Code | Scheme Name | District of Location | Commen. | Comple. | PC - I Status | Status Date |
Where Pending |
Cost Orignnal / Revised |
PFY Expenditure | Original Alloc. |
Revised Alloc. |
Releases | Expenditure | Acc. Expenditure | Throw Forward | Targets | Achievements | Remarks | Images |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 03-11-16 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- December - 2017 |
Barracks - foundation in progress. Site handed over on 01/12/2017. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 03-11-16 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- September - 2017 |
Work order issued. Site not yet handed over. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 03-11-16 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- August - 2017 |
Work order issued. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
- | - | - | 03-11-16 | - | 152.549 | 0 | 0 | 0 | 0 | 0 | 0 | 152.549 | - |
- July - 2017 |
Tender approval under process. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- November - 2017 |
Work started. Site handed over on 01/12/2017. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- October - 2017 |
Work order issued. Site not yet handed over. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 10.5 | 10.5 | 10.5 | 10.5 | 10.5 | 142.049 | 7% |
7% June - 2018 |
Barracks - raft and foundation in progress. |
No Image |
Bannu | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 10.5 | 10.5 | 10.5 | 10.5 | 10.5 | 142.049 | 7% |
7% May - 2018 |
Barracks - raft and foundation in progress. Demand Rs.20 m. |
No Image |
Bannu | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 7.5 | 7.5 | 145.049 | 5% |
5% April - 2018 |
Barracks - raft and foundation in progress. Demand Rs.20 m. |
No Image |
Bannu | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 7.5 | 7.5 | 145.049 | 5% |
5% March - 2018 |
Barracks - foundation in progress. Demand Rs.20 m. |
No Image |
Bannu | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 7.5 | 7.5 | 145.049 | 5% |
5% February - 2018 |
Barracks - foundation in progress. Site handed over on 01/12/2017. |
No Image |
Bannu | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Bannu |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.549 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 145.049 | 5% |
- January - 2018 |
Barracks - foundation in progress. Site handed over on 01/12/2017. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
- | - | - | 03-11-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- December - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
- | - | - | 03-11-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- September - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
- | - | - | 03-11-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- August - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
- | - | - | 03-11-16 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- July - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- November - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- October - 2017 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- June - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- May - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- April - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- March - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- February - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Chitral |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | - |
- January - 2018 |
PC-I/DCE for Rs.23.330 m sent to Suptt Distt Jail Chitral on 20/11/2014. AA not yet received. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
15-05-17 | - | - | 03-11-16 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% December - 2017 |
Work upto DPC level completed. Rs.30 m demanded. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
15-05-17 | - | - | 03-11-16 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% September - 2017 |
Work upto DPC level completed. Rs.30 m demanded. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
15-05-17 | - | - | 03-11-16 | - | 152.728 | 13.5 | 10 | 10 | 10 | 0 | 13.5 | 129.228 | 15% |
9% August - 2017 |
Work in foundation in progress. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
15-05-17 | - | - | 03-11-16 | - | 152.728 | 13.5 | 0 | 0 | 0 | 0 | 13.5 | 139.228 | - |
9% July - 2017 |
Work in foundation in progress. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% November - 2017 |
Work upto DPC level completed. Rs.30 m demanded. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% October - 2017 |
Work upto DPC level completed. Rs.30 m demanded. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% June - 2018 |
Column upto roof level. |
No Image |
DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% May - 2018 |
Column upto roof level. Rs.10 m demanded. |
No Image |
DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% April - 2018 |
Column upto roof level. Rs.10 m demanded. |
No Image |
DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% March - 2018 |
Column upto roof level. Rs.10 m demanded. |
No Image |
DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% February - 2018 |
Column upto roof level. Rs.30 m demanded. |
No Image |
DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
D.I.Khan |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 152.728 | 13.5 | 10 | 10 | 10 | 10 | 23.5 | 129.228 | 15% |
15% January - 2018 |
Work upto DPC level completed. Rs.30 m demanded. |
No Image |
1) DI.Khan | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
- | - | - | 03-11-16 | - | 123.961 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 116.461 | 6% |
- December - 2017 |
Layout given. Site not yet handed over. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
- | - | - | 03-11-16 | - | 123.961 | 0 | 0 | 0 | 0 | 0 | 0 | 123.961 | - |
- September - 2017 |
Work orded issued. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
- | - | - | 03-11-16 | - | 123.961 | 0 | 0 | 0 | 0 | 0 | 0 | 123.961 | - |
- August - 2017 |
Tender approval under process. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
- | - | - | 03-11-16 | - | 123.961 | 0 | 0 | 0 | 0 | 0 | 0 | 123.961 | - |
- July - 2017 |
Work order issued. |
No Image |
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 55.941 | 0 | 0 | 0 | 0 | 55.941 | 4.08 | - |
93% December - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 55.941 | 0 | 0 | 0 | 0 | 55.941 | 4.08 | - |
93% December - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.961 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 116.461 | 6% |
- November - 2017 |
Work order issued. Site not yet handed over. |
No Image |
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.961 | 0 | 7.5 | 7.5 | 7.5 | 0 | 0 | 116.461 | 6% |
- October - 2017 |
Work order issued. Site not yet handed over. |
No Image |
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 0 | 0 | 0 | 0 | 0 | 0 | 60.021 | - |
- October - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 0 | 0 | 0 | 0 | 0 | 0 | 60.021 | - |
- September - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 0 | 0 | 0 | 0 | 0 | 0 | 60.021 | - |
- August - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
80643-Upgradation of 10 BHUs to RHCs in Khyber Pakhtunkhwa, on need basis. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 60.021 | 0 | 0 | 0 | 0 | 0 | 0 | 60.021 | - |
- July - 2020 |
Completed & H/O (1 unit). |
No Image |
BHU Village Kangra PK-51 | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.961 | 0 | 9.775 | 9.775 | 9.775 | 9.775 | 9.775 | 114.186 | 8% |
8% June - 2018 |
SS in progress. |
No Image |
Central Prison Haripur | |||||||||||||||||||
725 (OG) |
140205-F/S & Construction of Admin Blocks and Barracks for Prison Security Force (Watch & Ward Staff) in Khyber Pakhtunkhwa. |
Haripur |
30-11--1 | 30-11--1 | - | 30-11--1 | - | 123.961 | 0 | 10.07 | 10.07 | 10.07 | 9.775 | 9.775 | 113.891 | 8% |
8% May - 2018 |
Upto DPC level. Demand Rs.15 m. |
No Image |
Central Prison Haripur | |||||||||||||||||||