Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% December - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% December - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 0 | 0 | 0 | 0 | 0 | 0 | 178.173 | - |
- October - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 0 | 0 | 0 | 0 | 0 | 0 | 178.173 | - |
- September - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 0 | 0 | 0 | 0 | 0 | 0 | 178.173 | - |
- August - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 0 | 0 | 0 | 0 | 0 | 0 | 178.173 | - |
- July - 2020 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% May - 2021 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% April - 2021 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% March - 2021 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% February - 2021 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 178.173 | 187.565 | 0 | 0 | 0 | 0 | 187.565 | 0 | - |
100% January - 2021 |
Completed. |
No Image |
1) GC Lal Qilla Maidan (main building/50 Nos | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% December - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% December - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 0 | 0 | 0 | 0 | 0 | 0 | 155.264 | - |
- October - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 0 | 0 | 0 | 0 | 0 | 0 | 155.264 | - |
- September - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 0 | 0 | 0 | 0 | 0 | 0 | 155.264 | - |
- August - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 0 | 0 | 0 | 0 | 0 | 0 | 155.264 | - |
- July - 2020 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% May - 2021 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% April - 2021 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% March - 2021 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% February - 2021 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Dir Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 155.264 | 163.188 | 4 | 4 | 4 | 0 | 163.188 | 0 | 100% |
100% January - 2021 |
Completed. |
No Image |
GDC Barawal PK-91 | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% December - 2019 |
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus. |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17 | 17 | 17 | 17 | 209.352 | 43.447 | 83% |
83% December - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17 | 17 | 17 | 17 | 209.352 | 43.447 | 83% |
83% December - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 10.75 | 322.363 | 72.873 | 82% |
81% November - 2019 |
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus. |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 297.592 | 15 | 15 | 3.75 | 3.75 | 301.342 | 86.894 | 78% |
75% October - 2019 |
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus. |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 0 | 0 | 0 | 0 | 192.352 | 60.447 | - |
76% October - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress. |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 297.592 | 15 | 15 | 3.75 | 3.75 | 301.342 | 86.894 | 78% |
75% September - 2019 |
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus. |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 0 | 0 | 0 | 0 | 192.352 | 60.447 | - |
76% September - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress. |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 297.592 | 15 | 15 | 3.75 | 3.75 | 301.342 | 86.894 | 78% |
75% August - 2019 |
Length 18.5 Km - width 12 ft, Pack-I - earth work completed, road work, structure work in progress and 3.5 Km shifted to Jarikus. |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 0 | 0 | 0 | 0 | 192.352 | 60.447 | - |
76% August - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress. |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 0 | 0 | 0 | 0 | 192.352 | 60.447 | - |
76% July - 2020 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress. |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% May - 2020 |
Length 18.5 Km 10 km BT complted
Demand Rs 20 m for tempo of work |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17.405 | 17.405 | 17.405 | 17 | 209.352 | 43.042 | 83% |
83% May - 2021 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% April - 2020 |
Length 18.5 Km 10 km BT complted
Demand Rs 20 m for tempo of work |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17.405 | 17.405 | 17.405 | 17 | 209.352 | 43.042 | 83% |
83% April - 2021 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% March - 2020 |
Length 18.5 Km 10 km BT complted
Demand Rs 20 m for tempo of work |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17.405 | 17.405 | 17.405 | 17 | 209.352 | 43.042 | 83% |
83% March - 2021 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% February - 2020 |
Length 18.5 Km 10 km BT complted
Demand Rs 20 m for tempo of work |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17.405 | 17.405 | 17.405 | 17 | 209.352 | 43.042 | 83% |
83% February - 2021 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
140656-F/S, Design & Construction of road from i) Sulam Khand to Sira road (6.50 Km), ii) Ghazi to Sulam Khand, Salam Khan Gali to Triman (8.5 Km) and iii) Ghazi Jari Kas road (5-Km), District Haripur (20-Km). |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 399.486 | 311.613 | 15 | 15 | 15 | 15 | 326.613 | 72.873 | 82% |
82% January - 2020 |
Length 18.5 Km 10 km BT complted
Demand Rs 20 m for tempo of work |
No Image |
1) Pack-1 - Sira to Salam Khund road 6.5 Km
2) Pack-2 - Sira to Salam Khund road 8.5 Km
3) Pack-3 - Jhari Kas 3.5 Km | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 252.799 | 192.352 | 17 | 17 | 17 | 17 | 209.352 | 43.447 | 83% |
83% January - 2021 |
Academic block - Finsihing in progress.
Aduitorm Finishing in progress.
Admn Block, Suits finishing in progress.
Revsiion submitted to Higher Edu deptt |
No Image |
GDC Khanpur shifted to Sarai Saleh | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 186.665 | 0 | 0 | 0 | 0 | 186.665 | 5.706 | - |
97% December - 2020 |
GGC Sakhakot - MB Hostel, = Roof laid
admin block, cafeteria, suiits plastering & finishing in progress.
Guard Room = Finishing in progress.
Tube well, Over Head Tank completed.
Revised DCE submitted. |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 186.665 | 0 | 0 | 0 | 0 | 186.665 | 5.706 | - |
97% December - 2020 |
GGC Sakhakot - MB Hostel, = Roof laid
admin block, cafeteria, suiits plastering & finishing in progress.
Guard Room = Finishing in progress.
Tube well, Over Head Tank completed.
Revised DCE submitted. |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 0 | 0 | 0 | 0 | 0 | 0 | 192.371 | - |
- October - 2020 |
GGC Sakhakot - MB Hostel, = Roof laid
admin block, cafeteria, suiits plastering & finishing in progress.
Guard Room = Finishing in progress.
Tube well, Over Head Tank completed. Revised DCE submitted. |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 0 | 0 | 0 | 0 | 0 | 0 | 192.371 | - |
- September - 2020 |
GGC Sakhakot - MB Hostel, = Roof laid
admin block, cafeteria, suiits plastering & finishing in progress.
Guard Room = Finishing in progress.
Tube well, Over Head Tank completed. Revised DCE submitted. |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 0 | 0 | 0 | 0 | 0 | 0 | 192.371 | - |
- August - 2020 |
GGC Sakhakot - hostel, admin block, cafeteria, sui |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 0 | 0 | 0 | 0 | 0 | 0 | 192.371 | - |
- July - 2020 |
GGC Sakhakot - hostel, admin block, cafeteria, sui |
No Image |
1) GGDC Sakhakot PK-98
2) GGDC | |||||||||||||||||||
908 (OG) |
50179-Establishment of Govt. Colleges in Khyber Pakhtunkhwa. (Phase-II) |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 192.371 | 186.665 | 0 | 0 | 0 | 0 | 186.665 | 5.706 | - |
97% May - 2021 |
Main Building Roof laid
Admin block roof laid cafeteria Finishing in progress
suiits plastering & finishing in progress.
Guard Room = Finishing in progress.
Tube well, Over Head Tank completed.
Revised DCE for Rs: 328.53 M submitted to CPO on 28-10-20 |
No Image |
1) GGDC Sakhakot PK-98
| |||||||||||||||||||