilitation of Roads (a) from Alladad Khel to Village Kani Teshil Shabqadar (b) from Ziam Rest House to Salgaray via Gud Killi Chowk Shamsabad (c) from Village Cheena to Dildar Ghari, Charsadda (12 Km).
Charsadda
10-06-15 - - 07-01-15 - 120 36 5 8.75 8.75 8.75 44.75 79 34% 37%
November - 2016
Length 12 Km. Sub base WBM completed. 60% structure wotrk completed.
1) Allah Dad Khel to village Kani Tehil Shabqadar
2) Ziam Rest House to Salgaray via Gud Killi Chowk Shams Abad
3) Village Cheena to Dildar Garhi Charsadda
909
(OG)
150818-Construction / rehabilitation / widening of road (a) Umerzai Yakhkoi to Turangzai, (b) Damdam to Hayat Gul Kalli Dedar Abad UC Sarki Titara, District Charsadda.
Charsadda
29-02-16 - - 10-09-15 - 90 19.095 5 5 2.5 2.5 21.595 65.905 27% 24%
November - 2016
Length 6 Km - (a) PCC road 20% completed. (b) 2 Km earth work completed. 30% structure work completed.
Pages : 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43