Report Date:
April 19, 2026
Infrastructure Type:
Road
Total Damages:
2
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
Damaged Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Sabirabad - Shakardara Road PHW (S-13)
|
24.50
(KM) |
Not restored |
3.709
(KM) |
Apr 14, 2026
10:25 AM |
|
|
Remarks:
Need urgent Protection Works
Reported by:
Managing Director PKHA
|
||||||
|
2
|
Amberi kili to Abbasi Banda
|
35
(KM) |
Not restored |
1.585
(KM) |
Apr 14, 2026
10:08 AM |
|
|
Remarks:
Need urgent Protection Works
Reported by:
Managing Director PKHA
|
||||||