Report Date: July 06, 2025
Infrastructure Type: Road
Total Damages: 5
5
Affected Infrastructures
5
Total Damages
7.2
Damaged Length (KM)
4
Fully Restored
1
Partially Restored
0
Not Restored
39.25 M
Total Cost (PKR)
Reporting Officers
Executive Engineer
XEN SHANGLA
5 damage(s) reported
Infrastructure Damages
S# | Road Name | Type | Total Length | Status | Damaged Length | Restoration Cost | Rehabilitation Cost | Date Reported |
---|---|---|---|---|---|---|---|---|
1 | Alpurai Lilonai Road | Road | 4.7 (KM) | Fully restored | 1 (KM) | 2.00 M | 15.00 M | Jun 30, 2025 |
2 | Kadona Awarai Mer Jalay Road | Road | 5.8 (KM) | Partially restored | 1.2 (KM) | 1.50 M | 10.00 M | Jun 30, 2025 |
3 | Lawarbat Banjo Sar Road | Road | 7 (KM) | Fully restored | 0.5 (KM) | 0.50 M | 8.00 M | Jun 30, 2025 |
4 | Board Yekhtangi Purn Martung Road. | Road | 52 (KM) | Fully restored | 2 (KM) | 1.05 M | 0.00 M | Jun 30, 2025 |
5 | Ber Teraj to dankol road | Road | 5 (KM) | Fully restored | 2.5 (KM) | 1.20 M | 0.00 M | Jun 30, 2025 |