Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
10-02-15 | - | - | 04-01-17 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% December - 2017 |
Completed. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
10-02-15 | - | - | 04-01-17 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% September - 2017 |
Completed & H/O. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
10-02-15 | - | - | 04-01-17 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% August - 2017 |
Completed. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
10-02-15 | - | - | 04-01-17 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% July - 2017 |
Completed. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% November - 2017 |
Completed. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% October - 2017 |
Completed. |
No Image |
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% June - 2018 |
Completed & H/O. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% May - 2018 |
Completed & H/O. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% April - 2018 |
Completed & H/O. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% March - 2018 |
Completed & H/O. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% February - 2018 |
Completed & H/O. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 20 | 19.521 | 0 | 0 | 0 | 0 | 19.521 | 0.479 | - |
98% January - 2018 |
Completed. |
No Image |
Abbottabad | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
- | - | - | 04-01-17 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- December - 2017 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
- | - | - | 04-01-17 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- September - 2017 |
Site not identified. |
No Image |
District Public Prosecutor offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
- | - | - | 04-01-17 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- August - 2017 |
Site not identified. |
No Image |
District Public Prosecutor offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
- | - | - | 04-01-17 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- July - 2017 |
Site not identified. |
No Image |
District Public Prosecutor offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- November - 2017 |
Site not identified. |
No Image |
District Public Prosecutor offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- October - 2017 |
Site not identified. |
No Image |
District Public Prosecutor offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- June - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- May - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- April - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- March - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- February - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.22 | 0 | 0 | 0 | 0 | 0 | 0 | 24.22 | - |
- January - 2018 |
Site not identified. |
No Image |
Construction of District Public Prosecutor Offices in District Bannu | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
12-02-15 | - | - | 04-01-17 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% December - 2017 |
Completed & H/O. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
12-02-15 | - | - | 04-01-17 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% September - 2017 |
Completed. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
12-02-15 | - | - | 04-01-17 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% August - 2017 |
Completed. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
12-02-15 | - | - | 04-01-17 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% July - 2017 |
Completed. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% November - 2017 |
Completed & H/O. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% October - 2017 |
Completed & H/O. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% June - 2018 |
Completed & H/O. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% May - 2018 |
Completed & H/O. Demand Rs.2.500 m to clear liability of contractor. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% April - 2018 |
Completed & H/O. Demand Rs.2.500 m to clear liability of contractor. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% March - 2018 |
Completed & H/O. Demand Rs.2.5 m to clear liability of contractor. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% February - 2018 |
Completed & H/O. Demand Rs.2.5 m to clear liability of contractor. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 22.779 | 18.825 | 0 | 0 | 0 | 0 | 18.825 | 3.954 | - |
83% January - 2018 |
Completed & H/O. Demand Rs. 2.5 M to clear libility of contractor. |
No Image |
District Battagram | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
05-10-14 | - | - | 04-01-17 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% December - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
05-10-14 | - | - | 04-01-17 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% September - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
05-10-14 | - | - | 04-01-17 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% August - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
05-10-14 | - | - | 04-01-17 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% July - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% November - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% October - 2017 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% June - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% May - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% April - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% March - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% February - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 24.066 | 21.123 | 0 | 0 | 0 | 0 | 21.123 | 2.943 | - |
88% January - 2018 |
Completed. |
No Image |
Construction of District Public Prosecutor office in District Buner PK-79 | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Charsadda |
02-02-15 | - | - | 04-01-17 | - | 24 | 19.299 | 0 | 0 | 0 | 0 | 19.299 | 4.701 | - |
80% December - 2017 |
Completed. |
No Image |
Govt Pleader office Charsadda | |||||||||||||||||||
792 (OG) |
110454-Directorate of Human Rights and its District based Resource Centres with Integrated Facilities for Public Prosecutors, Government Pleaders and Probation Officers, Government of Khyber Pakhtunkhwa (INL Assisted). |
Charsadda |
02-02-15 | - | - | 04-01-17 | - | 24 | 19.299 | 0 | 0 | 0 | 0 | 19.299 | 4.701 | - |
80% September - 2017 |
Completed. |
No Image |
Govt Pleader office Charsadda | |||||||||||||||||||
Pages : 1 2 3 4 5 6 7 |