Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
- | - | - | - | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
Approved in DDC on 10/10/2017. Tender approval under process. Work order will be issued in 7 days. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Approved in DDC on 10/10/2017. AA awaited. Tender approval under process. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
Work order issued. |
No Image |
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
Work order issued. |
No Image |
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
Work order issued. |
No Image |
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
Work order issued. |
No Image |
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
Work order issued. |
No Image |
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Abbottabad |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
Approved in DDC on 10/10/2017. Tender approval under process. Work order will be issued in 7 days. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34 | 0 | 0 | 0 | 0 | 0 | 0 | 34 | - |
- June - 2018 |
Work order issued on 28/02/2018. Layout given. |
No Image |
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel, Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34 | 0 | 0 | 0 | 0 | 0 | 0 | 34 | - |
- May - 2018 |
Work order issued on 28/02/2018. Layout given. Rs.20 m demanded. |
No Image |
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel, Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 34 | 0 | 0 | 0 | 0 | 0 | 0 | 34 | - |
- April - 2018 |
Work order issued on 28/02/2018. Layout given. Rs.20 m demanded. |
No Image |
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel, Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 0 | 0 | 0 | 0 | 0 | 0 | 35 | - |
- March - 2018 |
Work order issued on 28/02/2018. Layout given. |
No Image |
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel, Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 35 | 0 | 0 | 0 | 0 | 0 | 0 | 35 | - |
- February - 2018 |
Tender called on 20/03/2018 (2 units) and 22/03/2018 (1 unit). |
No Image |
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel, Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
- | - | - | - | - | 46.2 | 0 | 0 | 0 | 0 | 0 | 0 | 46.2 | - |
- December - 2017 |
Tender called on 08/12/2017. Stay order issued on e-bid. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
- | - | - | - | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE under preparation. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
- | - | - | - | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE under preparation. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 0 | 0 | 0 | 0 | 0 | 46.2 | - |
- November - 2017 |
Tender called on 08/12/2017. Stay order issued. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Approved in DDC on 26/10/2017. AA awaited. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 20.793 | 20.793 | 20.793 | 18.536 | 18.536 | 25.407 | 45% |
40% June - 2018 |
Work in progress. |
No Image |
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 20.793 | 20.793 | 20.793 | 15.818 | 15.818 | 25.407 | 45% |
34% May - 2018 |
Work started. |
No Image |
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 20.793 | 20.793 | 20.793 | 11.103 | 11.103 | 25.407 | 45% |
24% April - 2018 |
Work started. |
No Image |
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 20.793 | 20.793 | 20.793 | 0 | 0 | 25.407 | 45% |
- March - 2018 |
Tender called on 15/01/2018. Stay order on opening of tender, hearing date on 04/04/2018. |
No Image |
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 0 | 0 | 0 | 0 | 0 | 46.2 | - |
- February - 2018 |
Tender called on 15/01/2018. Stay order on opening of tender, hearing date on 14/03/2018. |
No Image |
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif | |||||||||||||||||||
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Battagram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 46.2 | 0 | 0 | 0 | 0 | 0 | 0 | 46.2 | - |
- January - 2018 |
Tender called on 15/01/2018. Stay order on opening of tender. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
- | - | - | - | - | 53 | 0 | 0 | 0 | 0 | 0 | 0 | 53 | - |
- December - 2017 |
Technical evaluation under process (PK-17 and PK-18). E-bid re-invited on 10/01/2018. |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
Technical evaluation under process (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
Re-tender opened on 16/11/2017 (PK-17 and PK-20). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 51.14 | 51.14 | 51.14 | 21.033 | 21.033 | 1.86 | 96% |
40% June - 2018 |
Work order issued (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 51.14 | 51.14 | 51.14 | 21.033 | 21.033 | 1.86 | 96% |
40% May - 2018 |
Work order issued (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 5 | 5 | 5 | 0.5 | 0.5 | 48 | 9% |
1% April - 2018 |
Work order issued (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 5 | 5 | 5 | 0.5 | 0.5 | 48 | 9% |
1% March - 2018 |
Work order issued (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 5 | 5 | 5 | 0.5 | 0.5 | 48 | 9% |
1% February - 2018 |
Work order issued (PK-17 and PK-18). |
No Image |
858 (New) |
170359-District Development Initiatives (List of schemes at Annex-IV). |
Charsadda |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 53 | 0 | 0 | 0 | 0 | 0 | 0 | 53 | - |
- January - 2018 |
Tender approval under process (PK-17 and PK-18). |
No Image |
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% December - 2019 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress. Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% November - 2019 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress. |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% October - 2019 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress. |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 5 | 5 | 155.713 | 107.348 | 61% |
56% September - 2019 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress. |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 5 | 0 | 150.713 | 107.348 | 61% |
54% August - 2019 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress. |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% May - 2020 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% April - 2020 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% March - 2020 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% February - 2020 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
150967-Construction of roads from Odigram to Haya Sairay, Odigram to Lajbook & Shahko, Kadh road and Shudas to Fazal Abad, Maimai road, Kumbatar to Burkhanay Nambaty Dir Lower |
Dir Lower |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 278.061 | 150.713 | 20 | 20 | 20 | 20 | 170.713 | 107.348 | 61% |
61% January - 2020 |
Length 20 (6 units) - 3 Km BT completed, 17 Km in progress.
Demand 60 M P-II |
No Image |
1) Odigram to Hayaserai road
2) Odigram to Lajbook road
3) Kadh to Shahko road
4) Shahko to Lajbook road
5) Shadas to Fazal Abad Meramai road
6) Kumbar to Burkhanay Nambatai road | |||||||||||||||||||
858 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 272.949 | 49 | 49 | 24.5 | 24.5 | 297.449 | 0 | 100% |
100% September - 2018 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
858 (OG) |
140627-Improvement, Widening and Rehabilitation of Road from Bannu Kohat Road to Indus Highway via Garrison College/Dhoda Golf Club, Kohat (6 Km). |
Kohat PKHA |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 294.598 | 291.588 | 49 | 49 | 24.5 | 0 | 291.588 | 0 | 100% |
99% July - 2018 |
Length 6 Km - NGC embankment, sub grade, sub base (1+300 to 2+600) completed. Structure work (6 Nos slab culverts) in progress. |
No Image |
858 (OG) |
191544-180358 - Construction of Doctor Hostel at AHQ Parachinar & THQ Sadda in District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 10 | 50 | 36.868 | 36.868 | 9.156 | 19.156 | 0 | 100% |
32% December - 2020 |
2 Units.
1- Work order issued.
2- Work in progress. |
No Image |
858 (OG) |
191544-180358 - Construction of Doctor Hostel at AHQ Parachinar & THQ Sadda in District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 10 | 50 | 36.868 | 36.868 | 9.156 | 19.156 | 0 | 100% |
32% December - 2020 |
2 Units.
1- Work order issued.
2- Work in progress. |
No Image |
858 (OG) |
191544-180358 - Construction of Doctor Hostel at AHQ Parachinar & THQ Sadda in District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 10 | 50 | 50 | 12 | 9.156 | 19.156 | 0 | 100% |
32% October - 2020 |
2 Units.
1- Work order issued.
2- Work in progress. |
No Image |
858 (OG) |
191544-180358 - Construction of Doctor Hostel at AHQ Parachinar & THQ Sadda in District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 10 | 50 | 50 | 12 | 9.156 | 19.156 | 0 | 100% |
32% September - 2020 |
2 Units.
1- Work order issued.
2- Work in progress. |
No Image |
858 (OG) |
191544-180358 - Construction of Doctor Hostel at AHQ Parachinar & THQ Sadda in District Kurram. [MA] |
Kurram |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 59 | 10 | 50 | 50 | 0 | 0 | 10 | 0 | 100% |
17% August - 2020 |
2 Units.
1- Work order issued.
2- Work in progress. |
No Image |
Pages : 1 2 |