Report Date:
September 03, 2025
Infrastructure Type:
Road
Total Damages:
41
Reported by:
Nizam Ud Din
(XEN H/W DIR LOWER)
Engr. Sohail Idrees
(Managing Director PKHA)
Affected Roads
Total Damages
Damaged Length
(KM)
Fully Restored
Partially Restored
Not Restored
Road Damages Overview
S# | Road Name & Location | Total Length | Status | Damaged Length | Damage Coordinates | Date Reported |
---|---|---|---|---|---|---|
1
|
Dooda Talash Road
No coordinates available
|
2
(KM) |
Partially restored |
0.5
(KM) |
No damage coordinates |
Aug 19, 2025
09:36 AM |
2
|
Kakas Road
No coordinates available
|
1
(KM) |
Partially restored |
0.5
(KM) |
Aug 18, 2025
05:19 PM |
|
3
|
Dal Maskiny Road
No coordinates available
|
1
(KM) |
Partially restored |
0.5
(KM) |
Aug 18, 2025
05:16 PM |
|
4
|
PCC Link Road Markhani
No coordinates available
|
1
(KM) |
Partially restored |
1
(KM) |
Aug 18, 2025
04:54 PM |
|
5
|
Qala Manzai Balokhan Road
No coordinates available
|
1
(KM) |
Partially restored |
0.5
(KM) |
No damage coordinates |
Aug 18, 2025
04:24 PM |
6
|
Tangodheri Markhani Maidan Road
No coordinates available
|
2
(KM) |
Partially restored |
1
(KM) |
Aug 18, 2025
11:38 AM |
|
Remarks:
The road surface and PCC shulders has been damaged, fully restored but need rehabilitation for smooth running of traffic.
Reported by:
XEN H/W DIR LOWER
|
||||||
7
|
Dapor Chamiary Road
|
2
(KM) |
Partially restored |
2
(KM) |
Aug 18, 2025
07:43 AM |
|
8
|
Toormang I Main Road
No coordinates available
|
6
(KM) |
Partially restored |
1
(KM) |
Aug 18, 2025
04:49 AM |
|
Remarks:
The road has been cleared for traffic
Reported by:
XEN H/W DIR LOWER
|
||||||
9
|
Lajbook Road
No coordinates available
|
13
(KM) |
Partially restored |
3
(KM) |
Aug 18, 2025
04:36 AM |
|
Remarks:
The road has been cleared for traffic
Reported by:
XEN H/W DIR LOWER
|
||||||
10
|
Sori Paw Maidan
No coordinates available
|
2
(KM) |
Partially restored |
1
(KM) |
Aug 18, 2025
12:19 AM |
|
11
|
Lacha Road
No coordinates available
|
2
(KM) |
Partially restored |
1
(KM) |
Aug 18, 2025
12:16 AM |
|
12
|
Mirza Abad shamshi khan Road
No coordinates available
|
2
(KM) |
Fully restored |
0.5
(KM) |
No damage coordinates |
Aug 17, 2025
03:05 PM |
Remarks:
The road surface and PCC shulders has been damaged, fully restored but need rehabilitation for smooth running of traffic.
Reported by:
XEN H/W DIR LOWER
|
||||||
13
|
Katan Alami Sar Road
No coordinates available
|
1
(KM) |
Fully restored |
0.3
(KM) |
Aug 17, 2025
11:14 AM |
|
Remarks:
The road surface, retaining wall has been damaged, fully restored but need rehabilitation
Reported by:
XEN H/W DIR LOWER
|
||||||
14
|
Anwarabad Anangoro Khwar gul Shah Banda
No coordinates available
|
2
(KM) |
Partially restored |
2
(KM) |
No damage coordinates |
Aug 17, 2025
09:30 AM |
Remarks:
The road has been rushed and surface has been damaged, restoration is in progress but need rehabilitation
Reported by:
XEN H/W DIR LOWER
|
||||||
15
|
Anwar Abad Yaqub korona
No coordinates available
|
1
(KM) |
Partially restored |
0.8
(KM) |
No damage coordinates |
Aug 17, 2025
09:24 AM |
Remarks:
The surface of the road has been washed and damaged fully. Restoration is in progress
Reported by:
XEN H/W DIR LOWER
|
||||||
16
|
Gawardesh Jandool Road
No coordinates available
|
5
(KM) |
Partially restored |
2
(KM) |
Aug 17, 2025
08:01 AM |
|
17
|
Munjai Road
No coordinates available
|
1
(KM) |
Partially restored |
0.4
(KM) |
Aug 16, 2025
01:38 PM |
|
18
|
Timergara Balambat Maidan Kalpani Barawal Road (S4B)
|
53
(KM) |
Fully restored |
3.5
(KM) |
No damage coordinates |
Aug 16, 2025
10:30 AM |
19
|
Khadagzai Badwan Chakdara Road
No coordinates available
|
17
(KM) |
Fully restored |
0.25
(KM) |
No damage coordinates |
Aug 16, 2025
10:14 AM |
20
|
Bishgram main Road Maidan
No coordinates available
|
3
(KM) |
Partially restored |
3
(KM) |
Aug 16, 2025
09:05 AM |
|
Remarks:
The restoration work is in progress
Reported by:
XEN H/W DIR LOWER
|
||||||
21
|
Balokhan Road
No coordinates available
|
3
(KM) |
Partially restored |
1
(KM) |
Aug 16, 2025
08:56 AM |
|
Remarks:
The partial restoration work is in progress
Reported by:
XEN H/W DIR LOWER
|
||||||
22
|
Dabako Main Road Maidan
No coordinates available
|
3
(KM) |
Fully restored |
1
(KM) |
Aug 16, 2025
08:11 AM |
|
Remarks:
The road has been cleared for traffic
Reported by:
XEN H/W DIR LOWER
|
||||||
23
|
Degan Khadagzai Road
No coordinates available
|
1
(KM) |
Partially restored |
0.075
(KM) |
Aug 16, 2025
06:56 AM |
|
24
|
Tangai Chenar Khadagzai Road
No coordinates available
|
1
(KM) |
Partially restored |
0.2
(KM) |
Aug 16, 2025
06:41 AM |
|
25
|
Aselo Road
No coordinates available
|
1
(KM) |
Partially restored |
0.2
(KM) |
Aug 16, 2025
06:21 AM |
|
26
|
Malakand Bala Road
No coordinates available
|
4
(KM) |
Partially restored |
2
(KM) |
No damage coordinates |
Aug 16, 2025
04:47 AM |
27
|
Banda Talash Road
No coordinates available
|
3
(KM) |
Fully restored |
0.8
(KM) |
Aug 16, 2025
04:42 AM |
|
28
|
Chenar Darmdal Shengal Road
No coordinates available
|
1.2
(KM) |
Partially restored |
1
(KM) |
Aug 16, 2025
04:37 AM |
|
29
|
Tawda Chena Road
No coordinates available
|
3
(KM) |
Partially restored |
3
(KM) |
Aug 16, 2025
04:30 AM |
|
30
|
Maidan Bypass from Odigram to Hayaseri Dir Lower
No coordinates available
|
3.5
(KM) |
Fully restored |
1
(KM) |
Aug 15, 2025
02:47 PM |
|
Remarks:
The road is partially restored but rehabilitation needs release of fund
Reported by:
XEN H/W DIR LOWER
|
||||||
31
|
Chakdara Bypass Road
No coordinates available
|
6
(KM) |
Partially restored |
0.2
(KM) |
No damage coordinates |
Aug 15, 2025
02:12 PM |
32
|
Ramyal Road
No coordinates available
|
2
(KM) |
Partially restored |
0.3
(KM) |
No damage coordinates |
Aug 15, 2025
02:09 PM |
33
|
Asbanr Shorshing Road
No coordinates available
|
4
(KM) |
Partially restored |
1
(KM) |
No damage coordinates |
Aug 15, 2025
02:07 PM |
34
|
Ouch Police Station Road
No coordinates available
|
1
(KM) |
Partially restored |
0.6
(KM) |
No damage coordinates |
Aug 15, 2025
12:06 PM |
35
|
Sia Warghar Road
No coordinates available
|
4
(KM) |
Partially restored |
0.4
(KM) |
No damage coordinates |
Aug 15, 2025
12:04 PM |
36
|
Asbanr Main Road
No coordinates available
|
4
(KM) |
Partially restored |
0.5
(KM) |
No damage coordinates |
Aug 15, 2025
12:01 PM |
37
|
Khanpur Teknai Road Chakdara
No coordinates available
|
2
(KM) |
Partially restored |
1.3
(KM) |
No damage coordinates |
Aug 15, 2025
10:16 AM |
Remarks:
The partial restoration work is in progress but rehabilitation needs funds for smooth running of traffic
Reported by:
XEN H/W DIR LOWER
|
||||||
38
|
Zani Main Road UC Gall Dir Lower
No coordinates available
|
10
(KM) |
Partially restored |
0.5
(KM) |
Aug 15, 2025
10:06 AM |
|
Remarks:
This is the main road of Zani Village UC Gall Dir Lower, The partial restoration of road is in progress for emergency traffic but needs funds for rehabilitation.
Reported by:
XEN H/W DIR LOWER
|
||||||
39
|
Koto Odigram Road Dir lower
No coordinates available
|
2
(KM) |
Partially restored |
0.03
(KM) |
Aug 15, 2025
07:31 AM |
|
40
|
Jan Passa Road Dir Lower
No coordinates available
|
5
(KM) |
Partially restored |
0.2
(KM) |
Aug 15, 2025
06:10 AM |
|
Remarks:
The Road is partially restored but rehabilitation need release of fund
Reported by:
XEN H/W DIR LOWER
|
||||||
41
|
Munda Samarbagh Shahi Road
No coordinates available
|
35
(KM) |
Fully restored |
0.5
(KM) |
No damage coordinates |
Jul 06, 2025
08:48 AM |
Remarks:
Slips and debris have been removed
Reported by:
Managing Director PKHA
|