Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
01-05-16 | 30-06-18 | - | 21-05-15 | - | 49.04 | 19.469 | 28.92 | 28.92 | 21.69 | 21.69 | 41.159 | 0.651 | 99% |
84% December - 2017 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
01-05-16 | 30-06-18 | - | 21-05-15 | - | 49.04 | 19.469 | 28.92 | 28.92 | 14.46 | 14.46 | 33.929 | 0.651 | 99% |
69% September - 2017 |
Length 32 mtr - pile cap competed, deck slab in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
01-05-16 | 30-06-18 | - | 21-05-15 | - | 49.04 | 19.469 | 28.92 | 28.92 | 14.46 | 10.267 | 29.736 | 0.651 | 99% |
61% August - 2017 |
Length 32 mtr - pile cap in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
01-05-16 | 30-06-18 | - | 21-05-15 | - | 49.04 | 19.469 | 28.92 | 28.92 | 10.267 | 0 | 19.469 | 0.651 | 99% |
40% July - 2017 |
Length 32 mtr - pile cap in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% December - 2020 |
16/16 units completed. |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% December - 2020 |
16/16 units completed. |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.469 | 28.92 | 28.92 | 21.69 | 17.282 | 36.751 | 0.651 | 99% |
75% November - 2017 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.469 | 28.92 | 28.92 | 14.46 | 14.46 | 33.929 | 0.651 | 99% |
69% October - 2017 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 0 | 0 | 0 | 0 | 0 | 0 | 74.977 | - |
- October - 2020 |
16/16 units completed. |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 0 | 0 | 0 | 0 | 0 | 0 | 74.977 | - |
- September - 2020 |
16/16 units completed. |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 0 | 0 | 0 | 0 | 0 | 0 | 81.786 | - |
- August - 2020 |
7 units - 7 completed, |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 81.786 | 0 | 0 | 0 | 0 | 0 | 0 | 81.786 | - |
- July - 2020 |
7 units - 7 completed, |
No Image |
1) Package-1 UC Dolola
(a) Doze | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.37 | 28.92 | 25.175 | 25.175 | 25.175 | 44.545 | 0.75 | 98% |
91% June - 2018 |
Length 32 mtr - Completed. |
No Image |
PK-46, Abbottabad | |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.37 | 28.92 | 28.92 | 28.92 | 25.175 | 44.545 | 0.75 | 98% |
91% May - 2018 |
Length 32 mtr - Completed. |
No Image |
PK-46, Abbottabad | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% May - 2021 |
16/16 units completed. |
No Image |
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
| |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.37 | 28.92 | 28.92 | 28.92 | 25.175 | 44.545 | 0.75 | 98% |
91% April - 2018 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46, Abbottabad | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% April - 2021 |
16/16 units completed. |
No Image |
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
| |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.37 | 28.92 | 28.92 | 28.92 | 21.69 | 41.06 | 0.75 | 98% |
84% March - 2018 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46, Abbottabad | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% March - 2021 |
16/16 units completed. |
No Image |
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
| |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.37 | 28.92 | 28.92 | 21.69 | 21.69 | 41.06 | 0.75 | 98% |
84% February - 2018 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46, Abbottabad | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% February - 2021 |
16/16 units completed. |
No Image |
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
| |||||||||||||||||||
1192 (OG) |
140882-F/S, Design and Construction of Bridge Bari Naichan Mangal, Abbottabad. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 49.04 | 19.469 | 28.92 | 28.92 | 21.69 | 21.69 | 41.159 | 0.651 | 99% |
84% January - 2018 |
Length 32 mtr - pile cap completed, deck slab in progress. |
No Image |
PK-46 | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 74.977 | 70.789 | 0 | 0 | 0 | 0 | 70.789 | 4.188 | - |
94% January - 2021 |
16/16 units completed. |
No Image |
1 PCC road banda batang to Banda Golra
2 Reh: of PCC road Jhangi Khoja
3 Const: of PCC Road KKH to Ghori Laigha
4 Rehab: of Jhangi Syedan Road
5 Const: of PCC road Islamia Par to Gohar Ayub Town
6 Const: of PCC road Gogree Battang Maira form Mangla Police station to Masjid Awais
7 PCC & Culvert, R/wall form Meira Phangla to Khattak Meira
8 Package I U/C Dolola
9 Package 2 U/C Boi
10 Package 3 U/C Kuckmang
11 Package 4 U/C Pattan
12 Package 5 U/C Pluck
13 Package 6 U/C Bakot
14 Package 7 U/C Berote
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 10 | 10 | 10 | 0 | 46.149 | 37.835 | 60% |
49% December - 2020 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 10 | 10 | 10 | 0 | 46.149 | 37.835 | 60% |
49% December - 2020 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 0 | 0 | 0 | 0 | 0 | 0 | 93.984 | - |
- October - 2020 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 0 | 0 | 0 | 0 | 0 | 0 | 93.984 | - |
- September - 2020 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 0 | 0 | 0 | 0 | 0 | 0 | 93.984 | - |
- August - 2020 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 0 | 0 | 0 | 0 | 0 | 0 | 93.984 | - |
- July - 2020 |
7 components - 2 completed, 4 earth work in progre |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 28 | 28 | 28 | 12 | 58.149 | 19.835 | 79% |
62% March - 2021 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 10 | 10 | 10 | 0 | 46.149 | 37.835 | 60% |
49% February - 2021 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 10 | 10 | 10 | 0 | 46.149 | 37.835 | 60% |
49% January - 2021 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 28 | 28 | 28 | 12.509 | 58.658 | 19.835 | 79% |
62% May - 2021 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Bannu HW |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.984 | 46.149 | 28 | 28 | 28 | 12.509 | 58.658 | 19.835 | 79% |
62% April - 2021 |
7 components - 2 completed, 4 earth work in progress |
No Image |
1) Construction/rehabilitation of Jehangir La | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 0 | 0 | 0 | 0 | 33.323 | 7.047 | - |
83% December - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 0 | 0 | 0 | 0 | 33.323 | 7.047 | - |
83% December - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 0 | 0 | 0 | 0 | 0 | 0 | 40.37 | - |
- October - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 0 | 0 | 0 | 0 | 0 | 0 | 40.37 | - |
- September - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 0 | 0 | 0 | 0 | 0 | 0 | 40.37 | - |
- August - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 0 | 0 | 0 | 0 | 0 | 0 | 40.37 | - |
- July - 2020 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 36.323 | 3.429 | 3.429 | 3.429 | 1.935 | 38.258 | 0.618 | 98% |
95% May - 2021 |
06- Units
All Scheme Completed |
No Image |
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 3.429 | 3.429 | 3.429 | 1.935 | 35.258 | 3.618 | 91% |
87% April - 2021 |
06 units - all Completed |
No Image |
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 0 | 0 | 0 | 0 | 33.323 | 7.047 | - |
83% March - 2021 |
06 units - all Completed |
No Image |
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 0 | 0 | 0 | 0 | 33.323 | 7.047 | - |
83% February - 2021 |
06 units - all Completed |
No Image |
1 Road Seri Shehzada road PK-59
2 PCC Road Dheri Jangeer Khan
3 PCC Ghado Road
4 PCC Gate Seri Road
5 PCC Joz Road
6 PCC Road Shalghary | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 40.37 | 33.323 | 0 | 0 | 0 | 0 | 33.323 | 7.047 | - |
83% January - 2021 |
Completed (6 units). |
No Image |
1) Road Seri Shehzada road PK-59
| |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 0 | 0 | 0 | 0 | 0 | 0 | 100.07 | - |
- October - 2020 |
80% work completed (7 units). |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 0 | 0 | 0 | 0 | 0 | 0 | 100.07 | - |
- September - 2020 |
80% work completed (7 units). |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 0 | 0 | 0 | 0 | 0 | 0 | 100.07 | - |
- August - 2020 |
80% work completed (7 units). |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 0 | 0 | 0 | 0 | 0 | 0 | 100.07 | - |
- July - 2020 |
80% work completed (7 units). |
No Image |
1) Kalpani Biam Dara Road UC Gagra PK-78 (1 K | |||||||||||||||||||
1192 (OG) |
140345-Rehabilitation of Rural Roads in Selected Districts of Khyber Pakhtunkhwa (on need basis) |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 100.07 | 82.251 | 0 | 0 | 0 | 0 | 82.251 | 17.819 | - |
82% April - 2021 |
07 units
04 completed
03 Non availibility of funds work stopped
Demand Rs: 10 M |
No Image |
| |||||||||||||||||||
Pages : 1 2 3 4 5 6 |