Report Date:
September 27, 2025
Infrastructure Type:
Road
Total Damages:
27
Reported by:
Engr. Muhammad Riaz
(XEN KHYBER H/W)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
---|---|---|---|---|---|---|
1
|
wermando mela road
|
3
(KM) |
Fully restored |
1
(KM) |
Sep 22, 2025
06:09 AM |
|
2
|
Zangal Kalli Road
|
3
(KM) |
Fully restored |
0.3
(KM) |
Sep 22, 2025
04:18 AM |
|
3
|
Shen Kamar
|
5
(KM) |
Fully restored |
5
(KM) |
Sep 22, 2025
03:37 AM |
|
4
|
Kamer Khel Road
|
5
(KM) |
Fully restored |
1
(KM) |
Sep 22, 2025
03:32 AM |
|
5
|
Spin Qaber Road
|
5
(KM) |
Fully restored |
1
(KM) |
Sep 22, 2025
03:27 AM |
|
6
|
Besay Road
|
3
(KM) |
Fully restored |
0.5
(KM) |
Sep 22, 2025
03:22 AM |
|
7
|
SAM BABA ROAD
|
5
(KM) |
Fully restored |
1.5
(KM) |
Sep 22, 2025
03:11 AM |
|
8
|
Loe Shalman inzari check post
|
13
(KM) |
Fully restored |
2
(KM) |
Sep 20, 2025
12:15 PM |
|
9
|
Karkany road from loe shulman
|
8
(KM) |
Fully restored |
1
(KM) |
Sep 20, 2025
12:05 PM |
|
10
|
Hamza Baba to Haji Ras Kalay
|
3
(KM) |
Fully restored |
1
(KM) |
Sep 20, 2025
11:44 AM |
|
11
|
Malakanu Road Landikotal
|
1
(KM) |
Partially restored |
0.2
(KM) |
Sep 20, 2025
11:34 AM |
|
12
|
Pirukhel to Dargai bagh kally
|
14
(KM) |
Partially restored |
3
(KM) |
Sep 20, 2025
11:20 AM |
|
13
|
Mukhtar khel road
2
|
8
(KM) |
1 Fully restored |
2.5
(KM) |
Sep 20, 2025
08:33 AM |
|
2 Fully restored |
2
(KM) |
Sep 20, 2025
05:29 AM |
||||
14
|
Qadri Darbar to shudan khel
|
2
(KM) |
Fully restored |
0.5
(KM) |
Sep 20, 2025
08:25 AM |
|
15
|
Qadri Darbar to Piru khel road
|
3
(KM) |
Fully restored |
0.5
(KM) |
Sep 20, 2025
08:21 AM |
|
16
|
Landikotal to Gagra road
|
3
(KM) |
Fully restored |
0.5
(KM) |
Sep 20, 2025
08:15 AM |
|
17
|
Sheikhmal khel to Ghani khel road
2
|
7
(KM) |
1 Fully restored |
1.5
(KM) |
Sep 20, 2025
08:10 AM |
|
2 Fully restored |
1.5
(KM) |
Sep 20, 2025
06:10 AM |
||||
18
|
Shin Pokh road
|
28
(KM) |
Partially restored |
8
(KM) |
Sep 20, 2025
08:06 AM |
|
19
|
Molayano kalli road
|
3
(KM) |
Fully restored |
0.7
(KM) |
Sep 20, 2025
07:54 AM |
|
20
|
Ghani Khel to Sadgi Road
|
11
(KM) |
Fully restored |
2
(KM) |
Sep 20, 2025
07:50 AM |
|
21
|
Main Bazzar to Abdulhad Road
|
5
(KM) |
Fully restored |
1
(KM) |
Sep 20, 2025
06:02 AM |
|
22
|
Paseed khel Road
|
9
(KM) |
Fully restored |
2
(KM) |
Sep 20, 2025
05:57 AM |
|
23
|
Haideri Kandawo Road
|
5
(KM) |
Fully restored |
1
(KM) |
Sep 20, 2025
05:39 AM |
|
24
|
Fatmi Khal Ashkhel Road
|
9
(KM) |
Partially restored |
3
(KM) |
Sep 20, 2025
05:22 AM |
|
25
|
Masoom Baba Road
|
10
(KM) |
Partially restored |
5
(KM) |
Sep 20, 2025
05:09 AM |