Report Date: July 06, 2025
Infrastructure Type: Road
Total Damages: 1
1
Affected Infrastructures
1
Total Damages
15
Damaged Length (KM)
0
Fully Restored
1
Partially Restored
0
Not Restored
6.8 M
Total Cost (PKR)
Reporting Officers
Executive Engineer
XEN H/W BAJAUR
1 damage(s) reported
Infrastructure Damages
S# | Road Name | Type | Total Length | Status | Damaged Length | Restoration Cost | Rehabilitation Cost | Date Reported |
---|---|---|---|---|---|---|---|---|
1 | Khar-Barang Road | Road | 45 (KM) | Partially restored | 15 (KM) | 0.80 M | 6.00 M | Jul 02, 2025 |
Remarks: Damage due to rain |