Report Date:
July 27, 2025
Infrastructure Type:
Road
Total Damages:
13
Reported by:
Abbas Khan
(XEN KURRAM LOWER)
,
Abid Khan
(XEN KURRAM UPPER)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | Khomasa to Arwaza Road Area Makhrany Central Kurram | 25.00 (KM) | Partially restored | 0.200 (KM) | Jul 11, 2025 |
Remarks: R/Wall Damaged , Land slide and some part of Road washed away
Reported by:
XEN KURRAM LOWER
|
|||||
2 | Various Roads In Upper Kurram | 30.00 (KM) | Partially restored | 1.00 (KM) | Jul 07, 2025 |
Remarks: i.e : Luqman Khel, Nastikot, Ahmadzai, Pewar, Burki, Zeran, Kirman, Shakh dowlat Khel etc.
Reported by:
XEN KURRAM UPPER
|
|||||
3 | Parachinar By-Pass Raod | 17.00 (KM) | Partially restored | 0.050 (KM) | Jul 07, 2025 |
Remarks: Road with culvert are partially damaged
Reported by:
XEN KURRAM UPPER
|
|||||
4 | Pewar Road | 23.00 (KM) | Partially restored | 0.030 (KM) | Jul 07, 2025 |
Remarks: Paratially Damaged. Traffic flow is on road shoulders
Reported by:
XEN KURRAM UPPER
|
|||||
5 | Pewar Burki Road | 23.00 (KM) | Partially restored | 0.050 (KM) | Jul 07, 2025 |
Remarks: Paratially Damaged. Traffic floww is on road shoulders
Reported by:
XEN KURRAM UPPER
|
|||||
6 | Zeran By-Pass Road in Main city (2 Damages) | 1.00 (KM) | 1 Not restored | 45.00 (KM) | Jul 07, 2025 |
Remarks: Full culvert has been washed away. The link of the village with the city has been cut off due to damage. The temporary diversion has be made for the traffic flow. And the PC-I has been already submitted for approval. When PC-I approved the road clearance work will be carried out as on priority basis.
Reported by:
XEN KURRAM UPPER
|
|||||
2 Not restored | 0.200 (KM) | Jul 07, 2025 | |||
Remarks: Complete part of the Road with the R/Wall has been washed away. The temporary diversion has be made for the traffic flow. And the PC-I has been already submitted for approval. When PC-I approved the road clearance work will be carried out as on priority basis.
Reported by:
XEN KURRAM UPPER
|
|||||
7 | Komasa to Arwaza Road | 25 (KM) | Partially restored | 1.200 (KM) | Jul 01, 2025 |
Remarks: Land slides. slips and R/wall damaged
Reported by:
XEN KURRAM LOWER
|
|||||
8 | Taby Khani Khel Main Road central kurram | 12 (KM) | Partially restored | 0.800 (KM) | Jul 01, 2025 |
Remarks: Land slided to the road and road was clear for the traffic on emergency basis
Reported by:
XEN KURRAM LOWER
|
|||||
9 | Sadda By-Pass Road | 23.00 (KM) | Fully restored | 0.300 (KM) | Jun 29, 2025 |
Remarks: R/Wall to be needed for the damaged portion and also Drain to be construct for the best flow of water from the road
Reported by:
XEN KURRAM LOWER
|
|||||
10 | Sadda Dogar Road (2 Damages) | 28.00 (KM) | 1 Partially restored | 0.060 (KM) | Jun 29, 2025 |
Remarks: 200 ft R/Wall is fully damaged which needs to be urgent restoration
Reported by:
XEN KURRAM LOWER
|
|||||
2 Partially restored | 0.010 (KM) | Jun 29, 2025 | |||
Remarks: Land slide and road is currently clrared for the trafic flow
Reported by:
XEN KURRAM LOWER
|
|||||
11 | Kemal Baza Road Central Kurram | 05 (KM) | Partially restored | 0.600 (KM) | Jun 29, 2025 |
Remarks: The road is satiauted in central kurram and badly damaged in several parts icluding land slide , fall of R/Wall and shigle road washed away.
Reported by:
XEN KURRAM LOWER
|