Dir Upper Affected Detail - Snow (2026)

Reported by:
Najm Ud Din (XEN DIR UPPER) Engr. Sohail Idrees (Managing Director PKHA)
57
Affected Roads
58
Total Affected
519.8
Affected Length (KM)
33
Fully Restored
21
Partially Restored
4
Not Restored
Road Affected Overview
S# Road Name & Location Total Length Status Affected Length Affected Coordinates Date Reported
1
SULTANKHEL DARA SHERATKAL TAKHTABANJ ROAD
8
(KM)
Partially restored 3
(KM)
Start: 35.076583, 72.151447 View
End: 35.071357, 72.166622 View
Feb 02, 2026
01:21 PM
2
KARODARA JABAI MASTAI DERAI KHRPOSAY ROAD
4
(KM)
Fully restored 1
(KM)
Start: 35.074444, 72.157777 View
End: 35.174556, 72.656670 View
Feb 02, 2026
01:11 PM
3
NIHAGDARA ABLA &SIYA KARPAT ROAD
6
(KM)
Partially restored 3
(KM)
Start: 35.078342, 72.162372 View
End: 35.078735, 72.160485 View
Feb 02, 2026
01:01 PM
4
KARODARA SHAGO BANDA ROAD
5
(KM)
Fully restored 3
(KM)
Start: 34.954091, 72.148651 View
End: 34.954664, 72.147665 View
Feb 02, 2026
12:41 PM
5
khwar jaber road
7
(KM)
Fully restored 7
(KM)
Start: 35.143278, 72.049479 View
End: 35.107106, 72.074874 View
Jan 30, 2026
08:44 PM
Remarks: no remarks
Reported by: XEN DIR UPPER
6
sia jaber
2.6
(KM)
Fully restored 2.6
(KM)
Start: 35.140174, 72.035646 View
End: 35.128095, 72.039497 View
Jan 30, 2026
08:30 PM
Remarks: no remarks
Reported by: XEN DIR UPPER
7
singaram
7.2
(KM)
Fully restored 7.2
(KM)
Start: 35.140429, 72.033886 View
End: 35.184517, 72.013170 View
Jan 30, 2026
08:12 PM
Remarks: Machinery have been deployed, however due to continuous snow and the tough terrain, clearance work has been stopped. As the snow stops, operation will be started. The Operating hours & Approximate cost may increase with time as the snow still continues.
Reported by: XEN DIR UPPER
8
Usheri Dara Main Road upto Gorkohi 2
32
(KM)
1 Fully restored 29.5
(KM)
Start: 35.110906, 71.993947 View
End: 35.206553, 72.209486 View
Jan 30, 2026
01:59 PM
Remarks: clear two spell of snow
Reported by: XEN DIR UPPER
2 Fully restored 32
(KM)
Start: 35.639050, 71.593788 View
End: 35.123660, 72.124671 View
Jan 26, 2026
10:43 AM
Remarks: Main Road opened for traffic
Reported by: XEN DIR UPPER
9
Ilgal Road
4
(KM)
Fully restored 4
(KM)
Start: 35.097179, 71.691678 View
End: 35.097179, 71.699874 View
Jan 30, 2026
01:35 PM
Remarks: Due to Internet Issue, coordinated pictures are not available
Reported by: XEN DIR UPPER
10
Gulbhar Shingara
8
(KM)
Fully restored 7
(KM)
Start: 35.130737, 71.730241 View
End: 35.196955, 71.705805 View
Jan 30, 2026
01:14 PM
Remarks: 90% road is clear
Reported by: XEN DIR UPPER
11
Noorkhel Road Bin Dara
5
(KM)
Fully restored 5
(KM)
Start: 35.134419, 71.673926 View
End: 35.171603, 71.675272 View
Jan 30, 2026
12:50 PM
Remarks: 90% road is clear
Reported by: XEN DIR UPPER
12
Rokhan, Belo & Mirshpati Road
7
(KM)
Partially restored 5
(KM)
Start: 35.224561, 71.888743 View
End: 35.255101, 71.908550 View
Jan 30, 2026
12:35 PM
Remarks: Machinery have been deployed. The Operating hours & Approximate cost may increase with time as the snow still continues.
Reported by: XEN DIR UPPER
13
Chindakot Road
2.5
(KM)
Partially restored 2.5
(KM)
Start: 35.094205, 71.771334 View
End: 35.077427, 71.778406 View
Jan 30, 2026
12:23 PM
Remarks: Machinery have been deployed. The Operating hours & Approximate cost may increase with time as the snow still continues. Cleared road will be shared later
Reported by: XEN DIR UPPER
14
Batlai Sultan khel dara Road
8
(KM)
Fully restored 3
(KM)
Start: 35.017037, 71.955727 View
End: 35.015414, 71.946653 View
Jan 29, 2026
01:32 AM
15
Gurli road
7
(KM)
Fully restored 3
(KM)
Start: 35.008958, 72.108475 View
End: 35.007896, 72.117777 View
Jan 28, 2026
02:49 PM
16
MANZAI BEDAMAI ROAD
7
(KM)
Fully restored 2
(KM)
Start: 35.078945, 72.133420 View
End: 35.078872, 72.133408 View
Jan 28, 2026
11:22 AM
17
Nihagdara Bandai dolar Road Wari
6
(KM)
Fully restored 3
(KM)
Start: 35.076583, 72.151447 View
End: 35.071357, 72.166622 View
Jan 28, 2026
11:07 AM
18
Jarjorry Road
7
(KM)
Not restored 2
(KM)
Start: 35.273743, 71.849336 View
End: 35.280516, 71.831528 View
Jan 27, 2026
12:32 PM
Remarks: Machinery have been deployed, however due to continuous snow and the tough terrain, clearance work has been stopped. As the snow stops, operation will be started. The Operating hours & Approximate cost may increase with time as the snow still continues.
Reported by: XEN DIR UPPER
19
Patrak kumrat Road (Non-P)
44
(KM)
Fully restored 44
(KM)
Start: 35.348146, 72.055220 View
End: 35.571892, 72.186202 View
Jan 27, 2026
11:16 AM
20
Chukyatan Patrak S-16
34
(KM)
Fully restored 30
(KM)
Start: 35.145665, 71.896518 View
End: 35.348146, 72.055220 View
Jan 27, 2026
11:11 AM
21
Pataw Nagril Road
12
(KM)
Partially restored 12
(KM)
Start: 35.052522, 72.000503 View
End: 35.053547, 71.928503 View
Jan 26, 2026
01:12 PM
22
kadikhel dara Road
8
(KM)
Fully restored 5
(KM)
Start: 35.077833, 71.991322 View
End: 35.085969, 72.044289 View
Jan 26, 2026
01:00 PM
23
badalai main road
10
(KM)
Fully restored 3
(KM)
Start: 35.034878, 72.139062 View
End: 35.035015, 72.139545 View
Jan 26, 2026
12:57 PM
24
Osori dara road
10
(KM)
Fully restored 4
(KM)
Start: 35.016388, 72.226388 View
End: 35.066814, 72.077936 View
Jan 26, 2026
12:52 PM
25
bandai serai road
8
(KM)
Fully restored 2
(KM)
Start: 34.945481, 72.092258 View
End: 34.969717, 72.077394 View
Jan 26, 2026
12:44 PM
26
Karo dara (left side) Road
26
(KM)
Partially restored 3
(KM)
Start: 35.076583, 72.139062 View
End: 35.035015, 72.139545 View
Jan 26, 2026
12:33 PM
27
Samang Sheringle Road
6
(KM)
Fully restored 5
(KM)
Start: 35.155057, 72.011740 View
End: 35.162424, 71.593647 View
Jan 26, 2026
11:54 AM
Remarks: opened for traffic
Reported by: XEN DIR UPPER
28
Aligasar Usheri
5
(KM)
Fully restored 5
(KM)
Start: 35.124240, 71.583271 View
End: 35.102564, 72.144810 View
Jan 26, 2026
11:48 AM
Remarks: opened for traffic
Reported by: XEN DIR UPPER
29
Doon Achar Road
8
(KM)
Partially restored 8
(KM)
Start: 35.124240, 71.583271 View
End: 35.102564, 72.144810 View
Jan 26, 2026
11:41 AM
Remarks: work is in progress
Reported by: XEN DIR UPPER
30
Sadiq Banda Panakot
3
(KM)
Not restored 3
(KM)
Start: 35.226533, 71.872767 View
End: 35.239851, 71.879484 View
Jan 26, 2026
11:21 AM
Remarks: Machinery will be mobilized. The Operating hours & Approximate cost may increase with time. As the road is closed, therefore no picture is available, and will be uploaded later.
Reported by: XEN DIR UPPER
31
Barkand Road
12
(KM)
Fully restored 7
(KM)
Start: 35.951840, 72.737700 View
End: 35.757605, 72.912970 View
Jan 26, 2026
11:15 AM
Remarks: opened for traffic
Reported by: XEN DIR UPPER
32
Kilot Road Doag dara
6
(KM)
Partially restored 6
(KM)
Start: 35.175377, 72.051500 View
End: 35.174747, 71.574734 View
Jan 26, 2026
11:02 AM
Remarks: work is in progress will be cleared soon
Reported by: XEN DIR UPPER
33
Goryal Sheringle Road
8
(KM)
Fully restored 8
(KM)
Start: 35.162745, 72.010990 View
End: 35.161168, 71.571402 View
Jan 26, 2026
10:54 AM
Remarks: Road opened for traffic
Reported by: XEN DIR UPPER
34
Bin dara Jaba bala Road
10
(KM)
Partially restored 10
(KM)
Start: 35.064740, 71.704196 View
End: 35.145050, 71.672175 View
Jan 26, 2026
10:41 AM
Remarks: Work is still under progress. The Operating hours & Approximate cost may increase with time. The pictures are without coordinates due to internet issue.
Reported by: XEN DIR UPPER
35
Doag Dara Main Road and its links
45
(KM)
Partially restored 35
(KM)
Start: 35.171605, 72.038500 View
End: 35.245880, 71.576400 View
Jan 26, 2026
10:35 AM
Remarks: Main road will be cleared today and links will be cleared in two days
Reported by: XEN DIR UPPER
36
Hayagai Road
26
(KM)
Not restored 12
(KM)
Start: 35.226761, 71.898648 View
End: 35.255053, 71.931615 View
Jan 26, 2026
10:34 AM
Remarks: Work is still under progress. The Operating hours & Approximate cost may increase with time. The picture is of road leading to Hayagy. Actual Pictures will be shared later
Reported by: XEN DIR UPPER
37
Badgoi Road
42
(KM)
Not restored 42
(KM)
Start: 35.273308, 72.141889 View
End: 35.293188, 72.214095 View
Jan 26, 2026
10:27 AM
Remarks: Badgoi road will be cleared in may june 2026 because badgoi top is closed upo june 206
Reported by: XEN DIR UPPER
38
Jandrai Lamoti Road
12
(KM)
Partially restored 12
(KM)
Start: 35.272284, 72.135804 View
End: 35.263639, 72.194044 View
Jan 26, 2026
10:18 AM
Remarks: work is in progress will be cleared soon
Reported by: XEN DIR UPPER
39
Gwaldi Dara Main Road
25
(KM)
Partially restored 25
(KM)
Start: 35.205383, 72.319370 View
End: 35.263756, 72.240990 View
Jan 26, 2026
10:12 AM
Remarks: Work is in progress will be cleared soon
Reported by: XEN DIR UPPER
40
Ganshal Road
17
(KM)
Partially restored 17
(KM)
Start: 35.141475, 71.594731 View
End: 35.143071, 72.512600 View
Jan 26, 2026
10:05 AM
Remarks: work is in progress will be cleared soon
Reported by: XEN DIR UPPER
41
Sonai Dara Road
5
(KM)
Partially restored 5
(KM)
Start: 35.062570, 71.702393 View
End: 35.093507, 71.623986 View
Jan 25, 2026
07:09 PM
Remarks: Work is still under progress. Only 1.8km portion remains to clear. The Operating hours & Approximate cost may increase with time.
Reported by: XEN DIR UPPER
42
Hattan Dara Road
12
(KM)
Fully restored 8
(KM)
Start: 35.125731, 71.816303 View
End: 35.177680, 71.792810 View
Jan 25, 2026
07:03 PM
Remarks: Work is still under progress. Only 1km portion remains to clear. The Operating hours & Approximate cost may increase with time.
Reported by: XEN DIR UPPER
43
Shingara Road
15
(KM)
Partially restored 5
(KM)
Start: 35.171980, 71.714478 View
End: 35.171977, 71.714466 View
Jan 25, 2026
06:43 PM
Remarks: Work is still under progress. The Operating hours & Approximate cost may increase with time.
Reported by: XEN DIR UPPER
44
Daskor Badali Maskari Road Wari
12
(KM)
Partially restored 5
(KM)
Start: 35.018228, 72.105466 View
End: 35.017893, 72.105420 View
Jan 25, 2026
02:45 PM
45
kakad Tangi Road Wari
7
(KM)
Fully restored 3
(KM)
Start: 34.995614, 72.033981 View
End: 34.999930, 72.091489 View
Jan 25, 2026
02:39 PM
46
sultankhel dara Mulvi Road
11.8
(KM)
Fully restored 1.5
(KM)
Start: 35.017037, 71.955727 View
End: 35.015414, 71.946653 View
Jan 25, 2026
01:33 PM
47
sundal to arimanzai Road
5.96
(KM)
Partially restored 2
(KM)
Start: 35.049444, 72.112761 View
End: 35.060994, 72.137950 View
Jan 25, 2026
01:10 PM
48
wari jilar road
15
(KM)
Fully restored 6
(KM)
Start: 35.046528, 72.001389 View
End: 35.015414, 71.946667 View
Jan 25, 2026
12:04 PM
49
Gal pashta Road wari
5
(KM)
Fully restored 3
(KM)
Start: 34.945481, 72.092258 View
End: 34.969717, 72.077394 View
Jan 25, 2026
11:27 AM
50
Matar Shawkand Road
8
(KM)
Fully restored 4
(KM)
Start: 35.034878, 72.139062 View
End: 35.035015, 72.139545 View
Jan 25, 2026
11:05 AM
51
Nihag Dara Phase I Road
27
(KM)
Fully restored 8
(KM)
Start: 35.076583, 72.151447 View
End: 35.071357, 72.166622 View
Jan 25, 2026
10:41 AM
52
Dobando Road
10
(KM)
Partially restored 5
(KM)
Start: 35.235160, 71.837280 View
End: 35.253997, 71.795882 View
Jan 25, 2026
08:42 AM
Remarks: One tractor has been mobilized and road is partially clear for one side flow. Work is still under progress. The Operating hours & Approximate cost may increase.
Reported by: XEN DIR UPPER
53
Shahikot Road
3
(KM)
Partially restored 3
(KM)
Start: 35.086373, 71.654943 View
End: 35.081884, 71.640385 View
Jan 24, 2026
09:18 PM
Remarks: One tractor has been mobilized and road is partially clear. for one side floor. Work is still under progress.
Reported by: XEN DIR UPPER
54
Bijligar Chinar Muhalal Road
1.5
(KM)
Fully restored 1.5
(KM)
Start: 35.205213, 71.874382 View
End: 35.204463, 71.869685 View
Jan 24, 2026
09:06 PM
Remarks: One tractor has been mobilized and road is almost clear. Work is still under progress. Pictures during working hours is attached.
Reported by: XEN DIR UPPER
55
Kair Dara Road
18
(KM)
Partially restored 15
(KM)
Start: 35.075849, 71.873062 View
End: 35.095018, 71.927783 View
Jan 24, 2026
07:35 PM
Remarks: Snow height increases from start to the end of road. Two tractors have been mobilized and the road is almost clear. Kair Dara consists of Nalu Road, Shamorgar Road, Muto Road, Kair Khass Road
Reported by: XEN DIR UPPER
56
Nasrat Dara Road
10
(KM)
Fully restored 10
(KM)
Start: 35.069772, 71.666572 View
End: 35.093445, 71.637237 View
Jan 24, 2026
07:24 PM
Remarks: Restored completely on 30-01-2026
Reported by: XEN DIR UPPER
57
Seyasan Dara Road
12
(KM)
Partially restored 12
(KM)
Start: 35.208801, 72.338260 View
End: 35.248860, 72.635970 View
Jan 24, 2026
01:09 PM
Remarks: Road is block due to heavy snowfall work is in progress
Reported by: XEN DIR UPPER