Stories
Loading...

MAIRA REHMAL ROAD

MAIRA REHMAL ROAD

Fully restored
26 January, 2026 Abbottabad XEN H/W ABBOTTABAD

This activity provides a detailed overview of the operational status of the Road MAIRA REHMAL ROAD, recorded on 26 January, 2026. The affected site is situated within the Abbottabad district, operating under the administrative jurisdiction of XEN H/W ABBOTTABAD. The infrastructure has been primarily affected by Snow Clearance, encompassing a total span of 2 Kilometers.

Environmental conditions at the site indicated an average recorded snow depth of 3.00 inches. Restoration and clearance efforts were facilitated by the deployment of Paydozer , which remained in active operation for a duration of 6 hours . In a formal assessment of the situation, the reporting officer noted with remarks: Road is opened for traffic.

The affected area has been mapped using geographic coordinates. The section starts at 73.353126, 33.957822 and ends at 73.364453, 33.949888. For location reference and navigation, view the route on Google Maps.

All required restoration activities have been successfully completed, and the road is now fully operational, allowing safe and uninterrupted movement of traffic.

The following photographs provide a visual record of the site conditions before and after the activity, illustrating the extent of the affected area and the improvements achieved through the executed operations.

Before Images (2)
After Images (2)
CWD