Buner Damages Detail - Monsoon (2025)

Reported by:
Shah Nawaz (XEN BUNER 1) Engr. Sohail Idrees (Managing Director PKHA)
51
Affected Roads
88
Total Damages
104.6575
Damaged Length (KM)
15
Fully Restored
60
Partially Restored
13
Not Restored
Road Damages Overview
S# Road Name & Location Total Length Status Damaged Length Damage Coordinates Date Reported
1
Pir Baba Balo Khan Road District Buner 2
1.00
(KM)
1 Not restored 1
(KM)
Start: 34.598368, 72.452494 View
End: 34.598368, 72.452494 View
Sep 02, 2025
03:18 PM
Remarks: road 3rd time washed away
Reported by: XEN BUNER 1
2 Partially restored 1
(KM)
Start: 34.598368, 72.452494 View
Aug 17, 2025
09:33 PM
2
Mula Banda Saagar village road District Buner
8
(KM)
Not restored 3
(KM)
Start: 34.655186, 72.445446 View
End: 34.655003, 72.445335 View
Sep 02, 2025
03:11 PM
Remarks: Saggar road main sport where cloud burst hit first time
Reported by: XEN BUNER 1
3
Mula Banda road District Buner 2
7
(KM)
1 Not restored 5
(KM)
Start: 34.655186, 72.445446 View
End: 34.655186, 72.445446 View
Sep 02, 2025
02:52 PM
Remarks: road 3rd time washed away
Reported by: XEN BUNER 1
2 Partially restored 0.83
(KM)
No damage coordinates Aug 17, 2025
10:24 PM
4
Elum road District Buner
13
(KM)
Not restored 5
(KM)
Start: 34.586238, 72.391185 View
End: 34.586238, 72.391185 View
Sep 02, 2025
02:40 PM
Remarks: road 3rd time washed away
Reported by: XEN BUNER 1
5
Pir Baba Batai road District Buner
2
(KM)
Not restored 0.3
(KM)
Start: 34.610028, 72.463753 View
End: 34.610028, 72.463753 View
Sep 02, 2025
02:20 PM
Remarks: Pair baba batai road 3rd time washed away on 02-09-2025
Reported by: XEN BUNER 1
6
Shoga to kuz Gokand road District Buner 2
3
(KM)
1 Not restored 1
(KM)
Start: 34.625540, 72.530649 View
End: 34.625594, 72.530702 View
Sep 02, 2025
01:03 PM
Remarks: today report 02-09-2025 road 3rd time washed away
Reported by: XEN BUNER 1
2 Partially restored 0.82
(KM)
Start: 72.530629, 34.625696 View
Aug 17, 2025
10:34 PM
7
Gokand Kot Road District Buner 3
4.5
(KM)
1 Not restored 3.5
(KM)
Start: 34.667904, 72.506300 View
End: 34.679213, 72.503713 View
Sep 02, 2025
12:48 PM
Remarks: Today report. 02-09-2025 The Gokand kot Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has 3rd time rendered the road completely unusable.
Reported by: XEN BUNER 1
2 Partially restored 0.5
(KM)
Start: 34.667966, 72.506318 View
End: 34.670553, 72.503765 View
Aug 30, 2025
11:51 AM
Remarks: Today report. 30-08-2025 The Gokand kot Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has once again rendered the road completely unusable. With the weather still unstable and rainfall continuing.
Reported by: XEN BUNER 1
3 Partially restored 3.5
(KM)
Start: 34.668153, 72.506289 View
Aug 17, 2025
10:47 PM
8
Nizamo to Qadar Nagar Road District Buner 3
2
(KM)
1 Not restored 0.7
(KM)
Start: 34.641345, 72.473629 View
End: 34.639243, 72.471789 View
Sep 02, 2025
12:34 PM
Remarks: Today report. 02-09-2025 The Nizamo to Qadar Nagar Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding 3rd time rendered the road completely unusable
Reported by: XEN BUNER 1
2 Partially restored 0.4
(KM)
Start: 34.639243, 72.471789 View
End: 34.641792, 72.474045 View
Aug 30, 2025
11:13 AM
Remarks: Today report. 30-08-2024 The Batai Qadar Nagar Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has once again rendered the road completely unusable. With the weather still unstable and rainfall continuing. Rehabilitation cost already included previously
Reported by: XEN BUNER 1
3 Partially restored 1.4
(KM)
No damage coordinates Aug 17, 2025
10:20 PM
9
Pir Baba Bypass District Buner 2
3.4
(KM)
1 Not restored 2.5
(KM)
Start: 34.597276, 72.449323 View
End: 34.597276, 72.449323 View
Sep 02, 2025
12:01 PM
Remarks: Today report. 02-09-2025 The Pir baba bayypas road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has 3rd time rendered the road completely unusable.
Reported by: XEN BUNER 1
2 Partially restored 0.75
(KM)
No damage coordinates Aug 17, 2025
10:29 PM
10
Palwari gokand road District Buner
6
(KM)
Not restored 3.5
(KM)
Start: 34.611131, 72.550467 View
End: 34.610045, 72.554221 View
Sep 02, 2025
11:21 AM
Remarks: Today report. 02-09-2025 The Palwarai Gokand Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has 3rd time rendered the road completely unusable.
Reported by: XEN BUNER 1
11
Malak Pur road District Buner 2
3
(KM)
1 Not restored 2.5
(KM)
Start: 34.599251, 72.453542 View
End: 34.598771, 72.453437 View
Sep 02, 2025
09:22 AM
Remarks: Today report. 02-09-2025 The Malak Pure road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has 3rd time rendered the road .
Reported by: XEN BUNER 1
2 Partially restored 3
(KM)
Start: 34.598721, 72.453393 View
Aug 17, 2025
09:10 PM
12
Batai to nizamo road District Buner 2
5
(KM)
1 Not restored 0.3
(KM)
Start: 34.610300, 72.463651 View
End: 34.610296, 72.463691 View
Sep 02, 2025
08:27 AM
Remarks: Today report. 02-09-2025 The Batai Nizamo road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was completed by C&W. However, last night's intense rainfall and flooding has 3rd time again rendered the road completely unusable.
Reported by: XEN BUNER 1
2 Partially restored 0.3
(KM)
Start: 34.609658, 72.463744 View
Aug 17, 2025
09:51 PM
13
Gokand Ghwardara Road District Buner
1
(KM)
Not restored 1
(KM)
Start: 34.609354, 72.548336 View
End: 34.605561, 72.542333 View
Sep 02, 2025
08:11 AM
Remarks: Today report. 02-09-2025 The Gokand Ghwardara due to cloud burst and heavy, However, last night's intense rainfall and flooding rendered the road completely unusable.
Reported by: XEN BUNER 1
14
Beshonai Road District Buner 2
3.80
(KM)
1 Partially restored 0.5
(KM)
Start: 34.631381, 72.431088 View
End: 34.636082, 72.433148 View
Aug 30, 2025
11:29 AM
Remarks: Today report. 30-08-2025 The Beshonai Road that was previously damaged due to cloud burst and heavy rainfall had undergone restoration and was in progress by C&W. However, last night's intense rainfall and flooding has once again rendered the road completely unusable. With the weather still unstable and rainfall continuing.
Reported by: XEN BUNER 1
2 Partially restored 3.8
(KM)
Start: 34.631381, 72.431088 View
Aug 17, 2025
09:39 PM
15
Swari - Deewana Baba - Batara - Sir Qilla - Chowga - Puran Road P-H/Way (S-10-A) 14
70
(KM)
1 Partially restored 0.157
(KM)
Start: 34.476862, 72.485751 View
End: 34.738307, 72.683425 View
Aug 22, 2025
04:44 PM
Remarks: This Cost is taken to provide excavator & loader for flood effected area adjacent to Provincial Highway
Reported by: Managing Director PKHA
2 Fully restored 0.018
(KM)
Start: 34.596305, 72.648968 View
End: 34.596305, 72.648968 View
Aug 18, 2025
09:23 AM
3 Partially restored 0.34
(KM)
Start: 34.617258, 72.642483 View
End: 34.616961, 72.666546 View
Aug 17, 2025
12:12 PM
Remarks: At this Section Huge Slide occurred at different spots and the road is partially cleared
Reported by: Managing Director PKHA
4 Partially restored 0.015
(KM)
Start: 34.653572, 72.652549 View
End: 34.653572, 72.652549 View
Aug 17, 2025
11:03 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
5 Partially restored 0.017
(KM)
Start: 34.621131, 72.640656 View
End: 34.621131, 72.640656 View
Aug 17, 2025
10:55 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
6 Partially restored 0.0125
(KM)
Start: 34.611341, 72.639309 View
End: 34.611341, 72.639309 View
Aug 17, 2025
10:51 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
7 Partially restored 0.026
(KM)
Start: 34.605058, 72.646870 View
End: 34.605058, 72.646870 View
Aug 17, 2025
10:38 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
8 Partially restored 0.01
(KM)
Start: 34.596305, 72.648968 View
End: 34.596305, 72.648968 View
Aug 17, 2025
10:19 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
9 Partially restored 0.017
(KM)
Start: 34.579262, 72.637136 View
End: 34.579262, 72.637136 View
Aug 17, 2025
10:16 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
10 Partially restored 0.013
(KM)
Start: 34.544151, 72.642813 View
End: 34.544151, 72.642813 View
Aug 17, 2025
10:10 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
11 Partially restored 0.027
(KM)
Start: 34.537712, 72.639214 View
End: 34.537712, 72.639214 View
Aug 17, 2025
09:39 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
12 Partially restored 0.018
(KM)
Start: 34.530823, 72.639541 View
End: 34.530823, 72.639541 View
Aug 17, 2025
09:14 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
13 Partially restored 2
(KM)
Start: 34.738307, 72.683425 View
End: 34.640560, 72.648937 View
Aug 17, 2025
08:02 AM
Remarks: Road partially restored
Reported by: Managing Director PKHA
14 Partially restored 0.12
(KM)
Start: 34.655832, 72.651203 View
End: 34.705293, 72.666665 View
Jul 15, 2025
06:27 AM
16
Rehabilitation of Kalan road
2
(KM)
Partially restored 2
(KM)
No damage coordinates Aug 22, 2025
05:07 AM
17
Rehabilitation of Malang Dara road
5
(KM)
Fully restored 2.3
(KM)
Start: 72.418627, 34.644777 View
Aug 22, 2025
05:04 AM
18
Rehabilitation of Dokada Jowari road
3.5
(KM)
Fully restored 1.5
(KM)
Start: 72.418687, 34.641223 View
Aug 22, 2025
05:02 AM
19
Rehabilitation of Pir Baba Landay Mazar Road
1
(KM)
Fully restored 1
(KM)
Start: 72.453231, 34.599006 View
Aug 22, 2025
04:59 AM
20
Rehabilitation of Elum Road
13
(KM)
Fully restored 2.5
(KM)
Start: 72.391185, 34.586238 View
Aug 22, 2025
04:47 AM
21
Pir Baba to Daggar i/c Pir Baba to Jowar Road (S-10-D)
67
(KM)
Partially restored 4
(KM)
Start: 34.592689, 72.445019 View
End: 34.641670, 72.473491 View
Aug 18, 2025
11:55 AM
Remarks: This Cost is taken to provide excavator and loader for disaster / flood affected areas adjacent to provincial highway
Reported by: Managing Director PKHA
22
Mingora-Jambail-Kokarai-Gokand-Pir Baba-Daggar Road 52 Km (S-10-D) 14
52
(KM)
1 Partially restored 0.1
(KM)
Start: 34.684762, 72.479265 View
End: 34.684762, 72.479265 View
Aug 18, 2025
10:53 AM
2 Partially restored 0.1
(KM)
Start: 34.684712, 72.479352 View
End: 34.684712, 72.479352 View
Aug 18, 2025
10:51 AM
3 Partially restored 0.075
(KM)
Start: 34.635509, 72.493767 View
End: 34.635509, 72.493767 View
Aug 18, 2025
10:49 AM
4 Partially restored 0.1
(KM)
Start: 34.635892, 72.493336 View
End: 34.635892, 72.493336 View
Aug 18, 2025
10:48 AM
5 Partially restored 0.05
(KM)
Start: 34.636139, 72.493149 View
End: 34.636139, 72.493149 View
Aug 18, 2025
10:45 AM
6 Partially restored 0.075
(KM)
Start: 34.636360, 72.493095 View
End: 34.636360, 72.493095 View
Aug 18, 2025
10:43 AM
7 Fully restored 0.012
(KM)
Start: 34.686200, 72.491730 View
End: 34.686200, 72.491730 View
Aug 18, 2025
10:40 AM
8 Fully restored 0.075
(KM)
Start: 34.586040, 72.639691 View
End: 34.586040, 72.639691 View
Aug 18, 2025
10:38 AM
9 Fully restored 0.015
(KM)
Start: 34.686200, 72.491730 View
End: 34.686200, 72.491730 View
Aug 18, 2025
10:36 AM
10 Fully restored 0.016
(KM)
Start: 34.686200, 72.491730 View
End: 34.686200, 72.491730 View
Aug 18, 2025
10:34 AM
11 Fully restored 0.02
(KM)
Start: 34.686200, 72.491730 View
End: 34.686200, 72.491730 View
Aug 18, 2025
10:32 AM
12 Fully restored 0.02
(KM)
Start: 34.626860, 72.492220 View
End: 34.626860, 72.492220 View
Aug 18, 2025
10:25 AM
13 Fully restored 0.009
(KM)
Start: 34.635870, 72.491670 View
End: 34.635870, 72.491670 View
Aug 18, 2025
10:21 AM
14 Fully restored 3
(KM)
Start: 34.645210, 72.501957 View
End: 34.655612, 72.496395 View
Aug 18, 2025
10:15 AM
Remarks: 3.0 Km road is badly damaged
Reported by: Managing Director PKHA
23
Shahi Road District Buner
2
(KM)
Partially restored 0.26
(KM)
Start: 34.571852, 72.710032 View
End: 34.568485, 72.716964 View
Aug 18, 2025
05:02 AM
24
Shaheeda Sar to Faiza Baba
12
(KM)
Partially restored 0.55
(KM)
Start: 34.364800, 72.395200 View
Aug 18, 2025
04:58 AM
25
Gumbat to Ashari Sar road District Buner
3
(KM)
Partially restored 0.64
(KM)
Start: 34.371500, 72.380400 View
Aug 18, 2025
04:50 AM
26
Bampur Ajlai Road District Buner
4
(KM)
Partially restored 0.81
(KM)
Start: 34.333100, 72.410900 View
Aug 18, 2025
04:25 AM
27
Dambara Road District Buner
3
(KM)
Partially restored 0.49
(KM)
Start: 34.627257, 72.616635 View
Aug 18, 2025
04:20 AM
28
Pandher road District Buner
3
(KM)
Partially restored 0.28
(KM)
Start: 34.324900, 72.392000 View
Aug 18, 2025
03:57 AM
29
Kuz Shmnal to Bar Shmanal
3
(KM)
Partially restored 0.62
(KM)
Start: 34.383003, 72.591100 View
Aug 18, 2025
12:55 AM
30
Pukhtano mira Road District Buner
3
(KM)
Partially restored 0.71
(KM)
Start: 34.613621, 72.637107 View
Aug 18, 2025
12:44 AM
31
Alami Banda Road District Buner
1.2
(KM)
Partially restored 0.39
(KM)
Start: 34.601689, 72.649367 View
Aug 18, 2025
12:40 AM
32
Muta Khan Dara Road District Buner
1.2
(KM)
Partially restored 0.72
(KM)
Start: 34.622802, 72.627238 View
Aug 18, 2025
12:36 AM
33
Ghazi Banda to Bami Road District Buner
3
(KM)
Partially restored 0.4
(KM)
Start: 34.567500, 72.685350 View
Aug 18, 2025
12:32 AM
34
Gombat to Jabagai road PK-26 District Buner
2
(KM)
Partially restored 0.49
(KM)
Start: 34.259410, 72.473607 View
Aug 18, 2025
12:21 AM
35
Gombat to Charona Dara road PK-26 District Buner
2
(KM)
Partially restored 0.96
(KM)
Start: 34.622802, 72.627238 View
Aug 18, 2025
12:12 AM
36
Ganshal Mira Road PK-26 district Buner
3
(KM)
Partially restored 0.61
(KM)
Start: 34.617031, 72.513691 View
Aug 18, 2025
12:08 AM
37
Kela to Daba Nakhtar road District Buner
3
(KM)
Partially restored 3
(KM)
Start: 34.225200, 72.405900 View
Aug 17, 2025
11:55 PM
38
Shalizara Road District Buner
1
(KM)
Partially restored 1
(KM)
Start: 34.261100, 72.404400 View
Aug 17, 2025
11:47 PM
39
Malka to Amlook Dara road District Buner
3
(KM)
Fully restored 3
(KM)
Start: 34.329149, 72.645250 View
Aug 17, 2025
11:43 PM
40
Shadam to Baghona Road District Buner
6
(KM)
Fully restored 6
(KM)
Start: 34.200700, 72.380300 View
Aug 17, 2025
11:37 PM
41
Nagrai to Charorai road District Buner
4
(KM)
Partially restored 0.19
(KM)
Start: 34.234900, 72.422500 View
Aug 17, 2025
11:32 PM
42
Kandar Katay Langar Langaw, Malka Mahabanr road District Buner
10
(KM)
Partially restored 4.5
(KM)
Start: 34.329121, 72.645257 View
Aug 17, 2025
11:28 PM
43
Nagrai to Daba Nakhtaro road District Buner
6
(KM)
Partially restored 6
(KM)
Start: 34.225200, 72.405900 View
Aug 17, 2025
11:18 PM
44
Qudro Sar Road District Buner
4
(KM)
Partially restored 0.27
(KM)
Start: 34.591560, 72.524860 View
Aug 17, 2025
11:13 PM
45
Bekand Road District Buner
1.2
(KM)
Partially restored 0.24
(KM)
Start: 34.659168, 72.501966 View
Aug 17, 2025
10:55 PM
46
Sudhair Road
1.2
(KM)
Partially restored 0.3
(KM)
Start: 34.686874, 72.482753 View
Aug 17, 2025
10:52 PM
47
Bar Gokand Road District Buner
3
(KM)
Partially restored 1.72
(KM)
Start: 34.668111, 72.506532 View
Aug 17, 2025
10:41 PM
48
Bagra Road District Buner
1.00
(KM)
Partially restored 0.4
(KM)
Start: 34.586855, 72.517877 View
Aug 17, 2025
10:37 PM
49
Poland Kursar road District Buner
8.00
(KM)
Partially restored 0.6
(KM)
Start: 34.639254, 72.417428 View
Aug 17, 2025
09:46 PM
50
Dokada road district Buner
0.250
(KM)
Partially restored 0.25
(KM)
Start: 34.632627, 72.421289 View
Aug 17, 2025
09:26 PM
51
Pir Baba Main Road District Buner
3.4
(KM)
Partially restored 3.4
(KM)
Start: 34.501536, 72.458409 View
Aug 17, 2025
08:59 PM
CWD