Dir Lower Damages Detail - Monsoon (2025)

Report Date: July 27, 2025 Infrastructure Type: Road Total Damages: 7
Reported by:
Nizam Ud Din (XEN H/W DIR LOWER) , Engr. Sohail Idrees (Managing Director PKHA)
7
Affected Roads
7
Total Damages
7.45
Damaged Length (KM)
1
Fully Restored
2
Partially Restored
4
Not Restored
Road Damages
S# Road Name Total Length Status Damaged Length Dated
1 Khadang Road Talash 5 (KM) Not restored 5 (KM) Jul 24, 2025
2 Asbarn Utala Road 2 (KM) Partially restored .2 (KM) Jul 24, 2025
3 Laram Road 5 (KM) Not restored 0.05 (KM) Jul 23, 2025
4 Dara Dolai shah Road 4 (KM) Not restored 0.4 (KM) Jul 23, 2025
Remarks: will be completed soon
Reported by: XEN H/W DIR LOWER
5 Sia laram Haider road 5 (KM) Not restored 1 (KM) Jul 23, 2025
Remarks: Will be restored soon
Reported by: XEN H/W DIR LOWER
6 Munda Samarbagh Shahi Road 35 (KM) Fully restored 0.5 (KM) Jul 06, 2025
Remarks: Slips and debris have been removed
Reported by: Managing Director PKHA
7 Gawardish Road 2 (KM) Partially restored .300 (KM) Jun 30, 2025
Remarks: Fully Damaged / work in progress
Reported by: XEN H/W DIR LOWER