Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 104.778 | 30 | 30 | 7.5 | 0 | 104.778 | 288.328 | 32% |
25% August - 2019 |
3 units - 12 km -in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 30 | 28.088 | 28.088 | 7.5 | 72.215 | 328.391 | 22% |
17% December - 2019 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 7.5 | 7.5 | 7.5 | 7.5 | 72.215 | 350.891 | 17% |
17% November - 2019 |
3 units - 12 km -in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 7.5 | 7.5 | 7.5 | 7.5 | 72.215 | 350.891 | 17% |
17% October - 2019 |
3 units - 12 km -in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 7.5 | 7.5 | 7.5 | 7.5 | 72.215 | 350.891 | 17% |
17% May - 2020 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 30 | 28.088 | 28.088 | 7.5 | 72.215 | 328.391 | 22% |
17% April - 2020 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 30 | 28.088 | 28.088 | 7.5 | 72.215 | 328.391 | 22% |
17% March - 2020 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 30 | 28.088 | 28.088 | 7.5 | 72.215 | 328.391 | 22% |
17% February - 2020 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 64.715 | 30 | 28.088 | 28.088 | 7.5 | 72.215 | 328.391 | 22% |
17% January - 2020 |
Km 1& 2 - Easrth and Structure work completed.
KM -3 to 7 Tender approval in process. |
No Image |
Junjerat to Junjerat Koh road (7 Km) - | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 0 | 0 | 0 | 0 | 57.481 | 19.407 | - |
75% December - 2019 |
2 units - 3.5 Km - in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 0 | 0 | 0 | 0 | 57.481 | 19.407 | - |
75% November - 2019 |
2 units - 3.5 Km - in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 0 | 0 | 0 | 0 | 57.481 | 19.407 | - |
75% October - 2019 |
2 units - 3.5 Km - in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 104.778 | 30 | 30 | 7.5 | 0 | 104.778 | 288.328 | 32% |
25% September - 2019 |
3 units - 12 km -in progress. |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 20.587 | 20.587 | 20.587 | 0 | 57.481 | 0 | 100% |
75% May - 2020 |
2 units - 3.5 Km - in progress.
Snow Bound |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
| |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 20.587 | 20.587 | 20.587 | 5.2 | 62.681 | 0 | 100% |
82% April - 2020 |
2 units - 3.5 Km - in progress.
Snow Bound |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
| |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 20.587 | 20.587 | 20.587 | 5.2 | 62.681 | 0 | 100% |
82% March - 2020 |
2 units - 3.5 Km - in progress.
Snow Bound |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
| |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 20.587 | 20.587 | 20.587 | 5.2 | 62.681 | 0 | 100% |
82% February - 2020 |
2 units - 3.5 Km - in progress.
Snow Bound |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
| |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Chitral Upper |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 76.888 | 57.481 | 20.587 | 20.587 | 20.587 | 0 | 57.481 | 0 | 100% |
75% January - 2020 |
2 units - 3.5 Km - in progress.
Snow Bound |
No Image |
1) Wajijun to Terich road (2 Km) - Shingle Roads
2) Kosht to Lone road (3 Km) - Shingle Roads
3) Junjerat to Junjerat Koh road (7 Km) - Shingle Roads | |||||||||||||||||||
874 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 12.5 | 12.5 | 302.35 | 673.67 | 32% |
31% September - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
874 (OG) |
140829-Improvement of 25 Km leftover portion of Chukiyatan - Barawal - Shahi Road, District Dir Upper. |
Dir Upper PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 988.52 | 289.85 | 25 | 25 | 12.5 | 0 | 289.85 | 673.67 | 32% |
29% July - 2018 |
Length 25 Km. Pack-1 - earth work 6.2/8 Km completed. Pack- 2 - earth work 6.2/8 Km completed. Pack-3 and 4 - earth work started. |
No Image |
Package-1 (Barawal Bandi to Jan Bati)
Package-2 (Jan Bati to Shaltalo)
Package-3 (Shaltalo to Marawaro)
Package-4 (Marawaro to Shahi Top) | |||||||||||||||||||
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.3 | 0 | 100 | 35.678 | 35.678 | 18.333 | 18.333 | 0 | 100% |
21% May - 2021 |
04 Units
1 Roof level
2 Roof level
3 Roof laid
4 Work started |
No Image |
| |||||||||||||||||||
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.3 | 0 | 100 | 35.678 | 35.678 | 18.333 | 18.333 | 0 | 100% |
21% April - 2021 |
04 Units
1 Roof level
2 Roof level
3 Roof laid
4 Work started |
No Image |
| |||||||||||||||||||
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.3 | 0 | 100 | 35.678 | 35.678 | 18.333 | 18.333 | 0 | 100% |
21% March - 2021 |
04 Units
1 Roof level
2 Roof level
3 Roof laid
4 Work started |
No Image |
| |||||||||||||||||||
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
FR Tank |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 88.3 | 0 | 100 | 35.678 | 35.678 | 18.333 | 18.333 | 0 | 100% |
21% February - 2021 |
04 Units
1 Roof level
2 Roof level
3 Roof laid
4 Work started |
No Image |
| |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% December - 2018 |
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% November - 2018 |
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% November - 2018 |
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% April - 2019 |
Bridge-completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% March - 2019 |
Bridge-completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% March - 2019 |
Bridge-completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% February - 2019 |
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
60323-Construction of RCC Bridge on River Swat alongwith approach road at Thana Malakand. |
Malakand |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 429.16 | 323.227 | 25 | 25 | 25 | 25 | 348.227 | 80.933 | 81% |
81% January - 2019 |
112/112 piles, 18/18 pile cap, 68/68 girders, 2/2 abutment, 32/32 pier shoft, 16/16 transum, 68/68 girders, 16/17 deck slabs completed.
Road work on right side in progress. Work on approaches resumed after clearnce of site dispute. |
No Image |
Rcc Bridge (17 span length 408 mtr width 8.9 mtr) | |||||||||||||||||||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- December - 2019 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- December - 2020 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- November - 2019 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 30 | 0 | 0 | 0 | 0 | - |
- October - 2019 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- October - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- September - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- August - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 0 | 0 | 0 | 0 | 0 |
- July - 2020 |
No Image | ||
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- May - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- May - 2021 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- April - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- April - 2021 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- March - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- March - 2021 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- February - 2020 |
No Image | |
874 (OG) |
195144-Provision of SBA Services & Revamping & Rehabilitation of Existing of BHUs in Mergred Areas (AIP) |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 557.341 | 0 | 100 | 100 | 0 | 0 | 0 | 0 | - |
- February - 2021 |
No Image | |
874 (OG) |
150844-Construction/ widening of roads Varijun to Terich, Jinjarit to Jinjarit Koh and Kosht to Loan District Chitral. |
Provincial |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 423.106 | 0 | 30 | 28.0875 | 28.0875 | 0 | 0 | 0 | - |
- January - 2020 |
No Image | |
Pages : 1 2 |