Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
16-11-15 | - | - | 08-10-15 | - | 81.786 | 54.996 | 4.584 | 4.584 | 4.584 | 4.584 | 59.58 | 22.206 | 73% |
73% December - 2017 |
7 units- 6 units completed. 1 unit work in progress. Demand Rs.16.400 m. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
16-11-15 | - | - | 08-10-15 | - | 81.786 | 54.996 | 4.584 | 4.584 | 4.584 | 3.51 | 58.506 | 22.206 | 73% |
72% September - 2017 |
Work in progress. Revised approved for Rs.20 m in DDWP on 10/02/2017. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
16-11-15 | - | - | 08-10-15 | - | 81.786 | 54.996 | 0 | 0 | 0 | 0 | 54.996 | 26.79 | - |
67% August - 2017 |
Work in progress. Revised approved for Rs.20 m in DDWP on 10/02/2017. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
16-11-15 | - | - | 08-10-15 | - | 81.786 | 54.996 | 0 | 0 | 0 | 0 | 54.996 | 26.79 | - |
67% July - 2017 |
Work in progress. Revised approved for Rs.20 m in DDWP on 10/02/2017. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 4.584 | 4.584 | 4.584 | 4.584 | 59.58 | 22.206 | 73% |
73% November - 2017 |
7 units- 6 units completed. 1 unit work in progress. Demand Rs.16.400 m. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 4.584 | 4.584 | 4.584 | 3.51 | 58.506 | 22.206 | 73% |
72% October - 2017 |
Work in progress. Revised approved for Rs.20 m in DDWP on 10/02/2017. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 5.584 | 5.584 | 5.584 | 5.584 | 60.58 | 21.206 | 74% |
74% June - 2018 |
7 units - 6 completed, 1 work in progress. |
No Image |
1) Package-1 UC Dolola
(a) Dozer/excavator work dograina Sirla Lower RW where required (b) PCC raod forSari Talaq Ban
2) Package-2 UC Bol
(a) Rehab/imp/PCC from GGPS Barbeento Sathian Bandi Imtiaz House (b) Tori Madai to GHSS Bol
3) Package-3 UC Kuchmang
(a) PCC/Rehab of Sargran Karwar to Gali (b) PCC/Rehab from Main road to Sania village
4) Package-4 UC Pattan
(a) Dozer/excavator work for Koatla to Kotlian Noorgucha (b) Rehab/Imp/widening of Grom Serian village to Dheri Sialkot via Hohri and Hastena Doga
5) Package-5 UC Pluck
(a) PCC/Rehab from main road Sari Plack to Nursery road (b) Dozer/excavator work from main rod Kutly Plack to Para Hotor (c) Dozer/excavator work from BHU Plack to Seri village RW (d) PCC/Imp from telephone exchange to Darwaza Lower Malkot
6) Package-6 UC Bakot
(a) PCC/rehab Moolia Kas to PS Bakot link road (b) PCC/Imp from main road to Moolia Numbal to Lower Sangal Master Javed
7) Package-7 UC Berote
(a) Rehab/PCC workGala Bandi Tower Berote to Mohallah Gulah House (b) Imp/rehab/PCC work Kohu Choorian road to Chairlift
8) Rehabilitation/improvement of PCC for BHU Kukmar Link road Pandian, remaining portion UC Kokmang
9) Rehabilitation/improvement fo PCC for Deedal to Naka road UC Bol
10) Rehabilitation/improvement of PCC Gali to Nargolo link road UC Pluck
11) Rehabilitation/improvement/PCC road to Village Kala Ban UC Pluck
12) Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Chaoona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 5.584 | 5.584 | 5.584 | 5.584 | 60.58 | 21.206 | 74% |
74% May - 2018 |
7 units - 6 completed, 1 work in progress. Demand Rs.16.400 m. |
No Image |
1) Package-1 UC Dolola
(a) Dozer/excavator work dograina Sirla Lower RW where required (b) PCC raod forSari Talaq Ban
2) Package-2 UC Bol
(a) Rehab/imp/PCC from GGPS Barbeento Sathian Bandi Imtiaz House (b) Tori Madai to GHSS Bol
3) Package-3 UC Kuchmang
(a) PCC/Rehab of Sargran Karwar to Gali (b) PCC/Rehab from Main road to Sania village
4) Package-4 UC Pattan
(a) Dozer/excavator work for Koatla to Kotlian Noorgucha (b) Rehab/Imp/widening of Grom Serian village to Dheri Sialkot via Hohri and Hastena Doga
5) Package-5 UC Pluck
(a) PCC/Rehab from main road Sari Plack to Nursery road (b) Dozer/excavator work from main rod Kutly Plack to Para Hotor (c) Dozer/excavator work from BHU Plack to Seri village RW (d) PCC/Imp from telephone exchange to Darwaza Lower Malkot
6) Package-6 UC Bakot
(a) PCC/rehab Moolia Kas to PS Bakot link road (b) PCC/Imp from main road to Moolia Numbal to Lower Sangal Master Javed
7) Package-7 UC Berote
(a) Rehab/PCC workGala Bandi Tower Berote to Mohallah Gulah House (b) Imp/rehab/PCC work Kohu Choorian road to Chairlift
8) Rehabilitation/improvement of PCC for BHU Kukmar Link road Pandian, remaining portion UC Kokmang
9) Rehabilitation/improvement fo PCC for Deedal to Naka road UC Bol
10) Rehabilitation/improvement of PCC Gali to Nargolo link road UC Pluck
11) Rehabilitation/improvement/PCC road to Village Kala Ban UC Pluck
12) Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Chaoona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 5.584 | 5.584 | 5.584 | 5.584 | 60.58 | 21.206 | 74% |
74% April - 2018 |
7 units - 6 completed, 1 work in progress. Demand Rs.16.400 m. |
No Image |
1) Package-1 UC Dolola
(a) Dozer/excavator work dograina Sirla Lower RW where required (b) PCC raod forSari Talaq Ban
2) Package-2 UC Bol
(a) Rehab/imp/PCC from GGPS Barbeento Sathian Bandi Imtiaz House (b) Tori Madai to GHSS Bol
3) Package-3 UC Kuchmang
(a) PCC/Rehab of Sargran Karwar to Gali (b) PCC/Rehab from Main road to Sania village
4) Package-4 UC Pattan
(a) Dozer/excavator work for Koatla to Kotlian Noorgucha (b) Rehab/Imp/widening of Grom Serian village to Dheri Sialkot via Hohri and Hastena Doga
5) Package-5 UC Pluck
(a) PCC/Rehab from main road Sari Plack to Nursery road (b) Dozer/excavator work from main rod Kutly Plack to Para Hotor (c) Dozer/excavator work from BHU Plack to Seri village RW (d) PCC/Imp from telephone exchange to Darwaza Lower Malkot
6) Package-6 UC Bakot
(a) PCC/rehab Moolia Kas to PS Bakot link road (b) PCC/Imp from main road to Moolia Numbal to Lower Sangal Master Javed
7) Package-7 UC Berote
(a) Rehab/PCC workGala Bandi Tower Berote to Mohallah Gulah House (b) Imp/rehab/PCC work Kohu Choorian road to Chairlift
8) Rehabilitation/improvement of PCC for BHU Kukmar Link road Pandian, remaining portion UC Kokmang
9) Rehabilitation/improvement fo PCC for Deedal to Naka road UC Bol
10) Rehabilitation/improvement of PCC Gali to Nargolo link road UC Pluck
11) Rehabilitation/improvement/PCC road to Village Kala Ban UC Pluck
12) Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Chaoona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 5.584 | 5.584 | 5.584 | 5.584 | 60.58 | 21.206 | 74% |
74% March - 2018 |
7 units - 6 completed, 1 work in progress. Demand Rs.16.400 m. |
No Image |
1) Package-1 UC Dolola
(a) Dozer/excavator work dograina Sirla Lower RW where required (b) PCC raod forSari Talaq Ban
2) Package-2 UC Bol
(a) Rehab/imp/PCC from GGPS Barbeento Sathian Bandi Imtiaz House (b) Tori Madai to GHSS Bol
3) Package-3 UC Kuchmang
(a) PCC/Rehab of Sargran Karwar to Gali (b) PCC/Rehab from Main road to Sania village
4) Package-4 UC Pattan
(a) Dozer/excavator work for Koatla to Kotlian Noorgucha (b) Rehab/Imp/widening of Grom Serian village to Dheri Sialkot via Hohri and Hastena Doga
5) Package-5 UC Pluck
(a) PCC/Rehab from main road Sari Plack to Nursery road (b) Dozer/excavator work from main rod Kutly Plack to Para Hotor (c) Dozer/excavator work from BHU Plack to Seri village RW (d) PCC/Imp from telephone exchange to Darwaza Lower Malkot
6) Package-6 UC Bakot
(a) PCC/rehab Moolia Kas to PS Bakot link road (b) PCC/Imp from main road to Moolia Numbal to Lower Sangal Master Javed
7) Package-7 UC Berote
(a) Rehab/PCC workGala Bandi Tower Berote to Mohallah Gulah House (b) Imp/rehab/PCC work Kohu Choorian road to Chairlift
8) Rehabilitation/improvement of PCC for BHU Kukmar Link road Pandian, remaining portion UC Kokmang
9) Rehabilitation/improvement fo PCC for Deedal to Naka road UC Bol
10) Rehabilitation/improvement of PCC Gali to Nargolo link road UC Pluck
11) Rehabilitation/improvement/PCC road to Village Kala Ban UC Pluck
12) Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Chaoona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 5.584 | 5.584 | 5.584 | 5.584 | 60.58 | 21.206 | 74% |
74% February - 2018 |
7 units - 6 completed, 1 work in progress. Demand Rs.16.400 m. |
No Image |
1) Package-1 UC Dolola
(a) Dozer/excavator work dograina Sirla Lower RW where required (b) PCC raod forSari Talaq Ban
2) Package-2 UC Bol
(a) Rehab/imp/PCC from GGPS Barbeento Sathian Bandi Imtiaz House (b) Tori Madai to GHSS Bol
3) Package-3 UC Kuchmang
(a) PCC/Rehab of Sargran Karwar to Gali (b) PCC/Rehab from Main road to Sania village
4) Package-4 UC Pattan
(a) Dozer/excavator work for Koatla to Kotlian Noorgucha (b) Rehab/Imp/widening of Grom Serian village to Dheri Sialkot via Hohri and Hastena Doga
5) Package-5 UC Pluck
(a) PCC/Rehab from main road Sari Plack to Nursery road (b) Dozer/excavator work from main rod Kutly Plack to Para Hotor (c) Dozer/excavator work from BHU Plack to Seri village RW (d) PCC/Imp from telephone exchange to Darwaza Lower Malkot
6) Package-6 UC Bakot
(a) PCC/rehab Moolia Kas to PS Bakot link road (b) PCC/Imp from main road to Moolia Numbal to Lower Sangal Master Javed
7) Package-7 UC Berote
(a) Rehab/PCC workGala Bandi Tower Berote to Mohallah Gulah House (b) Imp/rehab/PCC work Kohu Choorian road to Chairlift
8) Rehabilitation/improvement of PCC for BHU Kukmar Link road Pandian, remaining portion UC Kokmang
9) Rehabilitation/improvement fo PCC for Deedal to Naka road UC Bol
10) Rehabilitation/improvement of PCC Gali to Nargolo link road UC Pluck
11) Rehabilitation/improvement/PCC road to Village Kala Ban UC Pluck
12) Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Chaoona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 54.996 | 4.584 | 4.584 | 4.584 | 4.584 | 59.58 | 22.206 | 73% |
73% January - 2018 |
7 units- 6 units completed. 1 unit work in progress. Demand Rs.16.400 m. |
No Image |
Black Topping of Road from Lakhpati Chowk to Ilyasi Masjid i/c Beautification of Ilyasi Masjid Park and Choona Kari Road District Abbottabad (AA cost Rs.20 m dated 11/05/2017) | |||||||||||||||||||
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% December - 2020 |
3- Components Completed & H/O = 3 |
No Image |
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% December - 2020 |
3- Components Completed & H/O = 3 |
No Image |
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% October - 2020 |
3- Components Completed & H/O = 3 |
No Image |
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% September - 2020 |
3- Components Completed & H/O = 3 |
No Image |
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% May - 2021 |
03- Unit
All Completed & H/O |
No Image |
Solarization of existing AHQ/THQ Hospitals | |||||||||||||||||||
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% April - 2021 |
3- Components Completed & H/O = 3 |
No Image |
Solarization of existing AHQ/THQ Hospitals | |||||||||||||||||||
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% March - 2021 |
3- Components Completed & H/O = 3 |
No Image |
Solarization of existing AHQ/THQ Hospitals | |||||||||||||||||||
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% February - 2021 |
3- Components Completed & H/O = 3 |
No Image |
Solarization of existing AHQ/THQ Hospitals | |||||||||||||||||||
844 (OG) |
191526-130422 - Solarization of existing AHQ/THQ Hospitals FATA. [MA] |
Bajaur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35.51 | 35.479 | 0 | 0 | 0 | 0 | 35.479 | 0.031 | - |
100% January - 2021 |
3- Components Completed & H/O = 3 |
No Image |
Solarization of existing AHQ/THQ Hospitals | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
- | - | - | 24-08-17 | - | 48.019 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 26.126 | - |
46% December - 2017 |
7 components - 2 completed, 4 earth work in progress, 1 e-bi invited on 26/12/2017 Demand Rs.20 m. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
- | - | - | 08-10-15 | - | 38.828 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 16.935 | - |
56% September - 2017 |
Work in progress. Demand Rs.20 m. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
- | - | - | 08-10-15 | - | 38.828 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 16.935 | - |
56% August - 2017 |
Work in progress. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
- | - | - | 08-10-15 | - | 38.828 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 16.935 | - |
56% July - 2017 |
Work in progress. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.019 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 26.126 | - |
46% November - 2017 |
Work in progress. Demand Rs.20 m. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.019 | 21.893 | 0 | 0 | 0 | 0 | 21.893 | 26.126 | - |
46% October - 2017 |
Work in progress. Demand Rs.20 m. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 21.893 | 2 | 2 | 2 | 2 | 23.893 | 70.091 | 25% |
25% June - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bid invited on 26/12/2017. |
No Image |
1) Construction/rehabilitation of Jehangir Lalozai road via Piran road Surrani PK-70, Bannu
2) Construction/rehabilitation of Habak Sherza Khan Surrani road PK-70, Bannu
3) Construction of road Muhammad Khan Mera Khel PK-73, Bannu
4) Construction of road Sher Killay Kakki PK-73, Bannu
5) Construction of road Nekam Kalay Kakki PK-73, Bannu
6) Construction/rehabilitation of Kakki road to Deri Ferum BT road i/c Bridge Lora PK-73, Bannu
7) Construction of BT road from DI.Khan road to Kotka Juma Khan PK-73, Bannu
8) Construction of road from Waligai road Tehsil Domel PK-71, Bannu
9) Construction of road from Baran road to Airport Parking (Hafizullah)
10) Construction of road from Marwat Canal road to Farid Ullah Kor Bannu
11) Construction & BTR from Main Miryan road to Mumbati Barakzai (Shahqiaz) PK-72
12) Construction & BT/continuation of roads from Dhery Khuley road to Lavut Landidak Phase-II | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 21.893 | 7 | 7 | 7 | 1.932 | 23.825 | 65.091 | 31% |
25% May - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bid invited on 26/12/2017. Demand Rs.20 m. |
No Image |
1) Construction/rehabilitation of Jehangir Lalozai road via Piran road Surrani PK-70, Bannu
2) Construction/rehabilitation of Habak Sherza Khan Surrani road PK-70, Bannu
3) Construction of road Muhammad Khan Mera Khel PK-73, Bannu
4) Construction of road Sher Killay Kakki PK-73, Bannu
5) Construction of road Nekam Kalay Kakki PK-73, Bannu
6) Construction/rehabilitation of Kakki road to Deri Ferum BT road i/c Bridge Lora PK-73, Bannu
7) Construction of BT road from DI.Khan road to Kotka Juma Khan PK-73, Bannu
8) Construction of road from Waligai road Tehsil Domel PK-71, Bannu
9) Construction of road from Baran road to Airport Parking (Hafizullah)
10) Construction of road from Marwat Canal road to Farid Ullah Kor Bannu
11) Construction & BTR from Main Miryan road to Mumbati Barakzai (Shahqiaz) PK-72
12) Construction & BT/continuation of roads from Dhery Khuley road to Lavut Landidak Phase-II | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 21.893 | 7 | 7 | 7 | 1.29 | 23.183 | 65.091 | 31% |
25% April - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bid invited on 26/12/2017. Demand Rs.20 m. |
No Image |
1) Construction/rehabilitation of Jehangir Lalozai road via Piran road Surrani PK-70, Bannu
2) Construction/rehabilitation of Habak Sherza Khan Surrani road PK-70, Bannu
3) Construction of road Muhammad Khan Mera Khel PK-73, Bannu
4) Construction of road Sher Killay Kakki PK-73, Bannu
5) Construction of road Nekam Kalay Kakki PK-73, Bannu
6) Construction/rehabilitation of Kakki road to Deri Ferum BT road i/c Bridge Lora PK-73, Bannu
7) Construction of BT road from DI.Khan road to Kotka Juma Khan PK-73, Bannu
8) Construction of road from Waligai road Tehsil Domel PK-71, Bannu
9) Construction of road from Baran road to Airport Parking (Hafizullah)
10) Construction of road from Marwat Canal road to Farid Ullah Kor Bannu
11) Construction & BTR from Main Miryan road to Mumbati Barakzai (Shahqiaz) PK-72
12) Construction & BT/continuation of roads from Dhery Khuley road to Lavut Landidak Phase-II | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 73.984 | 21.893 | 7 | 7 | 7 | 1.29 | 23.183 | 45.091 | 39% |
31% March - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bid invited on 26/12/2017. Demand Rs.20 m. |
No Image |
1) Construction/rehabilitation of Jehangir Lalozai road via Piran road Surrani PK-70, Bannu
2) Construction/rehabilitation of Habak Sherza Khan Surrani road PK-70, Bannu
3) Construction of road Muhammad Khan Mera Khel PK-73, Bannu
4) Construction of road Sher Killay Kakki PK-73, Bannu
5) Construction of road Nekam Kalay Kakki PK-73, Bannu
6) Construction/rehabilitation of Kakki road to Deri Ferum BT road i/c Bridge Lora PK-73, Bannu
7) Construction of BT road from DI.Khan road to Kotka Juma Khan PK-73, Bannu
8) Construction of road from Waligai road Tehsil Domel PK-71, Bannu
9) Construction of road from Baran road to Airport Parking (Hafizullah)
10) Construction of road from Marwat Canal road to Farid Ullah Kor Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 73.984 | 21.893 | 7 | 7 | 7 | 1.29 | 23.183 | 45.091 | 39% |
31% February - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bid invited on 26/12/2017. Demand Rs.20 m. |
No Image |
1) Construction/rehabilitation of Jehangir Lalozai road via Piran road Surrani PK-70, Bannu
2) Construction/rehabilitation of Habak Sherza Khan Surrani road PK-70, Bannu
3) Construction of road Muhammad Khan Mera Khel PK-73, Bannu
4) Construction of road Sher Killay Kakki PK-73, Bannu
5) Construction of road Nekam Kalay Kakki PK-73, Bannu
6) Construction/rehabilitation of Kakki road to Deri Ferum BT road i/c Bridge Lora PK-73, Bannu
7) Construction of BT road from DI.Khan road to Kotka Juma Khan PK-73, Bannu
8) Construction of road from Waligai road Tehsil Domel PK-71, Bannu
9) Construction of road from Baran road to Airport Parking (Hafizullah)
10) Construction of road from Marwat Canal road to Farid Ullah Kor Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 48.019 | 21.893 | 2 | 2 | 2 | 1.29 | 23.183 | 24.126 | 50% |
48% January - 2018 |
7 components - 2 completed, 4 earth work in progress, 1 e-bi invited on 26/12/2017 Demand Rs.20 m. |
No Image |
Construction of road from Woligai road Tehsil Domel PK-71 Bannu | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
19-11-15 | - | - | 08-10-15 | - | 40.37 | 31.383 | 2 | 2 | 2 | 0 | 31.383 | 6.987 | 83% |
78% December - 2017 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
19-11-15 | - | - | 08-10-15 | - | 40.37 | 31.383 | 0 | 0 | 0 | 0 | 31.383 | 8.987 | - |
78% September - 2017 |
Out of 6 units, 4 completed, 2 in progress. |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
19-11-15 | - | - | 08-10-15 | - | 40.37 | 31.383 | 0 | 0 | 0 | 0 | 31.383 | 8.987 | - |
78% August - 2017 |
Out of 6 units, 4 completed, 2 in progress. |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
19-11-15 | - | - | 08-10-15 | - | 30.786 | 31.383 | 0 | 0 | 0 | 0 | 31.383 | 0 | - |
100% July - 2017 |
Work in progress (6 units). |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.383 | 0 | 0 | 0 | 0 | 31.383 | 8.987 | - |
78% November - 2017 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.383 | 0 | 0 | 0 | 0 | 31.383 | 8.987 | - |
78% October - 2017 |
Completed (6 units). |
No Image |
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.323 | 2 | 2 | 2 | 2 | 33.323 | 7.047 | 83% |
83% June - 2018 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
2) Improvement of PCC road Dheri Jangeer Khan road PK-59
3) PCC road Ghado road PK-59
4) PCC road Gat Seri road PK-59
5) PCC road Joz road PK-59
6) PCC road Shalghay and Habib-ur-Rehman Chaphargram PK-59
7) PCC Link rod Shahal UC Batkool PK-60
8) Link road Gat Khawa UC Banna PK-60
9) Link road Jhangri Dano UC Pashto PK-60
10) Link road Dum Dum UC Bateela PK-60
11) Extension in link road Galshoot UC Jambera PK-60
12) Extension in link road Kaho Kandow, Pashto PK-60
13) Link road Mir Ali Pashto instead of Karsow, Pashto PK-60
14) Extension in linkroad Sokar UC Sakargah PK-60
15) PCC link road Goshra UC Batkool PK-60
16) PCC link road Bandi Khanim Ullah UC Behari PK-60
17) PCC link road Mulyano Piza UC Batkool PK-60
18) Link road Char Saidan Surgay UC Batkool PK-60
19) PCC link road Nisa Ppokal UC Biari PK-60
20) PCC link road Dor Mano UC Bihari PK-60
21) Repair work of link road Tailous UC Banna PK-60
22) PCC road Phagora village Talib Baba UC Rajdhari PK-59
23) Construction of road Sparashma Kotgalla UC Peshora PK-59
24) PCC road Chohan UC Bannian PK-59
25) Construction of road Matokar Akbar Korona UC Ajmera PK-59
26) Construction/PCC road Malkot UC Gijbori PK-59
27) PCC raod Orangzeb Khan Tona Uc Banian PK-59
28) Construction/PCC Gat Chinar Banj road Ajmera UC Ajmera PK-59 | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.323 | 2 | 2 | 2 | 2 | 33.323 | 7.047 | 83% |
83% May - 2018 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
1) Road Seri Shehzada road PK-59
2) Improvement of PCC road Dheri Jangeer Khan road PK-59
3) PCC road Ghado road PK-59
4) PCC road Gat Seri road PK-59
5) PCC road Joz road PK-59
6) PCC road Shalghay and Habib-ur-Rehman Chaphargram PK-59
7) PCC Link rod Shahal UC Batkool PK-60
8) Link road Gat Khawa UC Banna PK-60
9) Link road Jhangri Dano UC Pashto PK-60
10) Link road Dum Dum UC Bateela PK-60
11) Extension in link road Galshoot UC Jambera PK-60
12) Extension in link road Kaho Kandow, Pashto PK-60
13) Link road Mir Ali Pashto instead of Karsow, Pashto PK-60
14) Extension in linkroad Sokar UC Sakargah PK-60
15) PCC link road Goshra UC Batkool PK-60
16) PCC link road Bandi Khanim Ullah UC Behari PK-60
17) PCC link road Mulyano Piza UC Batkool PK-60
18) Link road Char Saidan Surgay UC Batkool PK-60
19) PCC link road Nisa Ppokal UC Biari PK-60
20) PCC link road Dor Mano UC Bihari PK-60
21) Repair work of link road Tailous UC Banna PK-60
22) PCC road Phagora village Talib Baba UC Rajdhari PK-59
23) Construction of road Sparashma Kotgalla UC Peshora PK-59
24) PCC road Chohan UC Bannian PK-59
25) Construction of road Matokar Akbar Korona UC Ajmera PK-59
26) Construction/PCC road Malkot UC Gijbori PK-59
27) PCC raod Orangzeb Khan Tona Uc Banian PK-59
28) Construction/PCC Gat Chinar Banj road Ajmera UC Ajmera PK-59 | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.323 | 2 | 2 | 2 | 2 | 33.323 | 7.047 | 83% |
83% April - 2018 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
1) Road Seri Shehzada road PK-59
2) Improvement of PCC road Dheri Jangeer Khan road PK-59
3) PCC road Ghado road PK-59
4) PCC road Gat Seri road PK-59
5) PCC road Joz road PK-59
6) PCC road Shalghay and Habib-ur-Rehman Chaphargram PK-59
7) PCC Link rod Shahal UC Batkool PK-60
8) Link road Gat Khawa UC Banna PK-60
9) Link road Jhangri Dano UC Pashto PK-60
10) Link road Dum Dum UC Bateela PK-60
11) Extension in link road Galshoot UC Jambera PK-60
12) Extension in link road Kaho Kandow, Pashto PK-60
13) Link road Mir Ali Pashto instead of Karsow, Pashto PK-60
14) Extension in linkroad Sokar UC Sakargah PK-60
15) PCC link road Goshra UC Batkool PK-60
16) PCC link road Bandi Khanim Ullah UC Behari PK-60
17) PCC link road Mulyano Piza UC Batkool PK-60
18) Link road Char Saidan Surgay UC Batkool PK-60
19) PCC link road Nisa Ppokal UC Biari PK-60
20) PCC link road Dor Mano UC Bihari PK-60
21) Repair work of link road Tailous UC Banna PK-60
22) PCC road Phagora village Talib Baba UC Rajdhari PK-59
23) Construction of road Sparashma Kotgalla UC Peshora PK-59
24) PCC road Chohan UC Bannian PK-59
25) Construction of road Matokar Akbar Korona UC Ajmera PK-59
26) Construction/PCC road Malkot UC Gijbori PK-59
27) PCC raod Orangzeb Khan Tona Uc Banian PK-59
28) Construction/PCC Gat Chinar Banj road Ajmera UC Ajmera PK-59 | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.383 | 2 | 2 | 2 | 2 | 33.383 | 6.987 | 83% |
83% March - 2018 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
1) Road Seri Shehzada road PK-59
2) Improvement of PCC road Dheri Jangeer Khan road PK-59
3) PCC road Ghado road PK-59
4) PCC road Gat Seri road PK-59
5) PCC road Joz road PK-59
6) PCC road Shalghay and Habib-ur-Rehman Chaphargram PK-59
7) PCC Link rod Shahal UC Batkool PK-60
8) Link road Gat Khawa UC Banna PK-60
9) Link road Jhangri Dano UC Pashto PK-60
10) Link road Dum Dum UC Bateela PK-60
11) Extension in link road Galshoot UC Jambera PK-60
12) Extension in link road Kaho Kandow, Pashto PK-60
13) Link road Mir Ali Pashto instead of Karsow, Pashto PK-60
14) Extension in linkroad Sokar UC Sakargah PK-60
15) PCC link road Goshra UC Batkool PK-60
16) PCC link road Bandi Khanim Ullah UC Behari PK-60
17) PCC link road Mulyano Piza UC Batkool PK-60
18) Link road Char Saidan Surgay UC Batkool PK-60
19) PCC link road Nisa Ppokal UC Biari PK-60
20) PCC link road Dor Mano UC Bihari PK-60
21) Repair work of link road Tailous UC Banna PK-60
22) PCC road Phagora village Talib Baba UC Rajdhari PK-59
23) Construction of road Sparashma Kotgalla UC Peshora PK-59
24) PCC road Chohan UC Bannian PK-59
25) Construction of road Matokar Akbar Korona UC Ajmera PK-59
26) Construction/PCC road Malkot UC Gijbori PK-59
27) PCC raod Orangzeb Khan Tona Uc Banian PK-59
28) Construction/PCC Gat Chinar Banj road Ajmera UC Ajmera PK-59 | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.383 | 2 | 2 | 2 | 2 | 33.383 | 6.987 | 83% |
83% February - 2018 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
1) Road Seri Shehzada road PK-59
2) Improvement of PCC road Dheri Jangeer Khan road PK-59
3) PCC road Ghado road PK-59
4) PCC road Gat Seri road PK-59
5) PCC road Joz road PK-59
6) PCC road Shalghay and Habib-ur-Rehman Chaphargram PK-59
7) PCC Link rod Shahal UC Batkool PK-60
8) Link road Gat Khawa UC Banna PK-60
9) Link road Jhangri Dano UC Pashto PK-60
10) Link road Dum Dum UC Bateela PK-60
11) Extension in link road Galshoot UC Jambera PK-60
12) Extension in link road Kaho Kandow, Pashto PK-60
13) Link road Mir Ali Pashto instead of Karsow, Pashto PK-60
14) Extension in linkroad Sokar UC Sakargah PK-60
15) PCC link road Goshra UC Batkool PK-60
16) PCC link road Bandi Khanim Ullah UC Behari PK-60
17) PCC link road Mulyano Piza UC Batkool PK-60
18) Link road Char Saidan Surgay UC Batkool PK-60
19) PCC link road Nisa Ppokal UC Biari PK-60
20) PCC link road Dor Mano UC Bihari PK-60
21) Repair work of link road Tailous UC Banna PK-60
22) PCC road Phagora village Talib Baba UC Rajdhari PK-59
23) Construction of road Sparashma Kotgalla UC Peshora PK-59
24) PCC road Chohan UC Bannian PK-59
25) Construction of road Matokar Akbar Korona UC Ajmera PK-59
26) Construction/PCC road Malkot UC Gijbori PK-59
27) PCC raod Orangzeb Khan Tona Uc Banian PK-59
28) Construction/PCC Gat Chinar Banj road Ajmera UC Ajmera PK-59 | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 31.383 | 2 | 2 | 2 | 2 | 33.383 | 6.987 | 83% |
83% January - 2018 |
Completed (6 units). Demand Rs.8.429 m. |
No Image |
1) Seri Shehzada road 2) Dheri Jangeer Khan road 3) Ghado road 4) Gat Seri road 5) Joz road 6) Shalghay and Habib-ur-Rehman Chaphargram | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Buner |
01-05-16 | - | - | 08-10-15 | - | 100.07 | 24.766 | 0 | 0 | 0 | 0 | 24.766 | 75.304 | - |
25% December - 2017 |
80% work completed (7 units). |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 Km) --- Rs.7.44 m
2) Agra Matwani Road UC Deewana Baba PK-78 (1.50 Km) --- Rs.15.48 m
3) Topai Bakaar Road UC Chagarzai PK-78 (2.30 Km) --- Rs.21.17 m
4) Shalizara Road UC Norizi PK-78 (1.525 Km) --- Rs.19353 m
5) Cheena/Chanar Dund Barkalay Road UC Norizi PK-78 (2.275 Km) -- Rs.16.85 m
6) Shalbandi Bakhsha Hujra Road UC Shalbandi PK-78 (1.30 Km) --- Rs.10.30 m
7) Krapa Maizari Road UC Gagra PK-78 (1 Km) --- Rs.9.30 m | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Buner |
01-05-16 | - | - | 08-10-15 | - | 100.07 | 24.766 | 0 | 0 | 0 | 0 | 24.766 | 75.304 | - |
25% September - 2017 |
Work in progress. |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 Km) --- Rs.7.44 m
2) Agra Matwani Road UC Deewana Baba PK-78 (1.50 Km) --- Rs.15.48 m
3) Topai Bakaar Road UC Chagarzai PK-78 (2.30 Km) --- Rs.21.17 m
4) Shalizara Road UC Norizi PK-78 (1.525 Km) --- Rs.19353 m
5) Cheena/Chanar Dund Barkalay Road UC Norizi PK-78 (2.275 Km) -- Rs.16.85 m
6) Shalbandi Bakhsha Hujra Road UC Shalbandi PK-78 (1.30 Km) --- Rs.10.30 m
7) Krapa Maizari Road UC Gagra PK-78 (1 Km) --- Rs.9.30 m | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Buner |
01-05-16 | - | - | 08-10-15 | - | 100.07 | 24.766 | 0 | 0 | 0 | 0 | 24.766 | 75.304 | - |
25% August - 2017 |
Work in progress. |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 Km) --- Rs.7.44 m
2) Agra Matwani Road UC Deewana Baba PK-78 (1.50 Km) --- Rs.15.48 m
3) Topai Bakaar Road UC Chagarzai PK-78 (2.30 Km) --- Rs.21.17 m
4) Shalizara Road UC Norizi PK-78 (1.525 Km) --- Rs.19353 m
5) Cheena/Chanar Dund Barkalay Road UC Norizi PK-78 (2.275 Km) -- Rs.16.85 m
6) Shalbandi Bakhsha Hujra Road UC Shalbandi PK-78 (1.30 Km) --- Rs.10.30 m
7) Krapa Maizari Road UC Gagra PK-78 (1 Km) --- Rs.9.30 m | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Buner |
- | - | - | 08-10-15 | - | 100.07 | 24.766 | 0 | 0 | 0 | 0 | 24.766 | 75.304 | - |
25% July - 2017 |
Work in progress. |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 Km) --- Rs.7.44 m
2) Agra Matwani Road UC Deewana Baba PK-78 (1.50 Km) --- Rs.15.48 m
3) Topai Bakaar Road UC Chagarzai PK-78 (2.30 Km) --- Rs.21.17 m
4) Shalizara Road UC Norizi PK-78 (1.525 Km) --- Rs.19353 m
5) Cheena/Chanar Dund Barkalay Road UC Norizi PK-78 (2.275 Km) -- Rs.16.85 m
6) Shalbandi Bakhsha Hujra Road UC Shalbandi PK-78 (1.30 Km) --- Rs.10.30 m
7) Krapa Maizari Road UC Gagra PK-78 (1 Km) --- Rs.9.30 m | |||||||||||||||||||
844 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 24.766 | 0 | 0 | 0 | 0 | 24.766 | 75.304 | - |
25% November - 2017 |
Work in progress. |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 Km) --- Rs.7.44 m
2) Agra Matwani Road UC Deewana Baba PK-78 (1.50 Km) --- Rs.15.48 m
3) Topai Bakaar Road UC Chagarzai PK-78 (2.30 Km) --- Rs.21.17 m
4) Shalizara Road UC Norizi PK-78 (1.525 Km) --- Rs.19353 m
5) Cheena/Chanar Dund Barkalay Road UC Norizi PK-78 (2.275 Km) -- Rs.16.85 m
6) Shalbandi Bakhsha Hujra Road UC Shalbandi PK-78 (1.30 Km) --- Rs.10.30 m
7) Krapa Maizari Road UC Gagra PK-78 (1 Km) --- Rs.9.30 m | |||||||||||||||||||