Report Date:
August 23, 2026
Infrastructure Type:
Road
Total Damages:
2
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
Damaged Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
| S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
|---|---|---|---|---|---|---|
|
1
|
Kohala Pir Sohawa Road S-5-C
2
|
20
(KM) |
1 Not restored |
0.008
(KM) |
Aug 05, 2026
01:45 PM |
|
|
Remarks:
The work order for repair work has been awarded, and the contractor is expected to mobilize shortly. Meanwhile, the road is currently fully operational and open to traffic
Reported by:
Managing Director PKHA
|
||||||
| 2 Not restored |
0.035
(KM) |
Aug 05, 2026
01:39 PM |
||||
|
Remarks:
The work order for repair work has been awarded, and the contractor is expected to mobilize shortly. Meanwhile, the road is currently fully operational and open to traffic.
Reported by:
Managing Director PKHA
|
||||||