Progressive Review for the month(s) of : January - 2020, January - 2021, January - 2018, January - 2019, February - 2020, February - 2021, February - 2018, February - 2019, March - 2020, March - 2021, March - 2018, March - 2019, April - 2020, April - 2021, April - 2018, April - 2019, May - 2020, May - 2021, May - 2018, June - 2018, July - 2020, July - 2017, August - 2020, August - 2017, August - 2019, September - 2020, September - 2017, September - 2019, October - 2020, October - 2017, October - 2019, November - 2019, November - 2017, November - 2018, December - 2020, December - 2017, December - 2018, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
December - 2019
Substantially completed. Shifting of Electronic pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 10 2.5 2.5 305.65 376.849 45% 44%
November - 2019
Substantially completed. Shifting of Electronic pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 10 2.5 2.5 305.65 376.849 45% 44%
October - 2019
Substantially completed. Shifting of Electronic pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 10 2.5 2.5 305.65 376.849 45% 44%
September - 2019
Substantially completed.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 10 2.5 2.5 305.65 376.849 45% 44%
August - 2019
Substantially completed.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
May - 2020
Substantially completed. Shifting of Electric pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
April - 2020
Substantially completed. Shifting of Electric pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
March - 2020
Substantially completed. Shifting of Electric pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
February - 2020
Substantially completed. Shifting of Electric pole not yet done.
No Image
Package-1
Package-2
997
(OG)
140623-Construction of road from Balambat Timergara to Kalpani Maidan Link road District Dir Lower.
Dir Lower
PKHA
30-11--1 30-11--1 - 30-11--1 - 689.999 303.15 10 9.575 9.575 9.575 312.725 376.849 45% 45%
January - 2020
Substantially completed. Shifting of Electric pole not yet done.
No Image
Package-1
Package-2
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
11-06-10 30-06-18 - 13-12-11 - 532.754 441.534 10.507 10.507 10.511 10.511 452.045 80.713 85% 85%
December - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
11-06-10 30-06-18 - 13-12-11 - 532.754 441.534 7.007 7.007 7.007 7.007 448.541 84.213 84% 84%
September - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
11-06-10 30-06-18 - 13-12-11 - 532.754 441.534 7.007 7.007 7.007 7.007 448.541 84.213 84% 84%
August - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
11-06-10 - - 13-12-11 - 532.754 441.534 4.975 4.975 4.975 0 441.534 86.245 84% 83%
July - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
December - 2020
No Image
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
December - 2020
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 441.534 10.507 10.507 10.511 10.511 452.045 80.713 85% 85%
November - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 441.534 10.507 10.507 10.507 7.007 448.541 80.713 85% 84%
October - 2017
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
October - 2020
No Image
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
September - 2020
No Image
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
August - 2020
No Image
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 0 0 0 579.29 0 - -
July - 2020
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 14.014 14.014 14.014 14.014 482.729 50.025 91% 91%
June - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 31.261 31.261 15.732 14.014 482.729 32.778 94% 91%
May - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
May - 2021
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 31.261 31.261 15.732 10.511 479.226 32.778 94% 90%
April - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
April - 2021
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 31.261 31.261 10.511 10.511 479.226 32.778 94% 90%
March - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
March - 2021
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 31.261 31.261 10.511 10.511 479.226 32.778 94% 90%
February - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
February - 2021
No Image
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Hangu
30-11--1 30-11--1 - 30-11--1 - 532.754 468.715 31.261 31.261 31.261 10.511 479.226 32.778 94% 90%
January - 2018
18.5/20 Km BT completed, structure work in progress.
No Image
20 Km under jurisdiction of this division
997
(OG)
110359-23 Secure Armories Across Province and Mini Police Line, Hangu (P.M Package, 2nd & 3rd Tranch)
Hangu
30-11--1 30-11--1 - 30-11--1 - 588.93 579.29 9.64 9.64 0 0 579.29 0 - -
January - 2021
No Image
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
December - 2018
Bridge 300 mtr, -Complted.
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
November - 2018
Bridge 300 mtr, 10 span - launching of girders in progress, 5/10 deck slab laid.
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
November - 2018
Bridge 300 mtr, 10 span - launching of girders in progress, 5/10 deck slab laid.
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
April - 2019
Completed (Bridge 300 mtr) (physically/ financially).
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
March - 2019
Completed (Bridge 300 mtr) (physically/ financially).
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
March - 2019
Completed (Bridge 300 mtr) (physically/ financially).
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
February - 2019
Completed (Bridge 300 mtr). (Physically + financially).
No Image
Haripur
997
(OG)
150884-Construction of RCC Bridge over Dhoor at Mohra Mumdu Mankara, District Haripur.
Haripur
30-11--1 30-11--1 - 30-11--1 - 173.524 173.77 9.6 9.6 9.6 9.283 183.053 0 100% 100%
January - 2019
Completed (Bridge 300 mtr). (Physically + financially)
No Image
Haripur
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
25-05-10 30-06-18 - 13-12-11 - 440.41 425.182 19.032 19.032 19.032 0 425.182 0 100% 97%
December - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
25-05-10 30-06-18 - 13-12-11 - 440.41 425.182 2.032 2.032 2.032 0 425.182 13.196 97% 97%
September - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
25-05-10 30-06-18 - 13-12-11 - 440.41 425.182 2.032 2.032 2.032 0 425.182 13.196 97% 97%
August - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
25-05-10 - - 13-12-11 - 440.41 425.182 0 0 0 0 425.182 15.228 - 97%
July - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
30-11--1 30-11--1 - 30-11--1 - 440.41 425.182 3.507 3.507 0 0 425.182 11.721 97% 97%
November - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
30-11--1 30-11--1 - 30-11--1 - 440.41 425.182 3.507 3.507 2.032 0 425.182 11.721 97% 97%
October - 2017
Completed (22.35 Km).
No Image
1) Package-II (22.35 Kms) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
30-11--1 30-11--1 - 30-11--1 - 440.41 420.179 0 0 0 0 420.179 20.231 - 95%
June - 2018
Completed (22.35 Km).
No Image
1) Package-II (22.35 Km) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
30-11--1 30-11--1 - 30-11--1 - 440.41 420.179 19.032 19.032 19.032 0 420.179 1.199 100% 95%
May - 2018
Completed (22.35 Km).
No Image
1) Package-II (22.35 Km) from Lachi side
997
(OG)
80668-Construction of alternate Road Lachi to Hangu-Thall-Parachinar Road (41.80 Km).
Kohat
30-11--1 30-11--1 - 30-11--1 - 440.41 420.179 19.032 19.032 19.032 0 420.179 1.199 100% 95%
April - 2018
Completed (22.35 Km).
No Image
1) Package-II (22.35 Km) from Lachi side