Sam to Karama Road
Fully restoredThis activity provides a detailed overview of the operational status of the Road Sam to Karama Road, recorded on 22 January, 2026. The affected site is situated within the South Waziristan Upper district, operating under the administrative jurisdiction of XEN South Waziristan (U). The infrastructure has been primarily affected by Snow Clearance, encompassing a total span of 15 Kilometers.
Environmental conditions at the site indicated an average recorded snow depth of 1.00 inches. Restoration and clearance efforts were facilitated by the deployment of Tractor , which remained in active operation for a duration of 15 hours . In a formal assessment of the situation, the reporting officer noted with remarks: road is cleared.
The affected area has been mapped using geographic coordinates. The section starts at 69.802112, 32.524560 and ends at 69.822299, 32.510676. For location reference and navigation, view the route on Google Maps.
All required restoration activities have been successfully completed, and the road is now fully operational, allowing safe and uninterrupted movement of traffic.
The following photographs provide a visual record of the site conditions before and after the activity, illustrating the extent of the affected area and the improvements achieved through the executed operations.