Malakand Detail Monsoon (2025)

Report Date: July 06, 2025 Infrastructure Type: Road Total Damages: 8
8
Affected Infrastructures
8
Total Damages
5.15
Damaged Length (KM)
0
Fully Restored
5
Partially Restored
3
Not Restored
79.48 M
Total Cost (PKR)
Reporting Officers
Executive Engineer
XEN MALAKAND
8 damage(s) reported
Infrastructure Damages
S# Road Name Type Total Length Status Damaged Length Restoration Cost Rehabilitation Cost Date Reported
1 JALAL PUR ROAD U/C PALAI Road 3 (KM) Not restored .250 (KM) 0.00 M 3.50 M Jul 02, 2025
2 BABAGANO SAR ROAD KAMA AGRA Road 1 (KM) Not restored .200 (KM) 0.00 M 1.00 M Jul 02, 2025
3 Bazdara Road U/c Palai Road 5 (KM) Partially restored .50 (KM) 1.00 M 10.00 M Jul 02, 2025
4 RADAR ROAD THANA Road 2 (KM) Partially restored 1 (KM) 0.50 M 10.00 M Jul 02, 2025
Remarks: 0.00
5 PCC ROAD MUSAFAR KHANA GRAVEYARD THANA Road 1 (KM) Partially restored .80 (KM) 0.25 M 12.00 M Jul 02, 2025
6 PCC ROAD AKHTAR GHWANDAI BATKHELA Road .5 (KM) Not restored .400 (KM) 0.00 M 5.00 M Jul 02, 2025
7 PCC ROAD DANDA THANA KHASS DIST:MALAKAND Road 1 (KM) Partially restored 1 (KM) 1.00 M 15.00 M Jul 02, 2025
Remarks: N/A
8 JUNGAI ROAD U/C THANA JADEED DISTT:MALAKAND Road 1 (KM) Partially restored 1 (KM) 0.23 M 20.00 M Jul 02, 2025
Remarks: NILL
CWD