Bajaur Damages Detail - Monsoon (2026)

Reported by:
Engr. Imran (XEN H/W BAJAUR)
2
Damaged Roads
3
Total Damages
3.75
Damaged Length (KM)
1
Fully Restored
2
Partially Restored
0
Not Restored
Road Damages Overview
S# Road Name & Location Total Length Status Damaged Length Damage Coordinates Date Reported
1
Chargo to Dara
8
(KM)
Partially restored 0.05
(KM)
Start: 34.812380, 71.516249 View
End: 34.812380, 71.516249 View
Aug 22, 2026
09:40 PM
Remarks: Partially Restore
Reported by: XEN H/W BAJAUR
2
Khar-Barang Road 2
45
(KM)
1 Partially restored 3.5
(KM)
Start: 34.674236, 71.593320 View
End: 34.677458, 71.592065 View
Aug 20, 2026
11:52 AM
Remarks: Partially Restore
Reported by: XEN H/W BAJAUR
2 Fully restored 0.2
(KM)
Start: 34.679268, 71.520785 View
End: 34.673894, 71.592538 View
Aug 01, 2026
09:58 PM
Remarks: Fully Restore
Reported by: XEN H/W BAJAUR