Report Date:
July 27, 2025
Infrastructure Type:
Road
Total Damages:
1
Reported by:
Muhammad Adnan
(XEN LOWER CHITRAL)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages
S# | Road Name | Total Length | Status | Damaged Length | Dated |
---|---|---|---|---|---|
1 | Faizabad Hone road, Shiaqotak, Doomshor Orguch road | 7 (KM) | Partially restored | 0.20 (KM) | Jun 30, 2025 |
Remarks: Due to high flood level, the said retaining wall was damaged which was restored immediately. However rehabilitation of the retaining wall is required
Reported by:
XEN LOWER CHITRAL
|