Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, February - 2021, March - 2021, April - 2021, May - 2021, July - 2020, August - 2020, September - 2020, October - 2020, December - 2020,

Showing Page Number : 1 of 5

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 4 4 4 4 20.807 26.943 44% 44%
December - 2020
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 4 4 4 4 20.807 26.943 44% 44%
December - 2020
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 0.5 0.5 0.5 0.5 17.307 30.443 36% 36%
October - 2020
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 0 0.5 0.5 0.5 0.5 0.5 47.25 1% 1%
September - 2020
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 0 0.5 0.5 0.5 0.5 0.5 47.25 1% 1%
August - 2020
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 0 0 0 0 0 0 47.75 - -
July - 2020
Work started (2 units). Liability 15 m
No Image
1) Construcation of Bridgw Tandian U/C Beeran
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 7 7 7 7 23.807 23.943 50% 50%
March - 2021
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
 
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 7 7 7 7 23.807 23.943 50% 50%
February - 2021
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
 
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 4 4 4 4 20.807 26.943 44% 44%
January - 2021
Work started (2 units). Liability 15 M
No Image
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
 
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 7 7 7 7 23.807 23.943 50% 50%
May - 2021
Work started (2 units).
No Image
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
 
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Abbottabad
HW
30-11--1 30-11--1 - 30-11--1 - 47.75 16.807 7 7 7 7 23.807 23.943 50% 50%
April - 2021
Work started (2 units).
No Image
1) Construcation of Bridgw Tandian U/C Beerangali
2 PCC link tora at kharaki, daana darban, totan to mundrian, danna noral primary school to onward tehari danna langril...
3 Bakot Khan Kalan to Langa Loot 1.50 KM
4 Rehab: of Riyal road
 
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
December - 2020
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
December - 2020
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
October - 2020
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
September - 2020
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0 0 50.45 1% -
August - 2020
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0 0 0 0 0 50.95 - -
July - 2020
Bridge- Piles conc: completed.
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
March - 2021
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel Bharat Bannu
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
February - 2021
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel Bharat Bannu
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
January - 2021
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
May - 2021
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel Bharat Bannu
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Bannu
HW
30-11--1 30-11--1 - 30-11--1 - 50.95 0 0.5 0.5 0.5 0.5 0.5 50.45 1% 1%
April - 2021
Bridge- Piles completed. Demand Rs. 20 M
No Image
Main Kacha road to village Bazida Kokal Khel Bharat Bannu
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0.5 0.5 0.5 0 0 49.5 1% -
December - 2020
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0.5 0.5 0.5 0 0 49.5 1% -
December - 2020
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0.5 0.5 0.5 0.5 0.5 49.5 1% 1%
October - 2020
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0.5 0.5 0.5 0 0 49.5 1% -
September - 2020
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0.5 0.5 0.5 0 0 49.5 1% -
August - 2020
Work order issued. Demand Rs. 30 M
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 0 0 0 0 0 50 - -
July - 2020
Work order issued.
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
May - 2021
Demand Rs. 30 M?.. 5 units , Earth work completed.. Demand Rs. 20 M
No Image
1 Gnatar Road (1 KM)
2 Gangwal Road (1 KM)
3 Bateela Road (1 KM)
4 Pashto Road (1 KM)
5 Jambera Road (1 KM)
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
April - 2021
Demand Rs. 30 M?.. 5 units , Earth work completed.. Demand Rs. 20 M
No Image
1 Gnatar Road (1 KM)
2 Gangwal Road (1 KM)
3 Bateela Road (1 KM)
4 Pashto Road (1 KM)
5 Jambera Road (1 KM)
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
March - 2021
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1 Gnatar Road (1 KM)
2 Gangwal Road (1 KM)
3 Bateela Road (1 KM)
4 Pashto Road (1 KM)
5 Jambera Road (1 KM)
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
February - 2021
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1 Gnatar Road (1 KM)
2 Gangwal Road (1 KM)
3 Bateela Road (1 KM)
4 Pashto Road (1 KM)
5 Jambera Road (1 KM)
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Battagram
30-11--1 30-11--1 - 30-11--1 - 50 0 2 2 2 2 2 48 4% 4%
January - 2021
Work order issued. Demand Rs. 30 M?.. 5 units , Earth work completed..
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 2.5 2.5 2.5 0.767 0.767 54.04 4% 1%
December - 2020
Work in Progress Deamnd Rs. 30 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 2.5 2.5 2.5 0.767 0.767 54.04 4% 1%
December - 2020
Work in Progress Deamnd Rs. 30 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 0.5 0.5 0.5 0.5 0.5 56.04 1% 1%
October - 2020
Work in Progress Deamnd Rs. 30 M
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 0.5 0.5 0.5 0 0 56.04 1% -
September - 2020
Work in Progress Deamnd Rs. 30 M
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 0.5 0.5 0.5 0 0 56.04 1% -
August - 2020
Work in Progress Deamnd Rs. 30 M
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 0 0 0 0 0 56.54 - -
July - 2020
Work order issued. Demand Rs. 6.5 M (focal person)
No Image
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 3 3 3 2.5 2.5 53.54 5% 4%
March - 2021
Work in Progress Deamnd Rs. 20 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 3 3 3 3 3 53.54 5% 5%
February - 2021
Work in Progress Deamnd Rs. 20 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
30-11--1 30-11--1 - 30-11--1 - 56.54 0 3 3 3 2.5 2.5 53.54 5% 4%
January - 2021
Work in Progress Deamnd Rs. 30 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
HW
30-11--1 30-11--1 - 30-11--1 - 56.54 0 3 3 3 3 3 53.54 5% 5%
May - 2021
Work in Progress Deamnd Rs. 20 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
Charsadda
HW
30-11--1 30-11--1 - 30-11--1 - 56.54 0 2.5 2.5 2.5 2.5 2.5 54.04 4% 4%
April - 2021
Work in Progress Deamnd Rs. 20 M
No Image
A. i. Rehab:/Imp: of road Pir Qilla Michani Road to Main Killi.?. Rs: 6.548 M
B.
1. Const: of PCC road at U/C Hasanzai? Rs: 10.010 M
2. Const: of PCC road at U/C Matta ? Rs: 9.897 M
3. Const: of PCC road at U/C MC-I Shabqadar ? Rs: 5.003  M
4. Const: of PCC road at U/C Rahakai ? Rs: 5.050 M
5. Const: of PCC road at U/C Katozai ? Rs: 10.00 M
6. Const: of PCC road at U/C Panjpao? Rs: 10.002 M
 
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 1.5 1.5 1.5 1.5 1.5 84.173 2% 2%
December - 2020
(14 Units) 08- Units completed 06- units in progress Demand 68 m for completion scheme.
No Image
Improvement/rehabilitation of various roads i
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 1.5 1.5 1.5 1.5 1.5 84.173 2% 2%
December - 2020
(14 Units) 08- Units completed 06- units in progress Demand 68 m for completion scheme.
No Image
Improvement/rehabilitation of various roads i
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 0.5 0.5 0.5 0.5 0.5 85.173 1% 1%
October - 2020
Length 5 km- (10 Units) 1.5 Km completed. Demand 68 m for completion scheme.
No Image
Improvement/rehabilitation of various roads i
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 0.5 0.5 0.5 0.5 0.5 85.173 1% 1%
September - 2020
Length 5 km- (10 Units) 1.5 Km completed. Demand 68 m for completion scheme.
No Image
Improvement/rehabilitation of various roads i
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 0.5 0.5 0.5 0 0 85.173 1% -
August - 2020
Length 5 km- (10 Units) 1.5 Km completed. Demand 68 m for completion scheme.
No Image
Improvement/rehabilitation of various roads i
1758
(OG)
170585-Construction/ Widening / Rehabilitation / Dualization of C&W Roads in Khyber Pakhtunkhwa
D.I.Khan
HW
30-11--1 30-11--1 - 30-11--1 - 85.673 0 0 0 0 0 0 85.673 - -
July - 2020
Length 5 km- 1.5 Km completed. Demand 68 m for c
No Image
Improvement/rehabilitation of various roads i
Pages : 1 2 3 4 5