Report Date:
August 16, 2025
Infrastructure Type:
Road
Total Damages:
14
Reported by:
Engr. Sohail Idrees
(Managing Director PKHA)
,
Muhammad Zahid
(XEN H/W HARIPUR)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | Sarai Saleh – Rehana - Serian Road S-5-B | 13 (KM) | Not restored | 0.03 (KM) | Aug 16, 2025 |
Remarks: The Road is open for traffic as one lane is properly operational But the same may be restored at the earliest to avoid any further damage to road structure.
Reported by:
Managing Director PKHA
|
|||||
2 | Ghazi-Serikot-Panian Road (S-1) (2 Damages) | 40 (KM) | 1 Not restored | 0.04 (KM) | Aug 16, 2025 |
Remarks: Road is open to traffic as one lane is stable. But the same may be restored at the earliest so that the structure is not further damaged.
Reported by:
Managing Director PKHA
|
|||||
2 Not restored | 0.038 (KM) | Jul 06, 2025 | |||
Remarks: The restoration should be done at the earliest to avoid any damage to the remaining road structure. As it is worsening in the rains on 15 Aug 2025.
Reported by:
Managing Director PKHA
|
|||||
3 | Maqsood Jabri Kohala Rupper Section (2 Damages) | 35 (KM) | 1 Not restored | 0.09 (KM) | Aug 16, 2025 |
Remarks: The restoration should be done at the earliest to avoid any damage to the remaining road structure
Reported by:
Managing Director PKHA
|
|||||
2 Not restored | 0.09 (KM) | Aug 16, 2025 | |||
Remarks: The restoration should be done at the earliest to avoid any damage to the remaining road structure.
Reported by:
Managing Director PKHA
|
|||||
4 | Main road Kahal | 1 (KM) | Partially restored | 1 (KM) | Jul 29, 2025 |
Remarks: Rs. 6.00 (M) required for rehabilitation.
Reported by:
XEN H/W HARIPUR
|
|||||
5 | Baghpur Dehri Road | 5 (KM) | Not restored | 5 (KM) | Jul 28, 2025 |
Remarks: Rs. 2.200 (M) required for rehabilitation.
Reported by:
XEN H/W HARIPUR
|
|||||
6 | S-12 Haripur Chppar Chandur Shara-e-Tanawal to | 72 (KM) | Partially restored | 0.03 (KM) | Jul 06, 2025 |
Remarks: Vented Causeway has been damaged and the wingwall downstream needs to be restored. The Cause Way has been opened manually by labour. The condition of these spots is worsening by every rain fall since and has been affected in the rains of 15-aug-2025.
Reported by:
Managing Director PKHA
|
|||||
7 | Tarnawa to Kohala Bala | 35 (KM) | Partially restored | 14 (KM) | Jul 06, 2025 |
Remarks: The amount is for clearance of debris, sli[ps,ersosion and leveling of Kacha Road only. The boulders on site have been removed Primaly with help of locals,
Reported by:
Managing Director PKHA
|
|||||
8 | Haripur Sarai Nimat Khan road | 14 (KM) | Partially restored | 14 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged.
Reported by:
XEN H/W HARIPUR
|
|||||
9 | Karrach Road | 4 (KM) | Partially restored | 4 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged & road is partially opened for traffic.
Reported by:
XEN H/W HARIPUR
|
|||||
10 | Talhad Road. | 3 (KM) | Partially restored | 3 (KM) | Jul 02, 2025 |
Remarks: Retaining structure damaged on said road. An amount of Rs. 5.000 (M) is restoration of damaged structure.
Reported by:
XEN H/W HARIPUR
|
|||||
11 | Nartopa Road | 12 (KM) | Partially restored | 12 (KM) | Jul 02, 2025 |
Remarks: Retaining wall along road side damaged due to heavy rain fall. An amount of Rs. 2.500 (M) required for restoration of damaged structure.
Reported by:
XEN H/W HARIPUR
|
|||||
12 | Sahki Khenian road | 7 (KM) | Partially restored | 3 (KM) | Jul 02, 2025 |
Remarks: Landslide occurred at the site due to heavy rainfall. The debris has been partially cleared and the road has been restored for traffic
Reported by:
XEN H/W HARIPUR
|