Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, February - 2021, February - 2018, March - 2021, March - 2018, April - 2021, April - 2018, May - 2021, May - 2018, June - 2018, July - 2017, July - 2020, August - 2017, August - 2020, September - 2017, September - 2020, October - 2017, October - 2020, November - 2017, December - 2020, December - 2017,

Showing Page Number : 1 of 6

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
01-05-16 30-06-18 - 21-05-15 - 49.04 19.469 28.92 28.92 21.69 21.69 41.159 0.651 99% 84%
December - 2017
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
01-05-16 30-06-18 - 21-05-15 - 49.04 19.469 28.92 28.92 14.46 14.46 33.929 0.651 99% 69%
September - 2017
Length 32 mtr - pile cap competed, deck slab in progress.
No Image
PK-46
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
01-05-16 30-06-18 - 21-05-15 - 49.04 19.469 28.92 28.92 14.46 10.267 29.736 0.651 99% 61%
August - 2017
Length 32 mtr - pile cap in progress.
No Image
PK-46
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
01-05-16 30-06-18 - 21-05-15 - 49.04 19.469 28.92 28.92 10.267 0 19.469 0.651 99% 40%
July - 2017
Length 32 mtr - pile cap in progress.
No Image
PK-46
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
December - 2020
16/16 units completed.
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
December - 2020
16/16 units completed.
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.469 28.92 28.92 21.69 17.282 36.751 0.651 99% 75%
November - 2017
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.469 28.92 28.92 14.46 14.46 33.929 0.651 99% 69%
October - 2017
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 0 0 0 0 0 0 74.977 - -
October - 2020
16/16 units completed.
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 0 0 0 0 0 0 74.977 - -
September - 2020
16/16 units completed.
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.786 0 0 0 0 0 0 81.786 - -
August - 2020
7 units - 7 completed,
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 81.786 0 0 0 0 0 0 81.786 - -
July - 2020
7 units - 7 completed,
No Image
1) Package-1 UC Dolola
(a) Doze
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 25.175 25.175 25.175 44.545 0.75 98% 91%
June - 2018
Length 32 mtr - Completed.
No Image
PK-46, Abbottabad
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 28.92 28.92 25.175 44.545 0.75 98% 91%
May - 2018
Length 32 mtr - Completed.
No Image
PK-46, Abbottabad
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
May - 2021
16/16 units completed.
No Image
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
 
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 28.92 28.92 25.175 44.545 0.75 98% 91%
April - 2018
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46, Abbottabad
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
April - 2021
16/16 units completed.
No Image
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
 
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 28.92 28.92 21.69 41.06 0.75 98% 84%
March - 2018
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46, Abbottabad
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
March - 2021
16/16 units completed.
No Image
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
 
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.37 28.92 28.92 21.69 21.69 41.06 0.75 98% 84%
February - 2018
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46, Abbottabad
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
February - 2021
16/16 units completed.
No Image
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
 
1192
(OG)
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad.
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 49.04 19.469 28.92 28.92 21.69 21.69 41.159 0.651 99% 84%
January - 2018
Length 32 mtr - pile cap completed, deck slab in progress.
No Image
PK-46
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 74.977 70.789 0 0 0 0 70.789 4.188 - 94%
January - 2021
16/16 units completed.
No Image
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
 
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 10 10 10 0 46.149 37.835 60% 49%
December - 2020
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 10 10 10 0 46.149 37.835 60% 49%
December - 2020
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 0 0 0 0 0 0 93.984 - -
October - 2020
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 0 0 0 0 0 0 93.984 - -
September - 2020
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 0 0 0 0 0 0 93.984 - -
August - 2020
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 0 0 0 0 0 0 93.984 - -
July - 2020
7 components - 2 completed, 4 earth work in progre
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 28 28 28 12 58.149 19.835 79% 62%
March - 2021
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 10 10 10 0 46.149 37.835 60% 49%
February - 2021
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 10 10 10 0 46.149 37.835 60% 49%
January - 2021
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 28 28 28 12.509 58.658 19.835 79% 62%
May - 2021
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 93.984 46.149 28 28 28 12.509 58.658 19.835 79% 62%
April - 2021
7 components - 2 completed, 4 earth work in progress
No Image
1) Construction/rehabilitation of Jehangir La
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 0 0 0 0 33.323 7.047 - 83%
December - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 0 0 0 0 33.323 7.047 - 83%
December - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 0 0 0 0 0 0 40.37 - -
October - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 0 0 0 0 0 0 40.37 - -
September - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 0 0 0 0 0 0 40.37 - -
August - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 0 0 0 0 0 0 40.37 - -
July - 2020
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 36.323 3.429 3.429 3.429 1.935 38.258 0.618 98% 95%
May - 2021
06- Units All Scheme Completed
No Image
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 3.429 3.429 3.429 1.935 35.258 3.618 91% 87%
April - 2021
06 units - all Completed
No Image
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 0 0 0 0 33.323 7.047 - 83%
March - 2021
06 units - all Completed
No Image
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 0 0 0 0 33.323 7.047 - 83%
February - 2021
06 units - all Completed
No Image
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Battagram
30-11--1 30-11--1 - 30-11--1 - 40.37 33.323 0 0 0 0 33.323 7.047 - 83%
January - 2021
Completed (6 units).
No Image
1) Road Seri Shehzada road PK-59
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Buner
30-11--1 30-11--1 - 30-11--1 - 100.07 0 0 0 0 0 0 100.07 - -
October - 2020
80% work completed (7 units).
No Image
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Buner
30-11--1 30-11--1 - 30-11--1 - 100.07 0 0 0 0 0 0 100.07 - -
September - 2020
80% work completed (7 units).
No Image
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Buner
30-11--1 30-11--1 - 30-11--1 - 100.07 0 0 0 0 0 0 100.07 - -
August - 2020
80% work completed (7 units).
No Image
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Buner
30-11--1 30-11--1 - 30-11--1 - 100.07 0 0 0 0 0 0 100.07 - -
July - 2020
80% work completed (7 units).
No Image
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K
1192
(OG)
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis)
Buner
30-11--1 30-11--1 - 30-11--1 - 100.07 82.251 0 0 0 0 82.251 17.819 - 82%
April - 2021
07 units 04 completed 03 Non availibility of funds work stopped Demand Rs: 10 M
No Image
  1. Improvement, Extension and Black Topping of Shalbandai Bakhsha hujra road U/C Shalbandai PK-21 1.30-Km
  2. Improvement, Extension and Black Topping of Krapa Maizari road U/C Gagra PK-21 1-Km
  3. Improvement, Extension and Black Topping of Kalpani Biam Dara road U/C Gagra PK-21 1-Km
  4. Improvement, Extension and Black Topping of Arga Matwani road U/C Dewana Baba PK-21 1.50-Km
  5. Improvement, Extension and Black Topping of Cheena/ Chanar Dund Barkalay road  U/C Norizi PK-21  2.275-Km
  6. Improvement, Extension and Black Topping of Topai Bakaar road  U/C Chagharzi PK-21  2.30-Km
  7. Improvement, Extension and Black Topping of Shalizara road U/C Norizi PK-21 1.525-Km
 
Pages : 1 2 3 4 5 6