Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 0 | 0 | 0 | 0 | 24 | 12.386 | - |
66% December - 2018 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Work started |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 0 | 0 | 0 | 0 | 24 | 12.386 | - |
66% November - 2018 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Work started |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 0 | 0 | 0 | 0 | 24 | 12.386 | - |
66% November - 2018 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Work started |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 7.5 | 7.5 | 7.5 | 4.565 | 28.565 | 4.886 | 87% |
79% April - 2019 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Finishing in progress. |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 7.5 | 7.5 | 7.5 | 4.565 | 28.565 | 4.886 | 87% |
79% March - 2019 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Finishing in progress. |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 7.5 | 7.5 | 7.5 | 4.565 | 28.565 | 4.886 | 87% |
79% March - 2019 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Finishing in progress. |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 7.5 | 7.5 | 7.5 | 4.565 | 28.565 | 4.886 | 87% |
79% February - 2019 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Finishing in progress. |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 36.386 | 24 | 0 | 0 | 0 | 0 | 24 | 12.386 | - |
66% January - 2019 |
3 units - completed (Havelian). Work order issued for Mandian (principal unwilling to H/O site). Dhamtour - Work started |
No Image |
1) Havelian
2) PG at Mandian
3) PG at Dhamtour (school level) | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% December - 2018 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% November - 2018 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% November - 2018 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% April - 2019 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% March - 2019 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% March - 2019 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% February - 2019 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 82.286 | 30 | 0 | 0 | 0 | 0 | 30 | 52.286 | - |
36% January - 2019 |
Completed & H/O (Domel & Lalozai), site dispute (Baka Khel). |
No Image |
1) PG at Domel
2) PG at Lalozai ? AA cost Rs.15 m
3) PG at Tehsil Bakka Khel PK-72 Bannu | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% December - 2018 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% November - 2018 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% November - 2018 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% April - 2019 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% March - 2019 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% March - 2019 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% February - 2019 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 30 | 15 | 0 | 0 | 0 | 0 | 15 | 15 | - |
50% January - 2019 |
PG Battagram - land not yet handed over. PG Allai - completed & H/O. |
No Image |
1) Battagram
2) Allai | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.264 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 44.952 | - |
24% December - 2018 |
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progress (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.264 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 44.952 | - |
24% November - 2018 |
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progress (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.264 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 44.952 | - |
24% November - 2018 |
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progress (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.28 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 82.968 | - |
15% April - 2019 |
Out of 4 units, PG Khadu Khail - work order issued, site not available.
PG Mandar - finishing in progress (court case on land).
PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar.
PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Revised DCE submitted for scope change. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
| |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.28 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 82.968 | - |
15% March - 2019 |
Out of 4 units, PG Khadu Khail - work order issued, site not available.
PG Mandar - finishing in progress (court case on land).
PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar.
PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Revised DCE submitted for scope change. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
| |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.28 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 82.968 | - |
15% March - 2019 |
Out of 4 units, PG Khadu Khail - work order issued, site not available.
PG Mandar - finishing in progress (court case on land).
PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar.
PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Revised DCE submitted for scope change. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
| |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 97.28 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 82.968 | - |
15% February - 2019 |
Out of 4 units, PG Khadu Khail - work order issued, site not available.
PG Mandar - finishing in progress (court case on land).
PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar.
PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Revised DCE submitted for scope change |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
| |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Buner |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59.264 | 14.312 | 0 | 0 | 0 | 0 | 14.312 | 44.952 | - |
24% January - 2019 |
Out of 4 units, PG Khadu Khail - work order issued, site not available. PG Mandar - finishing in progress (court case on land). PG at GDC Daggar - work order issued, site not yet handed over by Principal GDC Dagar. PG at GHS Gagra submitted to DSO Buner. Conditionally approved. Summary under process for cost enhancement. |
No Image |
1) PG Khadukhail
2) PG Mandanr
3) PG at GHS Gagra
4) PG at GDC Daggar
5) Tehsil level PG at Gagra Buner | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% December - 2018 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% November - 2018 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% November - 2018 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% April - 2019 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% March - 2019 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% March - 2019 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% February - 2019 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 45 | 43.05 | 0 | 0 | 0 | 0 | 43.05 | 1.95 | - |
96% January - 2019 |
Completed & H/O (4 units). |
No Image |
1) PG at Tangi
2) PG at Attakay Shabqadar
3) PG at GCMHS Turangzai
4) PG at GHS Muslim Abad Shakoor | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 0 | 0 | 0 | 0 | 30 | 1.211 | - |
96% December - 2018 |
PG Gahli Booni - completed. PG Chitral - Revised scope in progress. |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 0 | 0 | 0 | 0 | 30 | 1.211 | - |
96% November - 2018 |
PG Gahli Booni - completed. PG Chitral - Revised scope in progress. |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 0 | 0 | 0 | 0 | 30 | 1.211 | - |
96% November - 2018 |
PG Gahli Booni - completed. PG Chitral - Revised scope in progress. |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 3 | 3 | 3 | 0 | 30 | 0 | 100% |
96% April - 2019 |
PG Gahli Booni - completed. PG Chitral - finishing |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 3 | 3 | 3 | 0 | 30 | 0 | 100% |
96% March - 2019 |
PG Gahli Booni - completed. PG Chitral - finishing |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 3 | 3 | 3 | 0 | 30 | 0 | 100% |
96% March - 2019 |
PG Gahli Booni - completed. PG Chitral - finishing |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 3 | 3 | 3 | 0 | 30 | 0 | 100% |
96% February - 2019 |
PG Gahli Booni - completed. PG Chitral - finishing |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 31.211 | 30 | 3 | 3 | 3 | 0 | 30 | 0 | 100% |
96% January - 2019 |
PG Gahli Booni - completed. PG Chitral - Revised scope in progress. |
No Image |
1) PG Gahli Booni
2) PG Syed Abad Chitral | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.69 | 65.739 | 5 | 5 | 5 | 5 | 70.739 | 22.951 | 76% |
76% December - 2018 |
Out of 9 units, Kulachi, Daraban and Paroa, GHSS No. 2 Islamia , GGHS Kachi Mali Khel - completed & H/O.
PG tehsil Pharpur at panyal - complted.
Pg Tehsil Pharpur- stay order issued.
2 units work in progress. |
No Image |
1) Kulachi PK-67
2) Daraban PK-67
3) Paroa PK-66
4) Paharpur PK-68
5) GHSS No.2 Islamia DI.Khan PK-64
6) GGHS Kacha Mali Khel Paharpur PK-64
7) GMS No.1 Daraban Kalan PK-67 shifted to GHS Takwara
8) Tehsil level PG at Panyala Tehsil Paharpur | |||||||||||||||||||
1116 (OG) |
130061-Establishment of Playgrounds in Khyber Pakhtunkhwa on need basis. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 93.69 | 65.739 | 5 | 5 | 5 | 0 | 65.739 | 22.951 | 76% |
70% November - 2018 |
Out of 7 units, Kulachi, Daraban and Paroa - completed & H/O. GMS Mali Khel and GGHS Islamia completed. Paharpur and GMS Darban - stay order by PHC, work stopped. |
No Image |
1) Kulachi PK-67
2) Daraban PK-67
3) Paroa PK-66
4) Paharpur PK-68
5) GHSS No.2 Islamia DI.Khan PK-64
6) GGHS Kacha Mali Khel Paharpur PK-64
7) GMS No.1 Daraban Kalan PK-67 shifted to GHS Takwara
8) Tehsil level PG at Panyala Tehsil Paharpur | |||||||||||||||||||
Pages : 1 2 3 4 5 6 |