Report Date:
July 27, 2025
Infrastructure Type:
Road
Total Damages:
7
Reported by:
Nizam Ud Din
(XEN H/W DIR LOWER)
,
Engr. Sohail Idrees
(Managing Director PKHA)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | Khadang Road Talash | 5 (KM) | Not restored | 5 (KM) | Jul 24, 2025 |
2 | Asbarn Utala Road | 2 (KM) | Partially restored | .2 (KM) | Jul 24, 2025 |
3 | Laram Road | 5 (KM) | Not restored | 0.05 (KM) | Jul 23, 2025 |
4 | Dara Dolai shah Road | 4 (KM) | Not restored | 0.4 (KM) | Jul 23, 2025 |
Remarks: will be completed soon
Reported by:
XEN H/W DIR LOWER
|
|||||
5 | Sia laram Haider road | 5 (KM) | Not restored | 1 (KM) | Jul 23, 2025 |
Remarks: Will be restored soon
Reported by:
XEN H/W DIR LOWER
|
|||||
6 | Munda Samarbagh Shahi Road | 35 (KM) | Fully restored | 0.5 (KM) | Jul 06, 2025 |
Remarks: Slips and debris have been removed
Reported by:
Managing Director PKHA
|
|||||
7 | Gawardish Road | 2 (KM) | Partially restored | .300 (KM) | Jun 30, 2025 |
Remarks: Fully Damaged / work in progress
Reported by:
XEN H/W DIR LOWER
|