Chitral Lower Damages Detail - Monsoon (2025)

Report Date: August 16, 2025 Infrastructure Type: Road Total Damages: 4
Reported by:
Muhammad Adnan (XEN LOWER CHITRAL)
4
Affected Roads
4
Total Damages
20.7
Damaged Length (KM)
1
Fully Restored
3
Partially Restored
0
Not Restored
Road Damages
S# Road Name Total Length Status Damaged Length Dated
1 Arkari Valley 32 (KM) Partially restored 10 (KM) Aug 15, 2025
Remarks: Work on restoration is in progress
Reported by: XEN LOWER CHITRAL
2 Prait Road 5 (KM) Partially restored 0.5 (KM) Aug 15, 2025
Remarks: Work on restoration (Blasting) is in progress
Reported by: XEN LOWER CHITRAL
3 Madaklasht Road 45 (KM) Partially restored 10 (KM) Jul 30, 2025
Remarks: Road has been temporarily restored. Further work in progress
Reported by: XEN LOWER CHITRAL
4 Faizabad Hone road, Shiaqotak, Doomshor Orguch road 7 (KM) Fully restored 0.2 (KM) Jun 30, 2025
Remarks: Due to high flood level, the said retaining wall was damaged which was restored immediately. However rehabilitation of the retaining wall is required
Reported by: XEN LOWER CHITRAL