Communication and Works Department

Annual Development Review


Search With ADP Advance Search
Home Page


Progressive Review for the month(s) of : January - 2021, January - 2018, January - 2019, January - 2020, February - 2021, February - 2018, February - 2019, February - 2020, March - 2021, March - 2018, March - 2019, March - 2020, April - 2021, April - 2018, April - 2019, April - 2020, May - 2021, May - 2018, May - 2020, June - 2018, July - 2018, July - 2020, July - 2017, August - 2019, August - 2020, August - 2017, September - 2017, September - 2018, September - 2019, September - 2020, October - 2017, October - 2019, October - 2020, November - 2017, November - 2018, November - 2019, December - 2017, December - 2020, December - 2018, December - 2019,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral
30-11--1 30-11--1 - 30-11--1 - 550 343.557 70 70 17.5 0 343.557 136.443 75% 62%
August - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 31.921 31.921 31.921 24.667798 199.699798 343.047 38% 36%
December - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 5.671 5.671 5.671 5.671 180.703 369.297 33% 33%
November - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 17.5 17.5 17.5 17.5 192.532 357.468 35% 35%
October - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 343.557 0 0 17.5 5.671 349.228 206.443 - 63%
September - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 22.25 17.381 17.381 12.838 187.87 352.718 36% 34%
May - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 22.25 31.92 31.92 12.838 187.87 352.718 36% 34%
April - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 22.25 31.92 31.92 12.838 187.87 352.718 36% 34%
March - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 22.25 31.92 31.92 12.838 187.87 352.718 36% 34%
February - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Lower
30-11--1 30-11--1 - 30-11--1 - 550 175.032 31.921 31.921 31.921 24.667798 199.699798 343.047 38% 36%
January - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.079 38.079 38.079 26.25 187.973 42.868 82% 77%
December - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 11.828 11.828 11.828 11.828 173.551 69.119 72% 72%
November - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 0 0 0 0 161.723 80.947 - 67%
October - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 0 0 0 0 161.723 80.947 - 67%
September - 2019
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.458 38.458 38.458 38.458 200.181 42.489 82% 82%
May - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.458 38.458 38.458 38.458 200.181 42.489 82% 82%
April - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.458 38.458 38.458 38.458 200.181 42.489 82% 82%
March - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.458 38.458 38.458 38.458 200.181 42.489 82% 82%
February - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Chitral Upper
30-11--1 30-11--1 - 30-11--1 - 242.67 161.723 38.458 38.458 38.458 38.458 200.181 42.489 82% 82%
January - 2020
9/9 roads completed. 4/9 bridges completed. 4/9 bridges in progress. 1 retendering (Osiak) 7th time on 12/12/18.
No Image
1) Immediate rehabiliation of Chitral - Garam Chashma road
2) Immediate rehabiliation of Chitral - Booni road at various road
3) Immediate rehabiliation of Ayn to Bumborate road
4) Immediate rehabiliation of road fromShoghore to Karimabad Sosum
5) Immediate rehabiliation of Chitral Drosh West road at Dome Shoghore Chitral Orghouch heavy flood, Drosh area
6) Immediate rehabiliation of Rumboor road from Dobach to Rumboor
7) Rehabilitation of Birir road
8) Rehabilitation of Yarkhoon to Boroghal Pass road
9) Rehabilitation of Charun Zondrangram road
10) Construction of RCC bridge at Osiak Drosh
11) Construction of RCC bridge at Shoghore
12) Construction of RCC bridge at Pockeel
13) Construction of RCC bridge at Reshun
14) Repair of existing bridge at Charun
15) Construction of RCC bridge connecting Mulkhow valley at Moazhgole
16) Construction of RCC bridge at Goldeh Broze
17) Construction of RCC bridge at Khorkashandeh
18) Construction of suspension bridge at Booni Gole Booni
875
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 344.978 316.7 10 10 5 5 321.7 18.278 95% 93%
September - 2018
Structure/road work in progress.
No Image
875
(OG)
150890-Rehabilitation / Black Topping of Chukyatan to Barawal Bandai Road, District Dir Upper.
Dir Upper
PKHA
30-11--1 30-11--1 - 30-11--1 - 344.978 191.7 10 10 5 0 191.7 143.278 58% 56%
July - 2018
Structure/road work in progress.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
December - 2020
Tendering under process.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
December - 2020
Tendering under process.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
October - 2020
Tendering under process.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
September - 2020
Tendering underc process.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
August - 2020
Tendering underc process.
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 32.607 0 0 0 0 0 -
July - 2020
No Image
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 12.112 12.112 12.112 12.112 12.112 20.495 37% 37%
May - 2021
F/F roof level, Repiar of Main builidng 20% Completed Latrine 80% Completed C/Wall finishing stage
No Image
RCH Kirriwam
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 12.112 12.112 12.112 12.112 12.112 20.495 37% 37%
April - 2021
F/F roof level, Repiar of Main builidng 20% Completed Latrine 80% Completed C/Wall finishing stage
No Image
RCH Kirriwam
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 12.112 12.112 12.112 12.112 12.112 20.495 37% 37%
March - 2021
F/F roof level, Repiar of Main builidng 20% Completed Latrine 80% Completed C/Wall finishing stage
No Image
RCH Kirriwam
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 12.112 12.112 12.112 12.112 12.112 20.495 37% 37%
February - 2021
F/F roof level, Repiar of Main builidng 20% Completed Latrine 80% Completed C/Wall finishing stage
No Image
RCH Kirriwam
875
(OG)
195145-Revamping of RHCs in Merged Areas (AIP).
FR Tank
30-11--1 30-11--1 - 30-11--1 - 32.607 0 0 0 0 0 0 32.607 - -
January - 2021
Tendering under process.
No Image
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 54.711 33.811 33.811 190.279 0 100% 89%
December - 2018
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 54.711 33.811 33.811 190.279 0 100% 89%
November - 2018
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 54.711 33.811 33.811 190.279 0 100% 89%
November - 2018
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 56.801 56.801 49.963 206.431 0 100% 97%
April - 2019
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 56.801 56.801 34.3369 190.8049 0 100% 89%
March - 2019
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 56.801 56.801 34.3369 190.8049 0 100% 89%
March - 2019
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 54.7109 54.7109 33.8109 190.2789 0 100% 89%
February - 2019
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(OG)
140918-F/S, Design & BT of road at Palai and Agra 10 Km, Malakand.
Malakand
30-11--1 30-11--1 - 30-11--1 - 213.269 156.468 56.801 54.711 33.811 33.811 190.279 0 100% 89%
January - 2019
Length 10 Km - BT 3 Km completed.
No Image
1) BT road from Palai Chowk to Ghazi Baba UC Palai (2 Km)
2) BT road from Zormandai Farsh to Khooq Dara UC Palai (1 Km)
3) BT road from Sherkhana to Sheikhta Baba UC Palai (1 Km)
4) BT road Bazdara road UC Palai (1 Km)
5) Improvement/widening/BT of Babaganosar Ghund Agra road UC Agra (2 Km)
6) PCC rod Parokhel UC Agra (0.5 Km)
7) PCC road Inzargay Mashoor Malak Koroona UC Agra (0.5 Km)
8) Improvement/widening/BT of Nekrahi road Agra UC Agra (2 Km)
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
June - 2018
PC-I/DCE for Rs.79.370 m submitted to SOR on 13/02/2018.
No Image
Village Sufeda (4 Km), District Mansehra
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
May - 2018
PC-I/DCE for Rs.79.370 m submitted to SOR on 13/02/2018.
No Image
Village Sufeda (4 Km), District Mansehra
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
April - 2018
PC-I/DCE for Rs.79.370 m submitted to SOR on 13/02/2018.
No Image
Village Sufeda (4 Km), District Mansehra
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
March - 2018
PC-I/DCE for Rs.79.370 m submitted to SOR on 13/02/2018.
No Image
Village Sufeda (4 Km), District Mansehra
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Mansehra
30-11--1 30-11--1 - 30-11--1 Line Deptt 0 0 0 0 0 0 0 0 - -
February - 2018
PC-I/DCE for Rs.79.370 m submitted to SOR on 13/02/2018.
No Image
Village Sufeda (4 Km), District Mansehra
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Provincial
- - - - Line Deptt 500 0 45 45 0 0 0 0 - -
December - 2017
No Image
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Provincial
- - - - Line Deptt 500 0 45 45 0 0 0 0 - -
September - 2017
No Image
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Provincial
- - - - Line Deptt 500 0 45 45 0 0 0 0 - -
August - 2017
No Image
875
(New)
170535-Construction of Access Roads to Mineral Bearing Areas of Khyber Pakhtunkhwa.
Provincial
- - - - Line Deptt 500 0 45 45 0 0 0 0 - -
July - 2017
No Image
875
(OG)
170171-Immediate Rehabilitation of flood damaged (09 Nos Roads & Bridges each) due to flash flood and GOLF 2015, District Chitral
Provincial
30-11--1 30-11--1 - 30-11--1 - 550 343.557 70 70 70 0 343.557 136.443 75% 62%
December - 2019
No Image
Pages : 1 2