Stories
Loading...

Dir Lower Detail Monsoon (2025)

Report Date: July 06, 2025 Infrastructure Type: Road Total Damages: 2
2
Affected Infrastructures
2
Total Damages
0.8
Damaged Length (KM)
1
Fully Restored
1
Partially Restored
0
Not Restored
8 M
Total Cost (PKR)
Reporting Officers
Managing Director
Managing Director PKHA
1 damage(s) reported
Executive Engineer
XEN H/W DIR LOWER
1 damage(s) reported
Infrastructure Damages
S# Road Name Type Total Length Status Damaged Length Restoration Cost Rehabilitation Cost Date Reported
1 Munda Samarbagh Shahi Road Road 35 (KM) Fully restored 0.5 (KM) 1.00 M 1.00 M Jul 06, 2025
Remarks: Slips and debris have been removed
2 Gawardish Road Road 2 (KM) Partially restored .300 (KM) 3.00 M 3.00 M Jun 30, 2025
Remarks: Fully Damaged / work in progress