Progressive Review for the month(s) of : January - 2019, January - 2021, February - 2019, February - 2021, March - 2019, March - 2021, April - 2019, April - 2021, May - 2021, July - 2018, July - 2020, August - 2020, September - 2018, September - 2020, October - 2020, November - 2018, December - 2018, December - 2020,

Showing Page Number : 1 of 2

Code Scheme Name District of Location Commen. Comple. PC - I Status Status
Date
Where
Pending
Cost
Orignnal / Revised
PFY Expenditure Original
Alloc.
Revised
Alloc.
Releases Expenditure Acc. Expenditure Throw Forward Targets Achievements Remarks Images
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
December - 2018
Work order issued.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
Work order issued.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
November - 2018
Work order issued.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
April - 2019
Work in progress.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
Work in progress.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
March - 2019
Work in progress.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
February - 2019
Work in progress.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Abbottabad
30-11--1 30-11--1 - 30-11--1 - 0 0 0 0 0 0 0 0 - -
January - 2019
Work in progress.
No Image
1) Construction of Dumail Kutli road Abbottabad
2) Construction of Treda Danna road Abbottabad
3) Construction of Topla Chajer road Abbottabad
4) Road work in village Kiala Uc Garhi Phulgraan
5) Road work Mohallah Guistan village Sajwal
6) Road work Mohallah Qais Khan Chumnaka
7) Road work Masah Gali to Kangar Gali
8) Road work Chando Maira road
9) Road work Abid Shaheed road Mohallah Ahmed Abad Hajia Gali
10) Road work for Nagri Tarli Makol Pain road
11) Road work for winding of road Nolotha to Karmati
12) Road work for widening to Ghora road
13) Road work for construction of road Hirlan Uc Nara
14) Road work for construcion of road Hirlan and and Mohallah Zohra and Nala for Jandar
15) Road work Karhaki Danna road Chainsa
16) Slab and PCC road from Mansehra road Karim Pura to Seena Liboratory UC Central Urban Abbottabad
17) PCC road with sewerage line at Jogan UC Nawanshehr Abbottabad
18) Pavement of streets, RW and sewerage line Metatal UC Mir Pur
19) Pavement of streets,RW and sewerage line Banda Dilazak UC Sheikhulbandi
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
December - 2018
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
November - 2018
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
November - 2018
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
April - 2019
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
March - 2019
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
March - 2019
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
February - 2019
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Bannu
30-11--1 30-11--1 - 30-11--1 - 34 0 0 0 0 0 0 34 - -
January - 2019
50% work completed.
No Image
1) Construction of shingle road in UCs Takhti Khel and Baka Khel (11 Nos) PK-72, Bannu
2) Construction of 10 Nos Bridges in UCs Takhti Khel, Baka Khel,  Jani Khel and Mohand Khel PK-72, Bannu
3) Construction of culverts in Ucs Baka Khel, Jani Khel, Takhti Khel and Haved, Bannu
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
December - 2018
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
November - 2018
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
November - 2018
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
April - 2019
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
March - 2019
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
March - 2019
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
February - 2019
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Battagram
30-11--1 30-11--1 - 30-11--1 - 46.2 18.536 1.257 1.257 1.257 1.076 19.612 26.407 43% 42%
January - 2019
Work in progress.
No Image
1) Construction of Maddrassa Jamia Usmania at Shiek-ul-Quran Colony, Neli Shang
2) Improvement & Construction of Kotwal, Korkan, Bagran, Daboona Road UC Tarand
3) Construction & Improvement Lammi Sarmast Road to Khet Khachri Road UC Rajdhari
4) Construction of Shingle road Nara UC Thakot
5) Widening & PCC Injobala road UC Peshora
6) Construction of Shingle road landai Tangai and Shagai UC Peshora
7) Construction of Chamsaidan road UC Koza Banda
8) Construction of Bajmira Totya Khan road UC Bania
9) Construction of Banjo Ajmira Lalzada Kohistani Korona road UC Ajmira
10) Construction of Mairi Tatoot road UC Batamori
11) Construction of Landa Rajmira road UC Batamori
12) Construction of Qalae Colony road Paimal Sharif & PCC in UC Paimal Sharif
13) Construction of Dabri Khwaja road UC Paimal Sharif
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
December - 2018
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
November - 2018
Work order issued (PK-17 and PK-18).
No Image
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
November - 2018
Work order issued (PK-17 and PK-18).
No Image
664
(OG)
150980-Construction of Sarwar Abad Umarzai Road and Road from Shakh No.4 to Shakh No.5 via Zarbab Ghari Maira Umarzai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 188.669 73.493 0.001 0.001 0.0005 0 73.493 115.175 39% 39%
September - 2018
6.5 Km - 3 Km asphalt completed.
No Image
Charsadda
664
(OG)
150980-Construction of Sarwar Abad Umarzai Road and Road from Shakh No.4 to Shakh No.5 via Zarbab Ghari Maira Umarzai, District Charsadda.
Charsadda
30-11--1 30-11--1 - 30-11--1 - 188.669 73.493 0.001 0.001 0.0005 0 73.493 115.175 39% 39%
July - 2018
6.5 Km - 3 Km asphalt completed.
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
April - 2019
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
March - 2019
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
March - 2019
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
February - 2019
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Charsadda
30-11--1 30-11--1 - 30-11--1 - 53 21.033 0 0 0 0 21.033 31.967 - 40%
January - 2019
Work order issued (PK-17 and PK-18).
No Image
Charsadda
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 0 0 0 0 2.695 42.305 - 6%
December - 2018
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 0 0 0 0 2.695 42.305 - 6%
November - 2018
Work started.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 0 0 0 0 2.695 42.305 - 6%
November - 2018
Work started.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 3 3 3 4.031 6.726 39.305 13% 15%
April - 2019
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 3 3 3 1.942 4.637 39.305 13% 10%
March - 2019
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 3 3 3 1.942 4.637 39.305 13% 10%
March - 2019
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 0 0 0 0 2.695 42.305 - 6%
February - 2019
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Mardan
HW
30-11--1 30-11--1 - 30-11--1 - 45 2.695 0 0 0 0 2.695 42.305 - 6%
January - 2019
Work in progress.
No Image
1) Construction of Baghechi Dheri Iltaf road (1.30 Km) PK-25
2) Construction of Check Hoti Bara road (0.7 Km) PK-25
3) Construction/BT of road Ameen Killi Bakri Banda UC Maho Dheri (0.675 Km) PK-24
4) Construction/BT of road Bagh Killi UC Maho Dheri (0.35 Km) PK-24
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Provincial
30-11--1 30-11--1 - 30-11--1 - 7000 0 100 100 0 0 0 0 - -
December - 2018
No Image
664
(OG)
191419-190336 - Establishment of District level food department offices in Merged Areas [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 16.013 5 0 0 0 0 5 0 - -
December - 2020
No Image
664
(OG)
191419-190336 - Establishment of District level food department offices in Merged Areas [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 16.013 5 0 0 0 0 5 0 - -
December - 2020
No Image
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Provincial
30-11--1 30-11--1 - 30-11--1 - 7000 0 100 100 0 0 0 0 - -
November - 2018
No Image
664
(OG)
170359-District Development Initiatives (List of schemes at Annex-IV).
Provincial
30-11--1 30-11--1 - 30-11--1 - 7000 0 100 100 0 0 0 0 - -
November - 2018
No Image
664
(OG)
191419-190336 - Establishment of District level food department offices in Merged Areas [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 16.013 5 0 0 0 0 5 0 - -
October - 2020
No Image
664
(OG)
191419-190336 - Establishment of District level food department offices in Merged Areas [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 16.013 5 0 0 0 0 5 0 - -
September - 2020
No Image
664
(OG)
191419-190336 - Establishment of District level food department offices in Merged Areas [MA]
Provincial
30-11--1 30-11--1 - 30-11--1 - 16.013 5 0 0 0 0 5 0 - -
August - 2020
No Image