Swat Detail Monsoon (2025)

Report Date: July 06, 2025 Infrastructure Type: Road Total Damages: 17
15
Affected Infrastructures
17
Total Damages
3.938
Damaged Length (KM)
0
Fully Restored
8
Partially Restored
9
Not Restored
226.38 M
Total Cost (PKR)
Reporting Officers
Managing Director
Managing Director PKHA
2 damage(s) reported
Executive Engineer
XEN Swat II Matta
14 damage(s) reported
Executive Engineer
XEN Swat I Saidu Sharif
1 damage(s) reported
Infrastructure Damages
S# Road Name Type Total Length Status Damaged Length Restoration Cost Rehabilitation Cost Date Reported
1 Chakdara-Shamozai-Kabal-Kanju-Matta-Bagh Dheri Road P/HWay (S-3-B) (2 Damages) Road 88 (KM) Not restored 0.015 (KM) 0.00 M 0.53 M Jul 06, 2025
Partially restored 0.018 (KM) 0.00 M 1.40 M Jul 06, 2025
2 Shahoona Rahat kot sakhra (2 Damages) Road 0.50 (KM) Not restored 0.50 (KM) 5.00 M 10.00 M Jul 02, 2025
Remarks: Nil
Not restored 0.50 (KM) 5.00 M 10.00 M Jul 02, 2025
Remarks: Nil
3 swato kalay road Road 1 (KM) Partially restored 0.1 (KM) 9.00 M 2.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
4 cheerbut pakli Road 0.03 (KM) Not restored 0.02 (KM) 8.00 M 4.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
5 Damana shaheed baba road Road 1 (KM) Not restored 1 (KM) 80.00 M 7.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
6 Chamanlai Dagai road matta Road 0.10 (KM) Not restored 0.10 (KM) 0.15 M 3.50 M Jul 02, 2025
Remarks: Nil
7 Chail road & shalikyar Road 8.8 (KM) Partially restored 0.2 (KM) 9.00 M 3.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
8 Ghuprial Balasoor Road Road 11 (KM) Partially restored 0.10 (KM) 1.00 M 3.00 M Jul 02, 2025
Remarks: Nil
9 Miandam road bela Road 2 (KM) Partially restored 0.05 (KM) 4.00 M 4.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
10 rorya road Road 4 (KM) Partially restored 0.01 (KM) 8.00 M 1.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
11 shahgram khwar road Road 0.2 (KM) Not restored 0.02 (KM) 9.00 M 2.50 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
12 Terat dara road Road 6 (KM) Partially restored 1 (KM) 8.00 M 3.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
13 peya chanchary road Road 4 (KM) Partially restored 0.015 (KM) 4.00 M 4.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
14 Dando zowalay road Road 2 (KM) Not restored 0.09 (KM) 8.00 M 3.00 M Jul 02, 2025
Remarks: the restoration work is slated to commence shortly
15 LoyeBand Road Road 3 (KM) Not restored 0.2 (KM) 3.00 M 3.30 M Jun 30, 2025