Sharakot Road
Partially restoredThis activity provides a detailed overview of the operational status of the Road Sharakot Road, recorded on 25 January, 2026. The affected site is situated within the Kolai Pallas Kohistan district, operating under the administrative jurisdiction of XEN KOLAI PALLAS KOHISTAN. The infrastructure has been primarily affected by Snow Clearance, Land Sliding, Surface of road, encompassing a total span of 10 Kilometers.
Environmental conditions at the site indicated an average recorded snow depth of 4.00 inches. Restoration and clearance efforts were facilitated by the deployment of Excavator , which remained in active operation for a duration of 115 hours . In a formal assessment of the situation, the reporting officer noted with remarks: Road has been partially restored..
The affected area has been mapped using geographic coordinates. The section starts at 73.011474, 35.079318 and ends at 73.058146, 35.035639. For location reference and navigation, view the route on Google Maps.
The road is now partially accessible; however, motorists are advised to proceed with caution as restoration work continues to achieve full safety and normal traffic flow.
The following photographs provide a visual record of the site conditions before and after the activity, illustrating the extent of the affected area and the improvements achieved through the executed operations.